Original PDF page 12, section 1. The text section number identifies this passage in the reader.

       EROSION AND SEDIMENT CONTROL NOTES
       THE FOLLOWING NOTES AND DETAILS PROVIDE INFORMATION ON THE CONTROLS AND
                                                                                                                                                                             EROSION AND SEDIMENT                                                                                                                                   SEDIMENT FENCE CONSTRUCTION NOTES
                                                                                                                                                                                                                                                                                                                                    1.      SEDIMENT FENCE TO BE INSTALLED ALONG                             WHICH CASE 3.0m MAX. SPACING.
       PROCEDURES THAT ARE TO BE IMPLEMENTED AS PART OF THE EROSION AND SEDIMENT
       CONTROL PLAN (E&SCP). THESE MEASURES ARE CONSIDERED SUFFICIENT TO ENSURE
       THE EROSION AND SEDIMENT CONTROL STANDARD WILL BE MET, GIVEN THE SITE
                                                                                                                                                                               CONTROL DETAILS                                                                                                                                              A LINE OF CONSTANT GROUND ELEVATION
                                                                                                                                                                                                                                                                                                                                            WHEREVER PRACTICAL.
                                                                                                                                                                                                                                                                                                                                                                                                     4.      FENCE ‘RETURNS’ SHALL BE INSTALLED AT
                                                                                                                                                                                                                                                                                                                                                                                                             MAXIMUM 20m SPACING IF FENCE IS
                                                                                                                                                                                                                                                                                                                                       2.   BOTH ENDS OF THE SEDIMENT FENCE TO                               INSTALLED ALONG THE CONTOUR,
       CHARACTERISTICS, PROPOSED DEVELOPMENT AND CONTROL MEASURES.                                                                                                                                                                                                                                                                          EXTEND UP THE SLOPE AT LEAST 1.0m.                               OTHERWISE 5 TO 10m MAXIMUM SPACING.
                                                                                                                                                                                                                                                                                                                                       3.   SUPPORT POST TO BE SPACED A MAXIMUM                      5.      MINIMUM 4 STAPLES OR TIE WIRES PER
       CONSTRUCTION MANAGEMENT PLAN                                                                                                                      ALL EROSION AND SEDIMENT IN ACCORDANCE WITH IECA MANUAL                                                                                                                            2.0m UNLESS THE FENCE IS SUPPORTED BY                            STAKE.

       OBJECTIVE/TARGET
                                                                                                                                                                    FOR EROSION AND SEDIMENT CONTROL                                                                                                                                        A TOP WIRE OR WIRE MESH BACKING, IN

       TO ENSURE THAT:
       (A) STORMWATER QUALITY LEAVING THE SITE IS OF ACCEPTABLE STANDARDS                                                                                                                                                                                                                                                                                                                     STAPLE/TACK                                  FABRIC B
       (<50MG/L TSS AND <75 NTU).
       (B) EROSION AND SEDIMENTATION DURING CONSTRUCTION IS MINIMISED.                                                                                                                                                                                                                                                       FABRIC

       THE ABOVE OBJECTIVES ARE TO BE ACHIEVED BY COMPLYING WITH THE FOLLOWING                                                                                                       ‘RETURNS’ PLACED AT 20 M SPACING (MAX.) IF FENCE IS
       REGULATIONS AND GUIDELINES:                                                                                                 3m (MAX.) WITH WIRE BACKING                       LOCATED ALONG THE CONTOUR, OTHERWISE 5 TO 10m
            ·        EPACT 1994 AND RELEVANT POLICES.                                                                                     OTHERWISE 2m (MAX.)                        DEPENDING ON SLOPE
            ·        INSTITUTION OF ENGINEERS SEDIMENT AND EROSION CONTROL GUIDELINES.                                                                                                                                                                                                                                            BACK FILL                                                      FABRIC A
            ·        IECA'S BEST PRACTICE EROSION & SEDIMENT CONTROL                                                                                                                                                                            1.5m (MIN.)                                                                                                                                                          SAFETY CAP
                                                                                                                   DIRECTION OF FLOW
       MANAGEMENT STRATEGY                                                                                                                                                                                                                                                                                                                                                      SUPPORT POST OPTION 1
       THE SITE FOREMAN WILL BE RESPONSIBLE FOR:                                                                                                                                                                                                                                                                                                                                1500mm² HARDWOOD STAKE
          ·    IDENTIFYING AND CHECKING STORMWATER LAND FLOWS.
                                                                                                                                                                                                                                                                                                                                            SOIL
          ·    PROVIDE BARRIERS AND OTHER MEASURES TO PREVENT STORMWATER FLOWS                                                                                                                                                                                                                                                                                                                                 SUPPORT POST OPTION 2
               OVER EMBANKMENTS AND SEDIMENTS INTO EXISTING GULLY PITS.                                                                                                                                                                                                                                                                                                                                           1.5kg/m STEEL PICKET

       TASKS/ACTION PRE-CONSTRUCTION                                                                                                                                                                                                                                                                         SEDIMENT FENCE                                                                        SEDIMENT FENCE
       BEFORE CONSTRUCTION ACTIVITIES BEGIN, THE FOLLOWING MEASURES NEED TO BE                                                                                                                                                                                                                           ANCHORING BASE OF FABRIC
       IMPLEMENTED TO MINIMIZE DISTURBANCE AND ADVERSE WATER QUALITY IMPACTS.
                                                                                                                                                                                                                                                                                                                                                                                                    JOINING FABRIC
          ·   SEDIMENT FENCES ARE TO BE CONSTRUCTED AT THE TOP OF EMBANKMENTS                                                                                                                                                                                                                                          NOT TO SCALE                                                                  NOT TO SCALE
              AND AT THE BASE OF FILL EMBANKMENTS.
          ·   DIVERSION BANKS TO BE CREATED AT THE UPSTREAM BOUNDARY OF                                                                                                                                                    ALL SUPPORT POSTS PLACED
              CONSTRUCTION ACTIVITIES TO ENSURE UPSTREAM RUNOFF IS DIVERTED                                                                                                                                                DOWN-SLOPE OF FABRIC                                                                                                                                                      TEMPORARY ENTRY/
              AROUND ANY AREAS TO BE EXPOSED. CATCH-DRAINS AT THE DOWNSTREAM                                       FABRIC
                                                                                                                   BURIED                                                                                                                                                                    CONSTRUCTION SITE                                     CATTLE GRID 3.0m NOM WIDTH                        EXIT CONSTRUCTION NOTES
              BOUNDARY OF CONSTRUCTION ACTIVITIES SHOULD ALSO BE CREATED                                                                                                                                                                                                                                                       5m                  SET 300mm ABOVE GROUND
                                                                                                                   200mm                                               SEDIMENT FENCE FABRIC, NOT                                                                                                                            MIN                                                                     1.      STRIP THE TOPSOIL, LEVEL THE SITE AND




                                                                                                                                                                                                                                                                                                   NOM
              (WHEREVER POSSIBLE) TO ENSURE ANY SEDIMENT-LADEN RUNOFF IS




                                                                                                                                                                                                                                                                                                   100
                                                                                                                                                                       FILTER CLOTH OR SHADE CLOTH                                                                                                                                                                                        T                  COMPACT THE SUBGRADE.
              CONTAINED AND DIRECTED TOWARD TREATMENT AREAS AND NOT PERMITTED                                                                                                                                                                                                                                                                                                          EN
                                                                                                                                                                                                                                                                                                                                                                                    NM                2.     COVER THE AREA WITH NEEDLE-PUNCHED
              TO FLOW ONTO DOWNSTREAM UNDISTURBED AREAS. DIVERSION BANKS SHOULD                                                                                                                                                                                                                                                                                               A LIG
                                                                                                                                                                                                                                                                                                                                                      10                   TY                                GEOTEXTILE.
              BE CONSTRUCTED APPROXIMATELY ALONG CONTOURS TO MINIMIZE SCOUR                                                                                                                                                                                                                                                                        MIN m                ER
                                                                                                                                                                   INSTALLATION OF SEDIMENT FENCE                                                                                                                                                                    OP                               3.     CONSTRUCT A 200mm THICK PAD OVER
              ALONG THE DRAINS.                                                                                                                                                                                                                                                                                                                                   PR            EL
                                                                                                                                                                                                                                                                                  GEOFABRIC FABRIC,                                                                         NN                               THE GEOTEXTILE USING ROAD BASE OR
          ·   SILT FENCES AND SAND BAGS WILL BE PLACED ALONG CATCH DRAINS TO SLOW                                                                                                   NOT TO SCALE                                                                                                                                                                          HA




                                                                                                                                                                                                                                                                                                             300
                                                                                                                                                                                                                                                                                  BIDUM A34 OR SIMILAR                                                                & C          Y                         30mm AGGREGATE.
              FLOW, REDUCE SCOUR, MINIMIZE SEDIMENT FROM RUNOFF.                                                                                                                                                                                                                                                                                                   RB          WA
                                                                                                                                                                                                                                                                                                                                                                KE          AD                        4.     ENSURE THE STRUCTURE IS AT LEAST
          ·   STRATEGICALLY PLACE CHECK DAMS AROUND GULLY PITS. DESIGNATION OF                                                                                                                                                                                                                                                                                           RO
                                                                                                                   FILTER SOCKS                                                                                                                                                                                                                    3 mIN              W                                      15m LONG OR TO BUILDING ALIGNMENT
              AREAS FOR PLANT AND MATERIAL STORAGE.                                                                                                                                                                                                                                                                                                  M             NE                                        AND AT LEAST 3m WIDE.
                                                                                                                   OVERLAP ONTO KERB                                                                                                                                                                                                                            OR
          ·   DESIGNATION AND MARKING OF TRANSPORT ROUTES ACROSS UNDISTURBED                                                                                                                                                                                                                                                                                 G,                                       5.     WHERE SEDIMENT FENCE JOINS ONTO
              PORTIONS OF THE SITE TO MINIMIZE UNNECESSARY VEGETATION DISTURBANCE.                                                                                                                                                                                                                                                                     I STIN
                                                                                                                                                                                                                                                                                  RUNOFF TO BE DIRECTED TO A SEDIMENT                              EX                                                        THE STABILISED ACCESS, CONSTRUCT A
          ·   EDUCATION OF SITE PERSONNEL TO THE SEDIMENT AND EROSION CONTROL                                                                                                                                                                                                     TRAP. REFER STANDARD DRAWING DS-302.                                                                                       HUMP OR GRATE IN THE STABILISED
              MEASURES IMPLEMENTED ON SITE.
                                                                                                                     SEDIMENT                                                                                                                                                                                                                                                                                ACCESS TO DIVERT WATER TO THE
       TASKS/ACTIONS DURING CONSTRUCTION                                                                                 POND                                                                                                                                                                              TEMPORARY ENTRY/EXIT                                                                              SEDIMENT FENCE.
       MEASURES TO MITIGATE WATER QUALITY IMPACTS DURING CONSTRUCTION.
         ·   CONSTRUCTION ACTIVITIES BE CONFINED WITHIN THE NECESSARY
             CONSTRUCTION AREA(S)
         ·   INSTALLATION OF SILT FENCES DOWNSTREAM OF DISTURBED AREAS. SILT                                       RUN-OFF                                                                                                                                               RUNOFF
             FENCES SHOULD BE LOCATED CONTINUOUSLY ALONG CONTOURS AND SHOULD                                                                                                          1m (MAX.) ON                                                                                                 FORMED TOP WIDTH                                                                                  CATCH DRAIN CONSTRUCTION
             TREAT AREAS LESS THAN 0.6 HA. PER 100M OF SILT FENCE.                                                                                                                    PUBLIC ROADS                                                                                                                                                                                                   NOTES
         ·   WEEKLY INSPECTION AND MAINTENANCE OF SILT FENCES, SEDIMENT BASINS                                                                                                                                                                                                                                                                                                                       1.      EXCAVATE THE DIVERSION CHANNEL
                                                                                                                                                                                                                                                                                                            150mm                                     2 (MIN.)
             AND OTHER EROSION CONTROL MEASURES. CHECK FENCES AFTER RAINFALL                                                                                                                                                                                                                                                                                                                                 REMOVING ALL DEBRIS
                                                                                                                                                                                                                                                                                                             (MIN.)
             EVENTS AND REMOVE COLLECTED MATERIAL WHEN FENCE IS 50% FULL.                                                                                                                                                                                                                                                                                                                            2.      ENSURE THE DRAIN INVERT MUST FALL
                                                                                                                                                              BYPASS                                                                                                                                                                                             1
             REPLACEMENT OF ANY DAMAGED EQUIPMENT SHOULD BE PERFORMED                                                                                                                                                                                                                                                                                                                                        10cm EVERY 10m FOR EACH 1% OF
                                                                                                                                                              FLOW
             IMMEDIATELY.                                                                                                                                                                                                                                                                                                                                                                                    CHANNEL GRADIENT
         ·   RETAIN SITE VEGETATION WHERE POSSIBLE AND SUITABLE.                                                                                                                                                                                                                                                                                                                                     3.      ENSURE THE SIDES OF THE CUT DRAIN
         ·   PROGRESSIVE RE-VEGETATION OF CUT AND FILL AREAS AND FILL BATTERS WITH                                              (A) ON-GRADE KERB INLET SEDIMENT TRAP
                                                                                                                                                                                                                                                                                                                                                                                                             ARE NO STEEPER THAN 1.5:1 (H:V) SLOPE
             TWO GRASS SPECIES IF SEEDING.                                                                                                                                                                                                                                                                                                                                                                   AND TEH EMBANKMENT FILL SLOPES ARE
         ·   MULCHING AND RETENTION OF VEGETATION AND TOPSOIL FOR FINAL SITE                                                                                                                                                                                                                                                                                                                                 NO STEEPER THAN 2:1
             REHABILITATION AND LANDSCAPING WORKS.                                                                                                                                                                                                                                                                                                                                                   4.      ENSURE THE DRAIN DISCHARGES TO A
         ·   AIM FOR 60% COVERAGE WITHIN 20 DAYS AND 70% WITHIN 6 WEEKS                                                                                                                                                                                                                                  NON-DISPERSIVE SUBSOIL
                                                                                                                                                                                      FILTER SOCKS MAY NEED TO FULLY SURROUND THE INLET TO                                                                                                                                                                   STABLE OUTLET
         ·   RE-VEGETATION AND LANDSCAPING OF REMAINING EXPOSED AREAS USING THE                                                                                                       INTERCEPT SEDIMENT RUNOFF FROM THE ROAD AND VERGE                                                                                                                                                              5.      IF GEOTEXTILE LINED FOLLOW THE
             TOPSOIL AND ANY MULCHED VEGETATION RETAINED FROM INITIAL SITE                                                   PVC PIPE                                                                                                                                                                                                                                                                        METHOD OD INTSALLATION PROCEDURES
             CLEARING. VEGETATION SHOULD BE WATERED AND MAINTAINED UNTIL IT IS                                               SPACERS                                                                                                                                         (A) PARABOLIC CATCH DRAIN WITH DOWN-SLOPE BANK                                                                                  PROVIDED BY THE MANUFACTURER OR
             SUITABLY ESTABLISHED.                                                                                                                                                                                                                                                                                                                                                                           DISTRIBUTOR OF THE PRODUCT.
         ·   IF LANDSCAPING IS REQUIRED SPECIES TO BE USED SHOULD PREFERABLY BE                                                                                                                                                                                                                                                                                                                      6.      INSPECT THE DIVERSION CHANNEL
             NATIVE AND ENDEMIC TO THE AREA. REMOVAL/MANAGEMENT OF WEEDS.                                                                                                                                                                                                                                                                                                                                    WEEKLY AND AFTER ANY INCREASE OF
       PERFORMANCE INDICATORS                                                                                                                                                                                                                                     RUNOFF                                                                                                                                     FLOWS OR RAIN EVENTS. REPAIR ANY
                                                                                                                                                                                                                                                                                               FORMED TOP WIDTH                                                                                              SLUMPS, WHEEL TRACK DAMAGE OR
       THE SITE FOREMAN WILL CARRY OUT REGULAR CHECKS OF THE ONSITE SEDIMENT AND
                                                                                                                                                                                                                                                                                                                                                                                                             LOSS OFF FREEBOARD
       EROSION CONTROL MEASURES DURING CONSTRUCTION AND AFTER EVERY RAINFALL
                                                                                                                                                                                                                                                                                                                                                                                                     7.      ON COMPLETION OF THE CONSTRUCTION
       EVENT. THE CHECKS WILL INCLUDE THE FOLLOWING:                                                                                                                                                                                                                                                                                                 2 (MIN.)                                                WORK, REMOVE THE TEMPORARY
          ·    EROSION AND SEDIMENT FLOWS CHECKED AT THE BASE OF EMBANKMENTS.                                                                                                                                                                                                                                150mm
                                                                                                                                                                                                                                                                                                                                                                                                             DIVERSION CHANNEL. THE AREA IS TO BE
          ·    NO VISIBLE EVIDENCE OF INCREASED TURBIDITY DIRECTLY ATTRIBUTED TO                                                                                                                                                                                                                              (MIN.)                                             1                                           STABILISED AND REHABILITED
               CONSTRUCTION ACTIVITIES.                                                                                                                                                                                                                                                                                                                                                                      APPROPRIATELY.
          ·    NO VISUAL EVIDENCE OF SCOURING.                                                                                     FILTER SOCK
          ·    CONSTRUCTED CHECK DAMS TO BE INSPECTED DURING RAINFALL EVENTS TO
               ENSURE THEY ARE OPERATING CORRECTLY.                                                                                         GULLY GRATE WRAPPED IN NON-WOVEN                                    SIDE INLET REMAINS
                                                                                                                                            FILTER FABRIC (MINIMUM, BIDIM A34 OR                                OPEN
       FREQUENCY/DEADLINE                                                                                                                   EQUIVALENT)
            ·        MATERIAL STOCKPILES WILL BE INSPECTED REGULARLY TO CONFIRM THEIR
                     LOCATION IS NOT RESULTING IN THE GENERATION AND UNCONTROLLED                                                                                                                                                                                                                NON-DISPERSIVE SUBSOIL
                     TRANSPORT OF SEDIMENT.                                                                                                                    (B) SAG INLET SEDIMENT TRAP
            ·        INSPECTION OF EROSION AND SEDIMENT CONTROL MEASURES AND
                     STRUCTURES TO BE UNDERTAKEN AFTER EACH RAINFALL EVENT.                                                                                  KERB INLET SEDIMENT TRAPS                                                                                            (B) TRIANGULAR V-DRAIN WITH DOWN-SLOPE BANK
            ·        IF AREAS ARE BEING RE-VEGETATED FOLLOWING COMPLETION OF
                     CONSTRUCTION, THESE AREAS WILL BE INSPECTED WEEKLY TO CONFIRM THAT                                                                                                                                                                                                                                                                                                                       Check all dimensions before commencement of work.
                     VEGETATION IS BECOMING ESTABLISHED.                                                                                                                                                                                                                                                                                                                                                      Check Site boundary dimensions from the Title plans
                                                                                                                                                                                                                                                                                                                                                                                                              Check Building Boundary clearances by set out.
       REPORTING AND REVIEW                                                                                                                                                                                                                                                                                                                                                                                   Notwithstanding the information supplied on this drawing,
       RESULTS OF INSPECTIONS WILL BE REPORTED AS PART OF THE DEVELOPERS REGULAR                                                                                                                                                                                                                                                                                                                              the location, depth and extent of underground or overhead
                                                                                                                                                                                                                                                                                                                                                                                                              services are to be confirmed and protected on site by the
       REPORTS TO THE NOOSA SHIRE COUNCIL SITE INSPECTOR.
                                                                                                                                                                                                                                                                                                                                                                                                              contractor prior to commencement of works.

                                                                                                                                                  Approved
Checked -       CT                                                                                                                                                                                   Drawing title -                                          Project -    PROPOSED 1 INTO 3                                  Site -                                                                        Project No.     233467       Sheet No.              C142
Design -    SK            Drawn -   SK          D   24/03/2025   UPDATED PROJECT NAME                SK                                                                                              EROSION & SEDIMENT CONTROL                                            DEVELOPMENT                                        62 LAKE MACDONALD DRIVE,                                                      Digital Ref :
                                                                                                                                                                                                                                                                                                                                                                                                                            C142 EROSION & SEDIMENT
                                                                                                                                                                                                                                                                                                                                                                                                                            CONTROL DETAILS           Issue :       D
                                                C   14/03/2025   UPDATED LOT LAYOUT                  SK
Scales -    AS SHOWN                            B   20/09/2024   ISSUE FOR APPROVAL                  SK                                           COVEY ASSOCIATES PTY LTD   124 DUPORTH AVENUE      DETAILS                                                  Client -
                                                                                                                                                                                                                                                                           NOOSA COUNCIL                                      COOROY                                                                          This Document is copyright and shall not be copied
                                                A    10/01/24    ISSUE FOR CLIENT REVIEW             SK
                                                                                                                                                  ABN 59 137 305 992         PO BOX 16                                                                                                                                                                                                                        without written approval, nor shall it be used except
Document Stage -              APPROVAL                                                                                                            (07) 5443 7777             MAROOCHYDORE QLD 4558                                                                                                                                                                                                            for the Development and the Site Specified.
                                               Issue Date                      Description          By                                            [email protected]
       c:\12dS\data\12DSERVER\233467_2957\DWG Covey\OPW\Uncontrolled\C142 EROSION & SEDIMENT CONTROL DETAILS.dwg                                                                                                                                                                                                                                                                                            Plot 25 March 2025 - 5:27 PM

Used in these records

About this file

File size
17.5 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix A - Engineering Design Plans - 1 of 2.pdf · 17.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.