Council archive · source document
132938-1 Application for a minor change to a development approval (s78-PA) 2018-11-27 · 132008.1128.02
Attached to the e-mail Change to DA (Report, Existing Approval, Bushfire Technical Note, DA Form, Owners consent) - 132008.1128.02.
72. The fire-fighting demand on Unitywater’s water supply system from the development must not
exceed 15 30 litres per second.
80. Prior to the issue of any Development Permit for Operational Works amended plans for the
development must be submitted to and approved by Council, the amended plans must be
consistent with the ‘Masterplan’ prepared by RPS dated 18 October 2017, Plan Ref: 132938-01D.
6. MINOR CHANGE STATUS
The proposed change to the development approval is consistent with the definition of a ‘minor change’ under
the Act as demonstrated in Table 9 below:
Table 9 – Minor Change Test under the Act
Minor change means a change that – for a development approval –
(i) Would not result in substantially different Refer to Table 5 below which demonstrates the
development changes does not result in ‘substantially different
development’.
If a development application for the development, including the change, were made when the change
application is made would not cause –
(a) The inclusion of prohibited development in the The proposed changes do not include prohibited
application; or development in the application.
(b) Referral to a referral agency, other than to the Not applicable. There were referral agencies for the
chief executive, if there were no referral original development application.
agencies for the development application; or
(c) Referral to extra referral agencies, other than The original application was referrable to the
to the chief executive; or Department of Environmental and Resource
Management (DERM) for the following matters:
Vegetation clearing
Koala conservation
Wetlands
Conservation estate
If the application were remade at the time of this
change application being lodged, a referral to the
Department of Transport and Main Roads (DTMR)
would be required as an extra referral agency for the
following trigger:
Infrastructure related referral (State transport
infrastructure) for exceeding the thresholds
specified in Schedule 20 of the Planning
Regulation 2017 (the Regulation).
However DTMR is part of the chief executive and
therefore the changes remain definable as a ‘minor
change’.
132938-1 | Grasstree Court, Sunrise Beach: Minor Change | 3 December 2018 Page 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
132938-1 Application for a minor change to a development approval (s78-PA) 2018-11-27.pdfRelated documentApplication case desk ↗
About this file
- File size
- 6.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.