R5304: NOOSA RESOURCE RECOVERY CENTRE - STORMWATER MANAGEMENT PLAN
2 SITE DESCRIPTION
2.1. LOCATION AND OPERATIONS
The NRRC is located on Eumundi-Noosa Road, Doonan and undertakes a range of waste processing and resource
recovery operations over the site. A large portion of the site is finished landfill and has a vegetated surface. Activities
across the site include:
+ waste collection,
+ resource recovery,
+ concrete crushing/recycling,
+ green waste recovery and processing, and
+ oil and paint collection.
The site activities and disturbed areas, as of the 24 th July 2026 are illustrated in Figure 2.
Green Waste
Processing
Site Entry
HES Basin Concrete
Processing
Weighbridge
Resource
Recovery
HES Basin
Figure 2 – Aerial Photography and Disturbed Areas (Source: NearMaps, image date 24-06-26)
2.2. CLIMATE
The Bureau of Meteorology (BOM) provides average monthly rainfall data for Tewantin RSL Park (Gauging Station
040908 - the nearest site to Eumundi with monthly climate records). Based on this data, the average annual rainfall is
~1,610 mm. Rainfall has a distinctly seasonal pattern, with approximately 67 % of the annual average rainfall occurring
between December and May inclusive. The average monthly rainfall records are illustrated in Figure 3.
Environment. Engineering. Education. PAGE 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8 - Interim Stormwater Management Plan - TOPO.pdfRelated documentApplication case desk ↗
About this file
- File size
- 19.4 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.