Figure 3 – Treatment Plan
5.3.3.7 MUSIC Results
The resulting percentage based load reductions at the outlet are shown in Table 4 below together
with the Water Quality Objectives for the receiving waters.
Residual
Sources % Reduction Target %
Load
Total Suspended Solids (kg/yr) 7260 1360 81.2 80
Total Phosphorous (kg/yr) 14.8 4.06 72.6 60
Total Nitrogen (kg/yr) 103 50.2 51.4 45
Gross Pollutants (kg/yr) 745 0 100 90
Table 4 – Percentage Based Load Reduction Results
Excellence with Economy in Engineering 13
https://mpncnetau.sharepoint.com/sites/administration/shared documents/9000-9999/9900-
9999/9954/report/29-09-23 stormwater management plan_issue a.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.