Original PDF page 16, section 1. The text section number identifies this passage in the reader.
29 September 2023
4.6 Proposed Stormwater Quality Treatment Devices
4.6.1 Locations
The location of the proposed stormwater quality treatment device is shown on MPN Plan 9954-
DA03-DA06 attached in Appendix 2.
4.6.2 Device and Size
The device type and size are depicted on MPN Plan 9954-DA.08 attached in Appendix 2.
4.6.3 Operation
The bioretention basin operates by filtering runoff through densely planted surface vegetation,
then percolating the water through a sandy loam filter media with details as per MPN Plan 9954-
DA07 attached in Appendix 2. As the water is percolated through the soil, pollutants are captured
by fine filtration, adsorption and biological uptake.
4.6.4 Maintenance
For the initial maintenance of the bioretention basin it is important to remove weeds and debris,
with regular watering until plants are established and actively growing.
Watering is to be undertaken following the construction of the basin at the following frequency:
• Week 1 – 6, 5 times/week
• Week 6 – 10, 3 times/week
• Week 11 – 15, 2 times/week
If there is no rain, each plant should receive 2.5 – 5.0 litres of water per week during establishment
in the first 6 weeks (40mm/week).
Watering requirements to sustain healthy vegetation should be determined during ongoing
maintenance visits.
Detailed establishment techniques can be found in the Water By Design Construction and
Establishment Guidelines.
Inspections are also recommended following large storm events to check for scour and other
damage.
Maintenance of the bioretention basin will include:
• Routine inspections of surface profile to identify areas of sediment buildup, scour and
erosion or clogging of the filter media;
• Routine inspection of the overflow pits and under drains for blockages and litter buildup;
• Removal of sediment where it is smothering the basin vegetation; and
• Repair all basin damage due to scour or erosion by replacement of filter media and
vegetation.
Excellence with Economy in Engineering 15
https://mpncnetau.sharepoint.com/sites/administration/shared documents/9000-9999/9900-
9999/9954/report/29-09-23 stormwater management plan_issue a.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.