Earthworks Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: Sept 2020

Performance Outcomes                              Acceptable Outcomes                                 Solution1      Comments                                                          Council Use

                                                  register.                                                          verify whether the development falls on
                                                                                                                     land listed on the contaminated land
                                                                                                                     register.
 Haulage activity and amenity                     No acceptable outcome provided.                                    RO7
 PO7                                                                                                                 Haul routes from trucks used to transport
 Haulage of material to and from a site                                                                              fill/spoil and material to and from the site
 ensures—                                                                                                            will only use major roads as required.
(a) minimal disturbance to neighbouring                                                                              Alternatively, if there is no major road route
    properties and properties along the                                                                             to the site, haul trucks will use minor roads
    haulage route; and                                                                                               with the shortest, most direct
(b) Council’s road infrastructure including                                                                          route that will have the least amount of
    pavements is not adversely affected.                                                                             environmental impact. This will be clearly
                                                                                                                     documented in the Construction
                                                                                                                     Management Plan.
 Extent of earthworks                             AO8                                                                RO8
 PO8                                              All earthworks, including cut and fill batters,                    All earthworks will be contained within the
 The layout of the development provides           retaining walls and the like are contained                         subject site. Any minor earthworks
 adequate, clearly defined and easily             within the subject site.                                           undertaken external to the site will only be
 accessible—                                                                                                        undertaken after all approvals and/or
(a) on-site vehicle parking and                                                                                      consent is obtained from Council and
     manoeuvring areas; and                                                                                          neighbouring property owners.
(b) loading and manoeuvring areas for
     delivery and service vehicles.
 Sloping sites                                    AO9                                                                RO9
 PO9                                              Cut or fill is less than 1.5 metres in depth                       The proposal complies.
 On sloping sites development follows the         relative to the natural ground level.                   
 natural landform wherever practical and
 excavation or filling is minimal.
 Infrastructure protection                        No acceptable outcome provided.                                    R10
 PO10                                                                                                                Prior to construction the contractor will
 Earthworks and vehicular access do not                                                                              confirm the correct locations of all existing
 adversely impact on the capacity,                                                                                  services whether indicated or not on the
 operations and maintenance of existing                                                                              plans. The construction of the proposed
 infrastructure.                                                                                                     development will ensure the protection of
                                                                                                                     all existing services or public utilities.


1
    Solution:          Acceptable Solution                                                                                                                                                         Page 3 of 4
                A/S     Alternative Solution                             D:\JOBS\20-Jobs\20169 - 101 & 105 Eumundi Noosa Road, Noosaville\Civil\Reports\ESA\Working\Appendices\20169 - NSC Earthworks Code 2020.docx
                N/A     Not applicable to this proposal                                                                                                                                                   Job: 20169
                                                                                                                                                                                                         Rev:      0
Site Address: 101-105 Eumundi Noosa Road, Noosaville                                                                                                                                                  30/11/2020
Log in to download the original file

Engineering Services Report (Rev 2).pdf · 7.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.