   BULK EARTHWORKS NOTES                                                                                                                                                                                                                                                                                                                                          BUILDING EARTHWORKS NOTES
                                                                                                                                                                                                                                     SUBGRADE AREAS (CUT/FILL & PAVEMENT AREAS)
   1.CROSS REFERENCES                                                                                                                                                                                                                            F.      COMPACT AS PER THE COMPACTION & OMC NOTES BELOW, UNDER GEOTECHNICAL SUPERVISION, TO A                    1. GENERAL
   REFER TO THE FOLLOWING SUPPORTING INFORMATION FOR PROJECT SPECIFIC                                                                                                                                                                                    DEPTH NOT LESS THAN 150mm FOR CUT/FILL AREA AND 300mm FOR PAVEMENT AREAS.                                A.   REFER TO THE STRUCTURAL ENGINEER'S DRAWINGS FOR STRUCTURAL SLAB
   REQUIREMENTS                                                                                                                                                                                                                                                                                                                                                        THICKNESS AND FOUNDATIONS.
              A.        SURVEY - REAL SERVE, 06/09/2024                                                                                                                                                                              FILL                                                                                                                         B.   REFER TO ARCHITECT FOR ALL SETOUT, LEVELS, STEPS, FALLS ETC. TO SLABS.
              B.        GEOTECHNICAL REPORT - APOD SOIL TESTING PTY LTD, 11/11/2023                                                                                                                                                              G.      ALL FILL SHALL BE PLACED IN ACCORDANCE WITH SECTION 6 OF AS3798 AND TESTED IN ACCORDANCE
                                                                                                                                                                                                                                                         WITH SECTION 7 OF AS3798                                                                                 C.   THE CONTRACTOR IS TO CONFIRM BUILDING SETOUT WITH THE
              C.        ARCHITECTURAL DRAWINGS - RED DESIGN GROUP                                                                                                                                                                                                                                                                                                      SUPERINTENDENT PRIOR TO COMMENCEMENT OF EARTHWORKS,
                                                                                                                                                                                                                                                 H.      BACKFILL AND FILL IS TO BE COMPACTED IN 250mm MAXIMUM DEPTH LOOSE LAYERS
              D.        STRUCTURAL ENGINEERING DRAWINGS - BORNHORST & WARD                                                                                                                                                                                                                                                                                             INCLUDING LOCATION AND DEPTH OF ALL SLAB SET DOWNS.
                                                                                                                                                                                                                                                 I.      FILL BATTER SLOPES ARE TO BE OVERFILLED AND TRIMMED BACK TO THE FINISHED BATTER SLOPE
    2.DESIGN BASIS
    THE BULK EARTHWORKS DESIGN HAS BEEN BASED UPON THE FOLLOWING                                                                                                                                                                     COMPACTION & OMC
              A.        EARTHWORKS LEVELS TO BE ADJUSTED ON SITE BASED ON THE FINAL PAVEMENT DESIGN (TO BE                                                                                                                                       J.      COMPACT IN ACCORDANCE WITH THE FOLLOWING MINIMUM DENSITY RATIOS:
                        CONFIRMED BY SUBGRADE TESTING ON SITE - REFER ROADWORKS NOTES)                                                                                                                                                                    ·  RESIDENTIAL LOT FILL: 95% STD
                                                                                                                                                                                                                                                          ·   COMMERCIAL FILL: 98% STD                                                                                                                                                       REFER SLAB DRAWINGS
                                                                                                                                                                                                                                                          ·  BUILDING PADS: 100% STD                                                                                                                                                         FOR DETAILS
    THE BULK EARTHWORKS DESIGN AND LEVELS ARE A GUIDE ONLY AND EXCLUDE                                                                                                                                                                                    ·   SUBGRADE (EXCEEDING 300MM BELOW PAVEMENT): 95% STD                                                                                     1m MIN
              B.        BOX OUT FOR TOPSOILED AREAS (FINISHED SURFACE SHOWN)                                                                                                                                                                              ·   SUBGRADE (WITHIN 300mm OF PAVEMENT): 100% STD
              C.        DETAILED EXCAVATION (FOOTINGS, TRENCHING, SLAB SET DOWNS, LANDSCAPE AREAS, DEEP PLANTING,                                                                                                                                J.      MANAGE THE MOISTURE CONTENT OF THE MATERIAL AS SPECIFIED BY THE GEOTECHNICAL REPORT OR
                        ETC)                                                                                                                                                                                                                             GEOTECHNICAL ENGINEER                                                                                                 2
              D.        TEMPORARY WORKS (TEMPORARY BATTERS, WORKING PLATFORMS, RAMPS, RETAINING WALL
                        EXCAVATIONS ETC)                                                                                                                                                                                                                                                                                                                                 1
              E.        INTERFACE BETWEEN CUT / FILL AREAS; BATTERS FOR SITE REPLACEMENT MATERIAL
                                                                                                                                                                                                                                     TOLERANCES
                                                                                                                                                                                                                                                 K.      VERTICAL
                                                                                                                                                                                                                                                          ·   PAVEMENT SUBGRADES IN EARTH AND FILL: +0mm / -50mm
    3.BULK EARTHWORKS SITE MANAGEMENT                                                                                                                                                                                                                     ·   PAVEMENT SUBGRADES IN ROCK: +0mm / -75mm                                                                       BUILDING PLATFORM FILL                                          BULK EARTHWORKS LEVEL
    THE CONTRACTOR IS TO:                                                                                                                                                                                                                                 ·   ALL OTHER AREAS: +/-50mm PROVIDED AREA MATCHES ADJACENT CONSTRUCTION
              A.        ENGAGE A GEOTECHNICAL INSPECTION AND TESTING AUTHORITY (GITA) AS PER AS3798 TO SUPERVISE ALL                                                                                                                                      ·   WHERE PAVEMENT SUBGRADES ARE CONSTRUCTED LOWER THAN DESIGN LEVELS, INCREASE                                                                                                    DETAILED EXCAVATION
                        FILLING ACTIVITIES                                                                                                                                                                                                                    THE LOWER PAVEMENT LAYER THICKNESS TO ACHIEVE FINISHED SURFACE LEVELS
              B.        ENGAGE AN RPEQ GEOTECHNICAL ENGINEER TO UNDERTAKE GEOTECHNICAL SUPERVISION OF THE                                                                                                                                        L.      HORIZONTAL
                        EARTHWORKS AND ADVISE ON TREATMENT FOR:                                                                                                                                                                                           ·   ALL AREAS: +/-50mm PROVIDED AREA MATCHES ADJACENT CONSTRUCTION                                                             BUILDING PLATFORM FILL DETAIL
                          ·   UNSUITABLE MATERIALS                                                                                                                                                                                                                                                                                                                                       N.T.S
                          ·
                          ·
                              GROUND IMPROVEMENT TREATMENTS BELOW FILL AREAS
                              TEMPORARY WORKS (INCLUDING BUT NOT LIMITED TO BATTERS, DEEP TRENCHES ETC)
                                                                                                                                                                                                                                     6.SUPERVISION
              C.        NOTWITHSTANDING THE BULK EARTHWORKS LEVELS DOCUMENTED ON THE DRAWINGS, COORDINATE                                                                                                                                        A.      LEVEL 1 INSPECTION AND TESTING IS TO BE IMPLEMENTED ON THE SITE IN ACCORDANCE WITH AS3798
                        EARTHWORKS (BULK AND DETAILED) REQUIREMENTS BETWEEN ALL TRADES AND PROJECT DOCUMENTS.                                                                                                                                    B.      UNLESS NOTED OTHERWISE THE FREQUENCY OF TESTING IS TO BE IN ACCORDANCE WITH TABLE 8.1 OF
                        BUILDING PLATFORM SETOUT IS AS PER THE ARCHITECTURAL DRAWINGS                                                                                                                                                                    AS3798
              D.        COMPLY WITH ALL REGULATIONS CONCERNING WORK HOURS, WARNING SIGNS, FENCING OR SECURITY                                                                                                                                    C.      THE GITA IS TO UNDERTAKE CONTINUOUS INSPECTION AND TESTING AND IS TO PROVIDE A COMPLIANCE
                        AND EMISSIONS FROM THE SITE INCLUDING DUST, WATER, SILT, NOISE AND SMOKE AS REQUIRED TO MEET                                                                                                                                     CERTIFICATE IMMEDIATELY FOLLOWING COMPLETION OF EARTHWORKS
                        THE 'GENERAL DUTY OF CARE' UNDER THE ENVIRONMENTAL PROTECTION ACT                                                                                                                                                                      THE COMPLIANCE CERTIFICATE SHALL BE SIGNED BY A SUITABLY QUALIFIED AND EXPERIENCED




                                                                                                                                                                                                                                                                                                                                                                                                                                        EXTENT OF BULK
                                                                                                                                                                                                                                                           ·
              E.        MANAGE MATERIALS FOR FIRE ANTS AS PER THE BIOSECURITY ACT 2014




                                                                                                                                                                                                                                                                                                                                                                                                                                        EARTHWORKS
                                                                                                                                                                                                                                                               GEOTECHNICAL ENGINEER (RPEQ) AND SHALL STATE THE FOLLOWING:
              F.        IMPLEMENT EROSION AND SEDIMENT CONTROLS ON THE SITE                                                                                                                                                                                ·   ALL EARTHWORKS HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE DRAWINGS AND SPECIFICATION
              G.        MANAGE ACID SULFATE SOILS AS PER THE ASSMP                                                                                                                                                                                         ·   THAT FILL HAS BEEN PLACED AND COMPACTED TO THE MINIMUM DENSITY RATIOS DETAILED ON THE                                    FLEXIBLE PAVEMENT
              H.        PROTECT THE EXCAVATION FROM PONDING DUE TO SURFACE RUN OFF AND DISCHARGE FROM PIPED                                                                                                                                                    DRAWINGS AND SPECIFICATION
                        DRAINAGE SYSTEMS. SHOULD WATER ENTER THE EXCAVATION, IT SHALL BE REMOVED AS SOON AS                                                                                                                                                ·   THAT FILL MATERIAL COMPLIES WITH THE DRAWINGS AND SPECIFICATION
                        POSSIBLE. FILL OR PAVEMENT MATERIALS ARE NOT TO BE PLACED OVER THE EXCAVATION UNTIL THE                                                                                                                                                                                                                                                                                                                                                    FINISHED SURFACE LEVEL
                                                                                                                                                                                                                                                 D.      THE GITA IS TO MAINTAIN SITE RECORD REPORTS SUCH THAT THEY MAY BE PRESENTED AT THE REQUEST                                                                        0.150
                        MOISTURE CONTENT RETURNS TO A SIMILAR LEVEL AS THE NATURAL GROUND. THE EXCAVATION SHALL                                                                                                                                          FROM THE SUPERINTENDENT
                        BE REINSPECTED AND PROOF ROLLED




                                                                                                                                                                                                                                                                                                                                                                                                                                                                            .
              I.        FOR HIGHLY REACTIVE MATERIALS                                                                                                                                                                                                                                                                                                                                                                                                                           150mm TOPSOIL NOMINAL
                          ·   TAKE APPROPRIATE PRECAUTIONS TO PROTECT MATERIAL FROM BECOMING TOO MOIST OR FROM                                                                                                                       7.HOLD POINTS FOR BORNHORST & WARD INSPECTION                                                                                                           FINISHED SURFACE LEVEL                                                             UNLESS SPECIFIED
                              DRYING OUT                                                                                                                                                                                                         A.      PROVIDE A MINIMUM OF 48 HOURS NOTICE TO INSPECT THE FOLLOWING                                     AC.                                                                                                                  OTHERWISE ON THE
                          ·   LIMIT THE SIZE OF EXCAVATIONS SUCH THAT THEY CAN BE QUICKLY PROTECTED WHEN RAINFALL IS                                                                                                                                      ·   APPROVAL OF IMPORTED FILL TEST CERTIFICATES                                                                                                                                                                       LANDSCAPE PLANS.
                                                                                                                                                                                                                                                                                                                                                         BASE.
                              PREDICTED                                                                                                                                                                                                                                                                                                                                                                                                                      1
                                                                                                                                                                                                                                                                                                                                             UPPER SUBBASE.                                      EARTHWORKS LEVEL
              J.        MANAGE CUT / FILL / IMPORTATION / STOCKPILE REQUIREMENTS, SPOIL GENERATED FROM TRENCHING                                                                                                                     8.WITNESS POINTS FOR BORNHORST & WARD INSPECTION                                                                                                                                                                    1
                        ETC                                                                                                                                                                                                                      NIL                                                                                                                                                                                                     LOWER SUB BASE DEPTH TO BE
              K.        MANAGE TOPSOIL GENERATION ON SITE, REUSE FOR LANDSCAPING WHERE PROVEN SUITABLE AS PER THE                                                                                                                                                                                                                                                                                                                                        DETERMINED BY THE ENGINEER
                        LANDSCAPE SPECIFICATION, SPOIL EXCESS OFF SITE
                                                                                                                                                                                                                                     9.SUBMISSIONS                                                                                                                                                                                                       WITH KNOWN CBR TEST RESULTS
   LANDSCAPE CONTRACTOR SPECIFIC REQUIREMENTS                                                                                                                                                                                                    A.      PROVIDE THE FOLLOWING PRIOR TO PRACTICAL COMPLETION
                                                                                                                                                                                                                                                          ·   LEVEL 1 INSPECTION AND TESTING REPORT, AND RPEQ SIGNED COMPLIANCE CERTIFICATE                  SUBGRADE
              L.        COMPLETE DETAILED EXCAVATION AND FINAL CUT FOR ALL LANDSCAPED AREAS                                                                                                                                                                                                                                                                  MATERIAL.
              M.        MANAGE MATERIAL GENERATED FROM EXCAVATIONS AS DIRECTED BY THE MANAGING CONTRACTOR                                                                                                                                                 ·   A CONSOLIDATED RECORD OF IMPORTED FILL TESTING CERTIFICATES
                                                                                                                                                                                                                                                          ·   FIRE ANT BIO SECURITY INSTRUMENT PERMIT WHERE APPLICABLE
   BUILDER SPECIFIC REQUIREMENTS                                                                                                                                                                                                                                                                                                                                                    EARTHWORKS LEVELS UNDER FLEXIBLE PAVEMENT DETAIL
              N.        COMPLETE DETAILED EXCAVATION FOR ALL BUILDING AREAS (FOOTINGS, SLAB SET DOWNS,                                                                                                                              10. VARIATIONS                                                                                                                                  N.T.S.
                        STEPS, WORKING PLATFORM AREAS)                                                                                                                                                                                           A.       VARIATIONS ARISING FROM LATENT CONDITIONS REQUIRE THE FOLLOWING:
                                                                                                                                                                                                                                                           ·   REPORT FROM THE GEOTECHNICAL ENGINEER WITH RECOMMENDATIONS FOR REMEDIATION
                                                                                                                                                                                                                                                           ·   12D FORMAT SURVEY PRE AND POST REMEDIATION
    4.MATERIALS                                                                                                                                                                                                                                            ·   PAYMENT TO BE SOLID VOLUMES, COMPACTED IN PLACE ON SITE (TRUCK DOCKETS NOT ACCEPTED)
    GENERAL SITE WON FILL MATERIAL
              A.        SITE WON MATERIAL SUBJECT TO ACCEPTANCE (AND OR IMPROVEMENT) DIRECTED BY THE GEOTECHNICAL
                        ENGINEER
              B.        COMPLY WITH THE FOLLOWING:
                          ·   INORGANIC, NON-PERISHABLE WITH NO CONTAMINANTS SUCH AS WOOD, PLASTIC, BOULDERS OR OTHER
                              DELETERIOUS MATERIALS
                          ·   MAXIMUM PARTICLE SIZE OF 75mm
                          ·   NOT CONSIST OF SILTY SAND OR SANDY SILT MATERIALS. WHERE ENCOUNTERED, THESE ARE TO BE
                              SPOILED OFF SITE OR BLENDED UNDER GEOTECHNICAL SUPERVISION TO FORM A SUITABLE MATERIAL
              C.        TEST SITE WON FILL AT A RATE OF 1 SAMPLE PER SOURCE FOR EVERY 1000M3 / (SOLID) OR PART THERE OF
              D.        MATERIAL NOT COMPLYING WITH THE ABOVE IS DEEMED UNSUITABLE, AND SHALL BE SPOILED OFF SITE.

    GENERAL EARTHWORKS IMPORTED FILL                                                                                                                                                                                                                                                                                                                             1m MIN.                          1% FALL FREE           STRUCTURAL
              E.        COMPLY WITH THE FOLLOWING:                                                                                                                                                                                                                                                                                                                                                DRAINING U.N.O         SLAB
                         ·    4 DAY SOAKED CBR: 5.0%                                                                                                                                                                                                                                                                                                                                                                                                     DETAILED EXCAVATION
                         ·    WPI: <1200                                                                                                                                                                                                                                                                         BUILDING PLATFORM LEVEL
                         ·    PI%: >= 7%                                                                                                                                                                                                                                                                         BULK EARTHWORKS LEVEL
                         ·    MINIMUM % PASSING 0.075mm SIEVE: 15%                                                                                                                                                                                                                                                                                                                                                                                                                               REFER BULK
                         ·    EMERSON CLASS: >3                                                                                                                                                                                                                                                                                                                                                                                                                                    3519




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                 EARTHWORKS
                         ·
                         ·
                              MAXIMUM PARTICLE SIZE: 75mm
                              NON-REACTIVE CONTROLLED
                                                                                                                                                                                                                                           PROJECT SETOUT                                                                                                                                                                                                                                        DRAWINGS
                                                                                                                                                                                                                                                                                                                                                                                                                                               BUILDING PLATFORM FILL.
              E.        TEST IMPORTED FILL AT A RATE OF 1 SAMPLE PER SOURCE FOR EVERY 1000m3 (SOLID) OR PART THERE OF                                                                                                                                                                                                                                                                                                                          REFER SETOUT DETAIL FOR EXTENT.
                                                                                                                                                                                                                                           1.         ALL PROJECT SETOUT (HORIZONTAL AND VERTICAL) IS TO BE                                REFER BULK EARTHWORKS                                 SITE REPLACEMENT FILL
                                                                                                                                                                                                                                                      UNDERTAKEN BY THE CONTRACTOR FROM A DIGITAL SURFACE                                                                                        BULK EXCAVATION LEVEL                         REFER STRUCTURAL ENGINEERING DRAWINGS
    5.EXECUTION                                                                                                                                                                                                                                       MODEL (12D OR 3D-DWG) PROVIDED BY BORNHORST & WARD,                                         DRAWINGS                                                                                     FOR MINIMUM BUILDING PLATFORM FILL
    SITE PREPARATION                                                                                                                                                                                                                                  RELATIVE TO PERMANENT SURVEY MARKS OR OTHER SURVEY                                                                                                                                       THICKNESS. THICKNESS MAY VARY TO SUIT
              A.        ALL SITE PREPARATION IS TO BE CARRIED OUT IN ACCORDANCE WITH AS3798 “GUIDELINES ON                                                                                                                                            CONTROL PROVIDED BY THE PRINCIPAL. THE CONTRACTOR IS TO                                                                                                                                  BULK EARTHWORKS LEVELS.
                        EARTHWORKS FOR COMMERCIAL AND RESIDENTIAL DEVELOPMENTS” AND THE RECOMMENDATIONS OF                                                                                                                                            ALERT THE SUPERINTENDENT IF SUITABLE CONTROL IS NOT
                                                                                                                                                                                                                                                                                                                                                 REPLACEMENT FILL FOR BUILDING PLATFORM




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             J:\2023\23169\05_DRAWINGS\DRG\C0100.DWG
                        THE GEOTECHNICAL REPORT.                                                                                                                                                                                                      AVAILABLE.
              B.        MATERIAL DEEMED UNSUITABLE BY THE GITA IN AREAS TO BE FILLED SHALL BE DEALT WITH AS PER THE                                                                                                                        2.         CONTRACTOR IS TO CONFIRM TIE-IN LEVELS TO EXISTING                                         N.T.S
                        RECOMMENDATIONS FROM THE GEOTECHNICAL ENGINEER                                                                                                                                                                                FEATURES PRIOR TO CONSTRUCTION
              C.        THE GITA SHALL CONFIRM THAT ALL ORGANIC MATERIAL HAS BEEN REMOVED PRIOR TO THE                                                                                                                                      3.        SURFACE LEVELS OF STORMWATER & SEWER MANHOLES AND                                                                                                                                                                                                                           THIS DRAWING IS BEST
                        COMMENCEMENT OF FILLING ACTIVITIES                                                                                                                                                                                            OTHER SERVICE PITS ARE TO SUIT THE FINISHED SURFACE (LEVEL                                                                                                                                                                                                                 VIEWED IN COLOUR AND
              D.        TEST ROLLING AND REMOVAL OF UNSUITABLE MATERIAL IS TO BE UNDERTAKEN IN ACCORDANCE WITH                                                                                                                                        AND GRADIENT), WHICH MAY BE SLIGHTLY DIFFERENT TO ANY                                                                                                                                                                                                                     ON AN ELECTRONIC DEVICE
                        AS3798. ANY SOFT SPOTS OR ZONES OF UNSUITABLE MATERIAL THAT ARE IDENTIFIED SHALL BE DEALT                                                                                                                                     CENTER OF STRUCTURE LEVELS PROVIDED.
                        WITH AS REQUIRED BY THE GEOTECHNICAL ENGINEER
              E.        UNCONTROLLED FILL IS TO BE REMOVED AND RECOMPACTED ON SITE WHERE MATERIAL IS SUITABLE.                                                                                                                                                                                                                                                                                                                                                                                                    STATUS


                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     FOR APPROVAL
                                                                                                                                                                                               DWN       DES       CHK       APP                                                                                                                                               CLIENT                                              PROJECT                                                    SUBJECT                                       PROJECT No.
    SCAN QR CODE TO
                                                                                     REV         DATE         DESCRIPTION
                                                                                                                                                                                                                                        ASSOCIATED CONSULTANTS                                     APPROVED            CHECKED




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             11/04/2025 3:40:34 PM
                                                                                       C      10.04.25         ISSUE FOR OPERATIONAL WORKS APPROVAL                                            AR       KHN        SG       NR                                                                                                                                                 QUEENSLAND VENUE                                    120 POINCIANA AVE,                                         EARTHWORKS NOTES AND                           23169
    CONFIRM CURRENT                                                                    B      04.02.25         IFC PART 1                                                                      AR       KHN        SG       NR
                                                                                                                                                                                                                                                                                                                                                                               COMPANY PTY LTD                                     TEWANTIN, QLD                                              DETAILS                                       DRAWING No.        REVISION
    DRAWING REVISION                                                                   A      17.10.24         ISSUE FOR CO-ORDINATION                                                         AR       KHN        SG
    http://docs.bornhorstward.com.au/revision/                                                                                                                                                                                                                                                                                                                                 ----                                                ----                                                                                                      C0100                 C
                                                                                                                                                                                                                                                                                                 DATE 11/04/25        DATE 11/04/25
COPYRIGHT © - This document is and shall remain the property of Bornhorst & Ward Pty. Ltd. The document may only be used for the purpose for which it was commissioned and in accordance with the terms of engagement. Unauthorised use of this document in any form whatsoever is prohibited.
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          0       10    20   30     40     50                 100         ORIGINAL SIZE A1
Log in to download the original file

Combined_Civil_Drawings_-_Royal_Mail_Hotel.pdf · 13.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.