Original source · versioned page text
OPW Application Cover Letter
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
Wednesday, 21 July 2021 Our Ref: 20281 / Office: Sunshine Coast Council Ref: MCU21/0033 NOOSA COUNCIL PO BOX 141 TEWANTIN QLD 4565 ATTENTION: The Chief Executive Officer Dear Sir, LODGEMENT OF DEVELOPMENT APPLICATION OPERATIONAL WORKS APPLICATION ASSOCIATED WITH APPROVED MULTIPLE DWELLINGS (LANDSCAPING AND CIVIL WORKS) 31 BOTTLEBRUSH AVENUE, NOOSA HEADS LOT 16 ON RP88934 Please find enclosed A Development Application for Operational Works in respect to the above site. In support of the application, please find attached: • DA Form 1, duly completed; • Civil Engineering plans, prepared by Empire Engineering; • Detailed Landscaping Plans, prepared by Project Urban; • Q Leave Levy receipt; • Traffic Management Control Plan; • Construction Management Plan; and • Draft Project Management Plan. We understand a fee of $3,474.00 applies to the application. Payment will be made upon receipt of a Council reference number and payment link. The application has been prepared to satisfy all the relevant conditions of the Material Change of Use approval (MCU21/0033) as demonstrated in the table below. Condition of MCU20/0249 Compliance Response Landscaping Works 22. The development site must be landscaped. Detailed landscape drawings have been prepared The works must be undertaken in accordance with by Project Urban and are included in the an Operational Works approval and Noosa Plan application. The detailed landscape has been 2020 Planning Scheme Policy PSP2 Landscaping. prepared generally in accordance with the In this regard, Landscape Plans must be provided approved landscape concept plan. to Council including the following: a. landscaping provided to a minimum of Complies. The areas provided on the landscape 35% of the site area, and 60% of this is to plans are consistent with those shown on the be soft landscaping; approved plans. b. the landscaped area in the south eastern Complies. A 1.8m landscape buffer with dense corner of the lot must be maintained at planting is provided to screen the fencing and
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (OPW Application Cover Letter.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 3 pages
Page 2
natural ground level and must be densely swimming pool.
landscaped with native screening
planting, for a depth of 1.8m to screen
fencing and the swimming pool from the
street;
c. shade trees and screening vegetation Complies. Shade trees and understorey plants
with layering of understorey plants and and grasses are provided along the rear
grasses must be planted for the length of boundary.
the rear boundary;
d. narrow growing screening vegetation Complies. Screening vegetation is provided along
must be planted for the length of the side both side boundaries.
boundaries;
e. a minimum 1.5m landscape buffer is to Complies. A 1.5m landscape buffer is provided to
be provided to the bin storage area, with the bin storage area and includes a Pandanus and
feature pandanus and screening shrubs; screening shrubs.
f. existing vegetation in the road reserve Complies. There is only one existing street tree
must be retained. An Arborist Report is to in front of the site which will have to be removed
be provided regarding the condition of for the new driveway. Two new banksia street
the existing street trees. Alternatively, if trees are proposed to replace this tree.
the street trees are required to be
removed, a minimum of 2 streets trees
must be provided, being advanced
Banksia (robu, integrifolia or serrata);
g. a pedestrian access pathway into the site Complies. No pathway within the road reserve is
is not approved within the road reserve; shown on the plans.
and
h. trees to be retained must be protected Not applicable
from clearing or construction activities by:
i. clearly marking vegetation to be
retained with flagging tape;
ii. installing protective fencing around the
drip line of the vegetation;
iii. restricting stockpiling, storage and
vehicle parking to those areas which are
already cleared; and
iv. using low impact construction
techniques around vegetation.
Site Access and Driveway
25. A sealed access driveway must be provided Complies. Refer to the submitted Civil
from the formation in Bottlebrush Avenue to all Engineering Plans.
parking and manoeuvring areas of the
development. The works must be undertaken in
accordance with an Operational Works approval
and must include in particular:
a. a driveway crossover in accordance with Complies. The proposal has been designed to
Council’s Standard Drawing RS-051; comply with the standard IPWEAQ drawings for
residential driveways, RS-049 & RS-050.
Page 3
b. be generally in accordance with drawing Complies
number SC-8839, C003 Revision C
prepared by Empire Engineering dated 18
May 2021; and
c. suitable safety measures, including Complies.
warning signage, to improve driver
awareness of pedestrians and enhance
pedestrian safety. Warning signage must
be provided near the exit to warn
motorists of pedestrian movement along
the frontage street.
Car Parking
26. A minimum of seven car parking spaces must
be provided and marked on the site. The works
must be undertaken in accordance with an
Operational Works approval and must include in
particular:
a. car parking as indicated on the approved Complies. In accordance with the approved plan,
plans; and the layout provides 6 resident and 1 visitor
parking spaces.
b. be generally in accordance with drawing Complies.
number SC-8839, C003 Revision C
prepared by Empire Engineering dated 18
May 2021; and
c. one visitor parking space within the total, Complies.
which are clearly marked for that purpose
and accessible at all times for visitor use;
d. dimensions, crossfalls and gradients in Complies.
accordance with Australian Standard
AS/NZS2890.1:2004 Parking Facilities.
Stormwater Drainage
28. The site must be provided with a stormwater Complies. Refer to the submitted Civil
drainage system connecting to a lawful point of Engineering Plans. The proposed stormwater
discharge. The works must be undertaken in drainage system has been designed in accordance
accordance with an Operational Works approval drawing number SC-8839, C003 Revision C
and be generally in accordance with drawing prepared by Empire Engineering dated 18 May
number SC-8839, C003 Revision C prepared by 2021. n.
Empire Engineering dated 18 May 2021.
Earthworks and Retaining Walls
36. All earthworks and associated Complies. Details of the proposed earthworks are
batters/retaining structures, both above ground provided in the Civil Engineering Plans.
and below ground level, temporary or permanent,
must be undertaken in accordance with an
Operational Works approval, and contained
entirely within the subject site unless written
permission from the respective landowner(s) is
provided to Council.
Page 4
In addition, the QLeave receipt, Traffic Control Management Plan and preliminary Project Management Plan are enclosed to satisfy the requirements of Advice Notes 2 and 5. Should you have any questions with respect to the above, please do not hesitate to contact me direct. Yours faithfully PROJECT URBAN Mick Sheppard Director Email: [email protected]