OPW Application Cover Letter
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
b. be generally in accordance with drawing Complies
number SC-8839, C003 Revision C
prepared by Empire Engineering dated 18
May 2021; and
c. suitable safety measures, including Complies.
warning signage, to improve driver
awareness of pedestrians and enhance
pedestrian safety. Warning signage must
be provided near the exit to warn
motorists of pedestrian movement along
the frontage street.
Car Parking
26. A minimum of seven car parking spaces must
be provided and marked on the site. The works
must be undertaken in accordance with an
Operational Works approval and must include in
particular:
a. car parking as indicated on the approved Complies. In accordance with the approved plan,
plans; and the layout provides 6 resident and 1 visitor
parking spaces.
b. be generally in accordance with drawing Complies.
number SC-8839, C003 Revision C
prepared by Empire Engineering dated 18
May 2021; and
c. one visitor parking space within the total, Complies.
which are clearly marked for that purpose
and accessible at all times for visitor use;
d. dimensions, crossfalls and gradients in Complies.
accordance with Australian Standard
AS/NZS2890.1:2004 Parking Facilities.
Stormwater Drainage
28. The site must be provided with a stormwater Complies. Refer to the submitted Civil
drainage system connecting to a lawful point of Engineering Plans. The proposed stormwater
discharge. The works must be undertaken in drainage system has been designed in accordance
accordance with an Operational Works approval drawing number SC-8839, C003 Revision C
and be generally in accordance with drawing prepared by Empire Engineering dated 18 May
number SC-8839, C003 Revision C prepared by 2021. n.
Empire Engineering dated 18 May 2021.
Earthworks and Retaining Walls
36. All earthworks and associated Complies. Details of the proposed earthworks are
batters/retaining structures, both above ground provided in the Civil Engineering Plans.
and below ground level, temporary or permanent,
must be undertaken in accordance with an
Operational Works approval, and contained
entirely within the subject site unless written
permission from the respective landowner(s) is
provided to Council.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (OPW Application Cover Letter.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.