Our ref: PR132983-1
Reshaping of basin
Issue
The information provided outlines that minor reshaping of the basin will be required. It is not clear how or
where the reshaping will occur and whether sufficient space exists for all components of the basin.
Advice Required
5. Provide detail design plans in expectation of changes to the respective operational works approvals to
demonstrate that all components of the water quality treatment system will be able to be located within
the development site.
Response
Accompanying this response are the Amended Engineering Drawings prepared by Calibre (Attachment D)
which demonstrate the water quality treatment system to be built. The minor reshaping that was referenced
in the original application relates to reshaping the bio-basin to ensure it is not located under the building, but
still retains its minimum required area. The drawings demonstrate that all components of the water quality
treatment system are located internal to the development site.
Public pathway
Issue
The new amended plans do not show a public pathway (2.0m wide) along the frontage of the site, which
was included in the previously approved plans for this development.
Advice Required
6. Amend plans to include the required 2.0m wide pathway.
Response
A 2.0m wide pedestrian pathway is shown on Drawing Reference: DA_118- Ground Floor Plan (Attachment
A) and also shown at Figure 2 below:
RPS Australia East Pty Ltd. Registered in Australia No. 44 140 292 762
rpsgroup.com Page 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
FurtherAdviceResponse_2020.09.07 (002).pdfRelated documentApplication case desk ↗
About this file
- File size
- 671 KB (small file)
- File type
No other editions are linked here.