Negotiated Decision Notice - Concurrence Agency - EPA [As Published] · 132008.170

of 18

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                        2008/170




      Processing of bonds for security where specific Council approval has been given for the
      bonding of contributions will incur an administration fee in accordance with Council’s Land
      Development Commercial & Regulatory Fees at the time of lodgement.

      In the event that the Development Permit for Material Change of Use of Premises lapses or is
      cancelled, the trading bank guarantee will be returned.
General
52.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be
      submitted in conjunction with an application for a Development Permit for Operational Works.
      In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
      submitted in conjunction with any application for Operational Works.
53.   Digital detailed designs including drawings, calculations, specifications etc, shall be submitted
      with any application for a Development Permit for Operational Works in respect of roadworks
      and stormwater drainage works. The design shall be in accordance with Council’s Planning
      Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage and Earthworks.
      To avoid conflict with underground pipes or services, all existing and proposed services
      required by the development shall be shown on the plans.
54.   To facilitate production of As Constructed drawings it is suggested that all design drawings are
      submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
      use of ADAC are available at www.adac.com.au).
55.   A construction management plan/strategy to ensure no damage occurs to Council services
      shall be prepared by a suitably qualified Registered Professional Engineer and submitted to
      Council in conjunction with any application for Operational Works.
56.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
57.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site shall be at no cost to Council.
58.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
59.   As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
      for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
      type of all services and structures. All of which shall be submitted to Council for checking and
      for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage
      structures, finished ground levels and pavement surface levels. The data shall be submitted in
      the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
      are available at www.adac.com.au).

      Approval of works shall not be granted until all As Constructed information has been supplied
      and accepted by Council.
Environmental Health
60.   The developer must provide a suitably screened imperviously paved area large enough for all
      refuse and recycling containers.



                                                                                          8 of 18

Used in these records

About this file

File size
306 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - Concurrence Agency - EPA [As Published].pdf · 306 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.