10.6. The applicant is advised that burning off is an unacceptable method of disposal.
11. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are
not constructed under overhead electricity transmission lines, or within any easements.
12. Gates must not be installed along the rear property boundary.
Demolition or Relocation of Existing Dwelling
13. Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be
protected from damage and made safe to the standard required by the regulatory authority;
14. All infrastructure must be disconnected, capped or sealed including:-
electricity meters removed and electrical wires disconnected; and
telephone lines are disconnected; and
high speed data cables and television provider boxes are disconnected and removed to
the standard required by the regulatory authority;
15. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging, must be removed from the building and disposed of in accordance with industry best
practice.
16. Waste generated during construction must be stockpiled in a centralised location and covered
as required to prevent material being blown onto adjoining properties including the road
reserve or food waste from generating vermin. All site waste must be disposed of to an
approved waste disposal facility either directly or via an approved waste receptacle and
collection service. Storage areas are to be located near the temporary access to the site so
that access can be gained with out damage to infrastructure.
17. All building materials containing asbestos products must be disposed on in accordance with
industry best practice.
18. A temporary crossing must be provided to protect road reserve infrastructure including kerb
and channel;
19. Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site,
the relocation site or between the sites must be repaired or reinstated to at least pre-existing
conditions.
20. Sediment and erosion control measures must be placed on site prior to the works
commencing and shall be maintained until all works are complete. The erosion and sediment
control measures shall be in accordance with the “Best practice guidelines for control of
stormwater on building sites” prepared by Healthy Waterways (copy attached or available at
www.healthywaterways.org).
21. All disturbed areas must be revegetated or otherwise stabilised at the completion of the works.
Disturbed areas are revegetated using species identified in PSP3 – Landscaping Plants and
Guidelines.
22. The transportation of all materials to and from the site must be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying out materials either to
or from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
23. A Waste Management Plan shall be submitted for the demolition to the Land Use Section of
Noosa Council, prior to the development permit for building works being issued. The Plan shall
contain the following information:-
Page 3 of8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2008.00000413.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 60 KB (small file)
- File type
No other editions are linked here.