Skip to the record
The gold standard in government transparency.

Original source · versioned page text

Revised Drawings SCG 31131-OPW-2022.061.01-Council RFI.pdf

of 4

Page text read automatically using OCR, there may be inaccuracies

                  Issue:




                                           Unit 1/11 Project Ave,
                                           Noosa Heads
                                           Ph (07) 5455 5604




                  DEBUILD T/A
                                           email:[email protected]
                                           web:www.scg-engineers.com
                                           ABN 40 098 481 899




                      Title:




                     Project




                     Date:       Drawn                Design

                      Checked:   Drg No.                        Rev.




Rev. - 10.06.16


[OCR of page images]
 

DRAWING SIZE — At

  
  
 
 
 
 

 

www.dialbeforeyoudig.com.au

SAY DIAL1100

yy BEFORE YOU DIG

 

  

 

 

EXISTING SIDE ENTRY PIT
PROVIDE FILTER SOCK

SURROUND DURING SITE
BULK EARTHWORKS.

 

  
   
       
   
       
 
 
  
    
 
 
 
 

SILT FENCES TO DIVERT FLOWS INTO
CONSTRUCTED DETENTION BASIN.
PROVIDE BUNDING AS SHOWN ALONG
NORTHERN BOUNDARY WITH BUND Ht
MIN 200mm HIGHER THAN BLOCKWALL
WEIR Ht (RL 11.30m), EXTEND BUND
ALONG BOUNDERY UNTIL HIGHER THAN
THE RL 11.70m CONTOUR.

x*

 
 
 
   

MAINTAIN EXISTING SITE TURFED AREA FOR A SILT
BUFFER. PROVIDE MAXIMUM POSSIBLE WIDTH. PROVIDE
BARK CHIP REPLACEMENT FOR ANY EXPOSED SOIL AREAS.
PROVIDE SILT FENCE ACROSS THE UPSTREAM EDGE OF
THE ZONE DURING THE CONSTRUCTION PHASE OF
BIO/DETENTION BED AND SILT/SEDIMENT BASIN

  
 
  

BLOCKWORK WALLS FOR DETENTION
ZONE AND BIO-RETENTION BED
CONSTRUCTED TO CREATE
SILT/SEDIMENT SETTLEMENT BED TO
SERVE SITE THROUGHOUT
CONSTRUCTION WORKS. PROVIDE GAPS
R| IN WALLS TO ALLOW SURFACE RUNOFF
INFLOWS INTO THE BED. REFER DRG
SW1.1/SW1.2 FOR DETAILS

CONSTRUCTED SEDIMENT
BED TO DETAIL MIN 80m2

PLAN SIZE, OUTFLOW TO /
EXISTING SITE DRAINAGE

GULLY PIT, REFER DRG /

QW2.2 FOR BED DETAILS //

 

 

HEIGHT DATUM

Lot 1 on RP130594 & Lots 80 &
81 on RP71151
Level Datum AHD I

 

 

 

  
 

EXISTING CONDITION SURVEY
A PHOTOGRAPHIC SURVEY OF THE EXISTING KERB &
CHANNEL AND FOOTPATHS FRONTING THE SITE IS TO
BE COMPLETED AND ISSUED TO COUNCIL PRIOR 10
THE PRE-START WORKS MEETING WITH COUNCIL.

 

 
  
 
 
 
 
  
   
    
      
   
  

 

80-120mm ROCK (NO FINES) | \ é
HARD STAND OVERLAY :
FOR“DELIVERY'S DURING
CONSTRUCTION. TYPICAL.

 

THE SILT FENCE ALONG THE NORTHERN
BOUNDARY TO BE COVERED WITH BUILDERS
PLASTIC TO DIVERT ALL FLOWS TOWARDS AND |
INTO THE INTO CONSTRUCTED DETENTION BASIN. \
FENCE TO BE MAINTAINED THROUGHOUT

i xX

 

Level Origin PSM115316, RL 3.593m CONSTRUCTION — _ — = (quune®S paste
Survey information provided by Noosa \x g a : «0
Cooloola Land Surveys Pty Ltd | } 2, =a = + tag | EXISTING Wat \
Drg No. 21215DET _ —— — Tie4/ GWE
P BOUNDARY, Hake \ | > | Swale 7
ot = — x over SUT FENCE) _ swe >
= PLA c a
- —— (puuDers \ cane > _— swat (c.-0) \

oO Field Inlet \
_— SWE \ “

  

\

SITE PLAN — SILT & SEDIMENT EROSION PLAN

 

LEGEND Scale 1: 200
Cannne——+>__ © 8 '0n1:200 @ AI
_--7-7 INDICATES EXISTING SURFACE CONTOURS — sw/EX INDICATES STORMWATER DRAIN EXISTING 1:400 @ A3
48077 AND LEVELS TO AHD. AS NOTED
SY
4480 EXISTING SURFACE SPOT LEVELS. wy INDICATES DIRECTION OF SURFACE FLOWS
————— INDICATES OVERHEAD ELECTRICITY — — — — sir SILT RETENTION FENCE TO DETAIL
SUPALY TINE INDICATES ALIGNMENT OF SWALE AND
— SWALE +>

INDICATES EXISTING SEWER LINE

w———— INDICATES WATER MAIN APPROX
ALIGNMENT, BUILDER TO CONFIRM EXACT
LOCATION PRIOR TO WORKS

a INDICATES TELSTRA LINE APPROX
ALIGNMENT, BUILDER TO CONFIRM EXACT
LOCATION PRIOR TO WORKS

BUNDING TO DETAIL

tl (.-0)

DIRECTION OF FLOW, REFER TYPICAL
SWALE DETAILS

INDICATES ALIGNMENT OF SOIL BUNDING
MOUNDS TO DETAIL. SITE FOREMAN TO
MAINTAIN BUNDS THROUGHOUT WORKS

INDICATES LOCATION OF COIR LOG CHECK
DAMS ACROSS DRAINAGE PATHS REFER
TYPICAL DETAIL

\
CREATE A VBHICLE PATH THROUGH .
THE SITE FOR SONSTRUCTION é
VEHICLES, COVER ‘N CRUSHED ROCK

OR ROAD BASE = SL. _- — ——

TEMPORARY SWALE CONSTRUCTED TO

 
 
        
          
   
   
       
         
 
 
 
 
  
   
        
     
     
      
       
   
   
   
   
   

xix—

; oe
95.916

71000

 

 

\ = \ % DIVERT SURFACE FLOWS PRIOR TO
2 \ 9% BUNDING CONSTRUCTION =
1 2 \ \ *
\ % oe \
\ PROVIDE RUMBLE GRATES \% + \
DURING DEMOLITION & \s \
\ SITE BULK EARTHWORKS. d \
\ ee ° \ Ke. $08 Manhole :
* \ a
sn \ . \ * 4
= —— \ \ Yn
G \ . \ + \ g
/ \ \ \ m
: \
/ \. “ . . |
+ \ \ A
. x \ .
PARKING AREA FOR \ . ooNS Sg
VISITORS AND WORKERS \ . we
\ & . \ Lot 1 ¢
SS * \ NC RPI 3054
—_ N\ > Ye
* SI
N \ ‘\ \ wy \ .
» \ . ‘ 2 f
4 S +
‘ \ SY 2 SA =
\ 3 \
\
\ . YN XN
N
y . +
wy s ~L — SIL —
SILT FENCING AROUND ‘ ° = — —_ |
é NN ~ poe
PARKING AREA . SS _ — SIL Oo ~

SEDIMENT BASIN DESIGN

The sediment basin has been designed using
the recommendations of IECA (International
Erosion Control Association). Refer to IECA
forBasin Management recommendations.
Basin type : D

RUSLE : 190 - 230 t/ha/yr

R (Y%, 5 day) : 54mm (R(85%))

Catchment : 0.4 ha

Cv: 0.60

Settlement Volume : 130m? (Depth: 750mm)
Storage Volume : 65m° (Depth : 375mm)
Basin Surface Area : 160m?

 

  

 

 

 

4+ \) 6
aPepISWALE > +

 

wail \
af eA.
we

4 q ss
Wok i

FOR DETAILS

BUNDING TO DIVERT FLOWS
INTO CONSTRUCTED

 

 

 

 

CONSTRUCTION BASIN

Ne A DETENTION BASIN.
{75910 25m
‘ eweh75,976 x
be )
SITE SILT & SEDIMENT MANAGEMENT — CONSTRUCTION PHASES
PHASE METHODOLOGY

DEMOLITION — Provide silt fencing around existing SW pit in N.E. Cnr of site
- Construct bunding along rear (eastern) boundaries as indicated on plan.
Cover bunds in builders plastic to prevent scour/silt runoff
— Maintain the existing turfed area shown on the plan and provide
additional silt fence upslope from the area.
— Install remaining silt fences as indicated on the plan.
— Rumble grates and no fines rock hardstand to be provided for all plant
and equipment exiting the site.
— Cover all stockpiled soil with builder plastic
— Maintain existing swale adhjacent northern boundary and install coir log
dams along its length

BIO/DETENTION/SILT | — Maintain all site measures implemented during the DEMOLITION phase.

— Fix and or improve any measures damaged or compromised during the
DEMOLITION phase or past storm event.

— Provide a clearly identified vehicle path through the site down to the
construction work-face. Provide crushed rock/road base as a temporary
pavement along these paths.

— Establish a clearly identified parking area within the site for workers and
visitors. This area should have crushed rock/road base surfacing and the
downslope areas surrounded by silt fencing.

SEDIMENT BASIN FOREBAY SLOTTED
150 DIAM PIPES AND WITH 225 DIAM
MANIFOLD PIPE DRINAING INTO

SEDIMENT BASIN, REFER DRG OW2.2

EXISTING SITE DRAINAGE GULLY PIT REMOVED
AND UPGRADED CONNECTION PIPE INSTALLED
AS PER DRG SW1.1 PROVIDE SILT BARRIER
SURROUNDS DURING CONSTRUCTION OF
DETENTION BASIN RETAINING WALLS. FULL
INFLOW CAPACITY TO BE MAINTAINED DURING
CONSTRUCTION WORKS

MAINTENANCE OF SILT PROTECTION

SITE FOREMAN TO MAINTAIN ALL SILT AND SEDIMENT
PROTECTION MEASURES THROUGHOUT THE DURATION OF
PROJECT. ANY BREACHING OF THE PROTECTION MEASURES
MUST BE REMEDIATED IMMEDIATELY AND REPORTED TO THE
ENGINEER FOR CORRECTION MEASURES. SILT RUNOFF
PROTECTION IS TO BE MAINTAINED UNTIL SUCH POINT THAT
LANDSCAPING IS COMPLETED AND NOT SUSCEPTABLE TO
STORMWATER SCOUR.

DUST MOBILISATION FROM WIND ACTION

SITE CONTROL TO INCLUDE PROTECTION AGAINST THE
CARRIAGE OF SOIL SEDIMENT FROM WIND ACTIONS. SITE
FOREMAN TO COVER ALL STOCKPILES WITH HESION OR
SIMILIAR, PROVIDE SILT FENCING AROUND BASE OF STOCKPILES

 

SITE DRAINAGE — CONSTRUCTION
CONSTRUCTED STORM WATER PITS WITHIN THE SITE

ARE TO BE COVERED UNTIL THE SITE IS COMPLETED
OR TO BE FITTED WITH SILT PROTECTION MEASURES
TO THE APPROVAL OF THE ENGINEER

 

 

BULK EARTHWORKS

— Maintain all site measures implemented during the previous construction
phase.

— Fix and or improve any measures damaged or compromised during the
previous phase or past storm event.

— Provide all detailed items within the constructed Bio/Detention basin
which will act as the a Silt Basin during the earthworks and subsequent
construction phases.

— Ensure all site surface runoff is channeled through the Silt Basin. No
runoff from the site must be allowed to drain into neighbouring properties.
— Maintain bunding where required

— The Silt Basin will require continual management/maintenance during the
remaining construction works. Refer Silt Basin detail.

— Approved flocculating agent should be used for any silt laden volumes
of detained runoff within the Silt Basin.

— Stripped Areas awaiting earthworks should be tilled or bucket raked in a
direction parallel to the surface contours to slow/impede surface runoff
and promote infiltration

— Completed earthworks areas should be treated with an approved soil
binder material.

 

BUILDING WORKS

— Maintain all site measures implemented during the previous construction
phase.

— Fix and or improve any measures damaged or compromised during the
previous phase or past storm event.

— The Silt Basin will require continual management/maintenance during the
remaining construction works. Refer Silt Basin detail.

— All constructed SW pits within the site must be covered until connected
to drains which discharge in the Silt Basin. At which point the pits should
still be covered with a Geofabric blanket.

— All installed gutters should be fitted with temporary down pipes which
drain directly into constructed SW pits.

 

BIO-RETENTION BED

 

 

— The silt capture measures shall be removed from the Silt Basin for
preparation of Bio—retention basin.

— The Bio-retention basin shall be constructed in accordance with the
details contained within these drawings.

 

 

These measures are provided with reference to IEAUST Soil and Sediment Erosion Engineering
Guidelines for Queensland Construction Sites and IEAC recomendations

 

 

 

 

 

 

 

B Basin details revised for Council RFI 01.06.22

A Revisions for Council RFI 19.05.22
Revision | Description Date
Iss

* FOR APPROVAL

 

DO NOT SCALE FROM THIS DRAWING

The design and associated details contained on this and associated
drawings are copyright and are not to be used or reproduced without
the written permission of SCG Consulting Engineers.

 

Unit 1/11 Project Ave,
Noosa Heads

Ph (07) 5455 5604
email:[email protected]

web:www.scg-engineers.com
ABN 40 098 481 299

C) S06

DEBUILD T/A

 

Title:

SITE SILT AND SEDIMENT
CONTROL

 

Project

89-93 Eumundi Noosa Rd,
NOOSAVILLE

 

Date: Drawn Design

 

 

 

April 22 SR SR
Checked: Drg No. Rev.

| 9.55 | 31131 -OW2.1) B.

 

 

 

 

 

 

Log in to download the original (Revised Drawings SCG 31131-OPW-2022.061.01-Council RFI.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 3 pages

Page 2

                  Issue:




                                           Unit 1/11 Project Ave,
                                           Noosa Heads
                                           Ph (07) 5455 5604




                  DEBUILD T/A
                                           email:[email protected]
                                           web:www.scg-engineers.com
                                           ABN 40 098 481 899




                      Title:




                     Project




                     Date:       Drawn                Design

                      Checked:   Drg No.                        Rev.




Rev. - 10.06.16


[OCR of page images]
 

 

DRAWING SIZE — At

 

www.dialbeforeyoudig.com.au

SAY DIAL1100

yy BEFORE YOU DIG

 

  

 

 

 

900(W) GEO-FABRIC SILT FENCE,
FIXED TO SPIKES AND BURIED ——-
300 INTO STABLE GROUND.

 
   
  
 
    

SILT RETENTION

SILT RETENTION FENCES PRIOR TO

 

IS TO BE CONSTRUCTED ALONG THE

WITHIN THE ALLLOTMENT MUST DRAIN

 

1200(L) 50 SQ. HDWD
SPIKES, 1800 CTRS DRIVE

600 INTO GROUND. ENTER NIEGHBOURING ALLOTMENTS

THROUGH THE USE OF SURFACE BUNDING

OR SCOUR PROTECTED DRAINS. THE FENCE
SILT FENCE DETAIL MUST REMAIN IN PLACE UNTIL SUCH TIME

THAT FINISHED LANDSCAPING AND
DRAINAGE MEASURES ARE INSTALLED.

EXISTING STORMWATER
INLET

PROVIDE SILT FENCE AROUND
INLET AS PER DETAIL ON THIS
SHEET.

PROTECTION OF EXISTING STORMWATER PITS

SILT/SEDIMENT BASIN MANAGEMENT

—The site foreman shall monitor and maintain the silt basin
throughout the works.

—Any trapped silt after storm events should be removed and the

substantial storm events.

— Trapped/detained silt laden stormwater can be flocculated with an
approved flocculating agent.

— Any breaching or overflow incidents should be reported immediately
to the Civil Engineer

   
 

WALL HT (RL 11.30m) PROVIDE EVENTS

SILT FENCE SURROUNDING PIPE
INFLOW

DETENTION BASIN
PERIMETER BLOCKWALLS

CONSTRUCTED FIRST TO
ESTABLISH THE
SEDIMENT BASIN RL11.05

THE CONTRACTOR IS TO INSTALL APPROVED
COMMENCING ANY EARTHWORKS. THE FENCE

LOWEST BOUNDARY AND RETURNED UP SIDE
BOUNDARIES TO ENSURE FULL STORMWATER
ENTRAPMENT. SURFACE RUNOFF FROM

TOWARDS THE FENCE AND SHALL NOT

GEOFABRIC_BLANKET

A34 BIDIM NON-WOVEN

Flow Rate @ 100mm head : 165Lt/m?/s
Pore Size : 75 Microns

protection measures maintained/reinstated to as built condition. Inflow Capacity @ 80m? ; 1300Lt/s
— The geofabric blanket should be removed and replaced after (GEOFABRICS.COM.AU)

   
 
 
   
  
   
  
   
   
  
 
 
 

 
  
  

SEDIMENT BASIN/SETTLING POND MIN 160m? PLAN
SETTLEMENT & STORAGE ZONE DEPTHS AS SHOWN

COIR LOGS STAKED ACROSS SWALE/DRAIN AND
EXTENDED BACK UP FLANKS TO RESTRICT FLOW
AROUND DAM EDGES. BUILDER TO ADJUST EXTENT
OR Ht OF DAM IF FLOW AROUND OCCURS. PROVIDE
LOOSE COBBLES ACROSS UPSTREAM EDGE OF LOG
TO AVOID UNDER FLOW

 

   
 

yyw
EXTEND BACK UP FLANKS ff ,
TO RESTRICT FLOW PROPOSED SWALE

AROUND DAM EDGES. Loy owoy OR TABLE DRAIN

COIR LOG CHECK DAM DETAIL

 
  
  

EXISTING SIDE ENTRY SILT FILTER SOCK TO
PIT OR SIMILIAR SURROUND GRATES AND
GRATED PIT SIDE ENTRY INTO PIT

KERB & CHANNEL

SILT FILTER SOCK DETAIL — STAND UP KERB

  
 
   
   
  
  
  
  
 

   
  
  
 

SEDIMENT BASIN DESIGN
The sediment basin has been designed using
the recommendations of IECA (International
Erosion Control Association). Refer to IECA
forBasin Management recommendations.
Basin type : D

RUSLE : 190 - 230 t/ha/yr

R (Y%, 5 day) : 54mm (R(85%))

Catchment : 0.4 ha

Cv : 0.60

Settlement Volume : 130m? (Depth: 750mm)
Storage Volume : 65m° (Depth : 375mm)
Basin Surface Area : 160m?

   
   
  
   
   
   
   

 

RAISE PIPE TO LEVEL INDICATED BUILDER TO REMOVE CAPTURED SILT AFTER STORM
TO ACHIEVE SETTLING DEPTHS, EVENTS OR AS REQUIRED.
TOP OF PIPE 10 BE BELOW WEIR PROVIDE CHEMICAL FLOCCULATION DURING STORM

___ FILLED SURFACE

  
   

 

   
 

   

 

 

 

 

UPGRADED SW PIPE FITTED
WITH A RISER AS SHOWN
STAKE RISER TO GROUND
TO STABILISE

TYPICAL SECTION SILT/SEDIMENT BASIN

mg

SEDIMENT BASIN FOREBAY FILTER

2/1508 SLOTTED PIPES ALONG FULL LENGTH OF FOREBAY
(REFER PLAN DR OW2.1) AND DRAINED INTO BASIN VIA
PENETRATIONS THROUGH BASIN WALL

BACKFILL SURROUND TO PIPES WITH 20-40mm NO FINES
GRAVEL, OVERLAY GRAVEL WITH GEOFABRIC BLANKET (A34
BIDIM NON-WOVEN), EXTEND UP EDGE BERMS & PIN TO
GROUND, BUILDER TO REPLACE GEOFABRIC AND REMOVE
CAPTURED SILT AFTER STORM EVENTS OR AS REQUIRED.

t
1 RLI1.10 |
1 wt
1 T
750mm MIN SEDIMENT er
SETTLEMENT ZONE _ — SEDIMENT SETTLEMENT ZONE” 1 RL10.30
— — — — — 1/4 tj WW __ __
375mm MIN. SEDIMENT SEDIMENT STORAGE ZONE | ! L9.9
STORAGE ZONE ~ t : SZ
1
"IL — RL 9.29
Vv

 

 
   
       
     
       
     
     
       
     
 

COMPACTED SOIL BUND TO
MINIMUM DIMENSIONS NOTED,
COVER IN BUILDERS PLASTIC
AND PIN SECURELY TO
GROUND

  

a

SURFACE BUNDING DETAIL

PROVIDE CHECK DAMS AS

1000mm MIN DETAILED
2
SY |
™——™ ON
“NNT [~~

TYPICAL SECTION CUTOFF SWALE

  

MAINTENANCE OF SILT PROTECTION

SITE FOREMAN TO MAINTAIN ALL SILT AND SEDIMENT PROTECTION
MEASURES THROUGHOUT THE DURATION OF THE PROJECT. ANY
BREACHING OF THE PROTECTION MEASURES MUST BE REMEDIATED
IMMEDIATELY AND REPORTED TO THE ENGINEER FOR CORRECTION
MEASURES. SILT RUNOFF PROTECTION IS TO BE MAINTAINED UNTIL
SUCH POINT THAT LANDSCAPING IS COMPLETED AND NOT
SUSCEPTABLE TO STORMWATER SCOUR.

DUST MOBILISATION FROM WIND ACTION
SITE CONTROL TO INCLUDE PROTECTION AGAINST THE CARRIAGE OF
SOIL SEDIMENT FROM WIND ACTIONS. SITE FOREMAN TO COVER ALL
STOCKPILES WITH HESION OR SIMILIAR, PROVIDE SILT FENCING
AROUND BASE OF STOCKPILES

   

SITE DRAINAGE — CONSTRUCTION
ENSURE GROUND PROFILE DURING CONSTRUCTION FALLS
TOWARDS THE CENTRE OF THE ALLOTMENT THEN TOWARDS
THE REAR BOUNDARY WHERE RUNOFF WILL DRAIN THROUGH
THE SILT POND & SILT FENCES. IN NO INSTANCE SHALL
THE ALLOTMENT DRAIN INTO NEIGHBOURING ALLOTMENTS.

 

 

 

SITE DRAINAGE — CONSTRUCTION

CONSTRUCTED STORM WATER PITS WITHIN THE SITE
ARE TO BE COVERED UNTIL THE SITE IS COMPLETED
OR TO BE FITTED WITH SILT PROTECTION MEASURES
TO THE APPROVAL OF THE ENGINEER

 

hannnt@—1_p——1_'}m1:200 @ All ppeg 5835 31131-OW2.2) A.

Project
89-93 Eumundi Noosa Rd,
NOOSAVILLE
Date: April 22 Drawn SR Design SR
Checked: Drg No. Rew.
:400 @ A3 ; S Richardson

 

A Basin details revised for Council RFI 1/06/22

 

Revision | Description Date

“FOR APPROVAL
DO NOT SCALE FROM THIS DRAWING

The design and associated details contained on this and associated
drawings are copyright and are not to be used or reproduced without
the written permission of SCG Consulting Engineers.

 

 

 

 

 

Unit 1/11 Project Ave,

j Noosa Heads
Ph (07) 5455 5604
email:[email protected]

web:www.scg-engineers.com
ABN 40 098 481 299

DEBUILD T/A

 

Title:

SILT AND SEDIMENT
CONTROL MEASURES

 

 

 

 

 

 

 

 

 

 

Page 3

     .26
  15
 WM
WM




                             Issue:




                                                      Unit 1/11 Project Ave,
                                                      Noosa Heads
                                                      Ph (07) 5455 5604




                             DEBUILD T/A
                                                      email:[email protected]
                                                      web:www.scg-engineers.com
                                                      ABN 40 098 481 899




                                 Title:




                                Project




                                Date:       Drawn                Design

                                 Checked:   Drg No.                        Rev.




           Rev. - 10.06.16


[OCR of page images]
 

 

DRAWING SIZE — At

 

www.dialbeforeyoudig.com.au ALL STORMWATE

SAY DIAL1100

BEFORE YOU DIG

 

  

 

 

 

 

HEIGHT DATUM

Lot 1 on RP130594 & Lots 80 &

81 on RP71151

Level Datum AHD

Level Origin PSM115316, RL 3.593m
Survey information provided by Noosa
Cooloola Land Surveys Pty Ltd

Drg No. 21215DET

 

 

 

 

BUILDER TO POT HOLE LOCATE AND
CONFIRM EXISTING SERVICES LOCATIONS
& LEVELS BEFORE ANY EARTHWORKS
ARE CARRIED OUT. REPORT ANY
DISCREPANCIES TO THIS FIRM.

 

 

 

BINS AREA.
PROVIDE DRAINAGE PIT FOR CONNECTION TO

 

R

PIPES TO BE LAID AT
1:100 MIN. UNO.

4/125x75x4.0 RHS (GALV.)
LAID AT 1 in 100 MIN. INSTALL TO
NEW KERB ADAPTORS IN
ACCORDANCE WITH COUNCIL STD
DETAIL RS—081 & MAKE
FOOTPATH GOOD. TYPICAL.

 
 
 
  
  
 
 

15kL ALL CAST PRE CAST IN-GROUND
TRAFFICABLE STORMWATER RETENTION TANK
RECEIVE ROOF RUNOFF (ONLY) FROM UNITS 1-3
& UNITS 17-20. PROVIDE PUMP OUT FOR
IRRIGATION PURPOSES & BIN WASH DOWN.
WARNING SIGNS AT TAPS 'NON POTABLE’.

 

 

 

 

 

REAR OF TOWNHOUSES UNITS SET AT EXISTING SURFACE
LEVEL WITH A FORMED STONE PITCHED SWALE TO ALLOW
FOR OVERLAND FLOW TOWARDS BIO-RETENTION /DETENTION
BASIN. PROVIDE UPSTAND TIMBER SLEEPER WALL ALONG
BOUNDARY TO RETAIN OVERLAND FLOWS WITHIN SITE
REFER SECTION B-B

REAR OF UNITS DRAINED VIA GRATED
FIELD INLETS AND INTERCONNECTING
DRAIN TO SITE DRAINAGE. REFER DRG
SW1.2 FOR TYPICAL DETAIL. SWALE
FORMATION FOR OVERLAND FLOWS
DIRECTED TO BIO/DETENTION BASIN

  
      

OVERFLOW WIER WALL AND
SCOUR PROTECTION ALONG
PROPERTY BOUNDARY. REFER

DRG SW1.2 FOR DETAILS

PROPOSED 60m2 BIO RETENTION

BED AND 200m3 DETENTION BASIN. (EXP—4)
FORMED WITH BLOCKWORK WALLS.

REFER DRG SW1.2 FOR DETAILS

  
  

 

 

 

 

 

 

 

 

 

   

 

SEWER MAIN. PROVIDE BUND SURROUND TO
DIVERT SW RUNOFF AWAY FROM AREA. REFER
TO HYDRAULIC CONSULTANTS DETAILS.

FRONT OF UNITS DRAINED VIA GRATED
FIELD INLETS AND INTERCONNECTING
SWALE DRAIN FORMATION FOR
OVERLAND FLOWS DIRECTED TO
DRIVEWAY

 

 

 

    

 

 

 

 

 

 

 

 

    

 

 

 

 
 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

    

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

       

 

  
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

LEGEND

INDICATES EXISTING SURFACE CONTOURS
AND LEVELS TO AHD.

INDICATES DIRECTION OF FALL
TO FINISHED SURFACES.

INDICATES SURFACE LEVEL (S.L.) AND INVERT
LEVEL (|.L.) OF ADJACENT STORMWATER PIT

49077

GD-200

F,
Alls

 

 

Sw

 

S.L. 12.50
LLL. 12.00

 

 

 

 

JP1

XI

— R-SW

 

450Sq STORMWATER JUNCTION PIT, PRE—CAST
CONCRETE. HEAVY DUTY GRATE WHERE IN
DRIVEWAY

400Sq GRATED FIELD INLETS, PRE-CAST
CONCRETE & HEAVY DUTY GRATE WHERE IN
DRIVEWAY, POLY AND LIGHT DUTY GRATE WHER
IN LANDSCAPE AREAS, REFER DRG SW1.2 FOR
TYPICAL REAR OF TOWNHOUSE CONNECTION
DETAIL.

600Sq GRATED FIELD INLETS, PRE-CAST
CONCRETE. HEAVY DUTY GRATE WHERE IN
DRIVEWAY

crt

Ej 6r2

 

RW

600x900 GRATED FIELD INLETS, PRE-CAST
CONCRETE. HEAVY DUTY GRATE WHERE IN
DRIVEWAY

— SWALE +>

& GP3
y6r4

900Sq GRATED FIELD INLETS, PRE-CAST
CONCRETE. WITHIN BIO/DETENTION BED, REFER
DRG SWI.2 FOR ORIFICE AND RAISED GRATE
DETAILS

 

 
  

  

OVERLAND FLOW

Qhoo - Qio = 12 L/s
Qatow = 215 L/s

 

  

 

 

INDICATES DIRECTION OF RAMP UP OR
DOWN AS INDICATED

 

RAMP. ww

    
   
    
    
 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PROVIDE A SWITCH OVER VALVE TO MAINS WHEN LOT 79 STONE SCOUR LOT 101
TANK VOLUME IS BELOW 10%. OVERFLOW TO RP71151 ie» PROTECTION T
EUMUNDI NOOSA ROAD KERB + CHANNEL. . Ca is RP106085
SL 1550] | Ix Ix \ Lk a i@
LIL 14.85 1500 uPVC cei 1508-uPVC = gpy_ 1508 uPVC apy 1508 uPVC 7910'00" 95.916 _cp1 2250 uPVC gp ws 2258 uPVC, N pt. 2258 uPVC py Pt BLOCK R-WALL SL 1110] “4 e
px - —sSw— Spar — sar -S Waar =e SWF sa > — WS Seale 7 sl Swale = SiS sare gg S Wie nr Sg sar SW See gy wae 9 Wo Sear —— Si Eh anne ILL. 9.25 x x F
Pt t FAL &. SE — sue Sea
Pt rh ee | 7. __ [SE 150] J) betentron’ easin 2
Po p—-—-———————4—---—--—~-_4 LL. 10.20 (grassed beyond bi x
/ | | bed area fp
4 / Z Y LITTTTIT IZ. ] EXISTING INTER-ALLOTMENT DRAINAGE
Bf / WMI. WY OCOE Ls YA | Z CONNECTION POINT. EXISTING PIT REPLACED WITH
iy Z | = EW PIT & EXISTING 2259 BRANCH PIPE
/ TH104 | TH201 TH202 <TH203 TH204 : 2 we INCREASED TO 3008
/ . L / : CEE] = : s kz IN ACCORDANCE WITH STORMWATER
1 / Hit. Loe 1 ry FFL: 14.000 FFL: 15.400 FFL: 13.400 FFL: 12.600 | a bo) MANAGEMENT REPORT BY SCG CONSULTING
) HH] |i Fe = oT | - FPL: 13.850 FPL: 13.250 FPL: 13.250 Y FPL: 12.450 Oi ENGINEERS.
! rood TTT s . . Y ; L
APE a ie | I GC 4 STUBS FOR ROOF WATER = ==]
Ce rr Qiao = Qn = 34 L/s | | OVERLAND FLOW Ye 1 CONNECTION, REFER INTERNAL | BIO-BED 2258 COLLECTOR
t ut Lo AAA Re _ ,
er Qatow = 934 L/s as LLL, | | Qtoo — Qo = 64 L/s “7A HYDRAULICS CONSULTANT I PIPE SHOWN WITH 100¢
715.1. 16.000 b eee : x | | Qatow = 235 L/s if Le YO, |= + FOR DETAILS, TYPICAL. 4 SLOTTED BRANCH PIPE AT
J] \\-15.600 ? SBE AWN CS =] OE S ap S LI NM AR a y 1.0m CTRS INTERCONNECTING
| / FALL SL 15.750 / “o SL 148 S.L. 12.450
z 7 ay wL. 10. / FALL y -L. 14.860 ? f, Ut.
el _ FLOW MveRT HL 18.150 S FLOW INVERT 2250PVe.. 1. 13.900 a “Reg [IL 11.000 | fe HEAD WALL AND STONE
——~— sh 7 =.
§| FLOW INVERT | | _ sw i % | Ew: \ L 3000 uPVC =| IL: 11.020 SCOUR PROTECTION
Ss es eS re t 3 rower Sl RP106085
N Re) ys \ \S \ WF A 9 ~<
SS is ~~ = DSF \ OS ROH] SENe ~ PROVDE 25m WDE RAMP FOR
Noa tase] JF ILL. 12.200 “om
yosS le ~~ | Ir ! a oye Ls TY MAINTENANCE ACCESS INTO
A, GPt pat g
a \ Y GP1 gz Z, ‘ we & BIO/DETENTION BASIN
| TH401 a ww] 4 N. §
16.600 afro Ya A = 01 fo aw J
16-45 PA : ei “ FFL: 16.500 | L| ST] / ~ FFL: 15.000 | SLasé0 wa “ XN e PAVEMENT LEVELS AND BREAKS IN
: ! FPL:16.150 7“ i SN FPL: 14.850 | be? \ i KERBING TO ALLOW OVERLAND
| S - ahi ‘ELS | [EL 1220 I = Fi f FLOWS INTO DETENTION BASIN
% OVERLAND FLOW & [i L| OVERLAND FLOW 2 ey, 5 L/-—~—
oot Bz Qtoo - Qi = 19 L/s Oo | Quo = Qy = 15 L/s ON : SW/EX aM 53076 ‘SW/EX SW/EX sw/ex
i Qaow = 409 L/s | , 6.1m MIN) Qgtow = 215 L/s JA x
1H402 Hi Y | I es \ PROPOSED BLOCK
| | FFL:16.450 <1, FFL:15.000 «4 +2 LU x BOUNDARY WALL
| A FPL: 16.300 SL 14.800H4 “44° a) 2 se. & c
Ss 6.1m] MIN LU CP! h | IL 14.250 | EL 14.890 CPt | one
= te TN t |b J
ie L- EXISTING
| P2_ | 4 7) lL aH | K . INTER—ALLOTMENT
| j TH403 ew ! / cer 1} 99 \4 >
S.L. 16.250 GP1 \ TH303 ¥ Y DRAINAGE
eh a / FFL: 15.000 85 LOT 99 ¥
=: FPL: 16.300 Ve FPL: 14.850 «| Rl XN v \
= dN \2 Te, ! | \ RP106085 \
3| | | 1B | a \ \ ¥
=| | | a | ; \ \
| 4
| AL) | | . \ AX a
| ! FEL 16.450 ! TH304 Of x ALAN
2 VSL, “10. “4 Fal .
wit FPL: 16.300 FFL:15.000 | 2
4 im v J 6 * /
L— LI | SL. 16.400 77 AN J pe Bs 5 be
IL, 15.800 K& by J] fe x
RE oes a 1 a
— = O° 84.965 LL == -!- {E i
BP .
W x x _ x \ x
HATCHING INDICATES ROOF I | :

STORMWATER

TO BE DIRECTED TO

HARVESTING TANK.

200(W) GRATED DRAIN WITH HEAVY

DUTY GRATE.

INDICATES STORMWATER DRAIN PROPOSED
AS NOTED MIN 1 IN 100 FALL UNLESS

NOTED OTHERWISE

INDICATES ROOF STORMWATER DRAINAGE
LINE TO HYDRAULIC DESIGNERS DETAILS.

INDICATES OVERHEAD ELECTRICITY

SUPPLY LINE

INDICATES TELSTRA LINE APPROX
ALIGNMENT, BUILDER TO CONFIRM EXACT

LOCATION PRIOR TO WORKS

INDICATES EXISTING SEWER LINE

INDICATES POSITION OF RETAINING WALL

REFER EARTHWORKS DETAILS

INDICATES ALIGNMENT OF SWALE AND
DIRECTION OF FLOW, REFER TYPICAL

SWALE DETAILS

INDICATES OVERLAND FLOW CAPACITY
ASSESSMENT OF DRIVEWAY (Qio9 Yr 2100
FLOWS) USING MANNINGS. Qig FLOWS
DRAINED VIA UNDER GROUND PIPING

 

FINISHED SURFACE LEVELS
ALONG SIDE BOUNDARY TO
FALL TOWARDS DRIVEWAY

 

REAR OF UNITS DRAINED VIA
GRATED FIELD INLETS AN

 

INTERCONNECTING DRAIN TO
SITE DRAINAGE TYP.

 

SITE PLAN — SITE STORMWATER DRAINAGE PLAN

Scale 1: 200

THIS PLAN TO BE READ IN CONJUNCTION WITH
SCG CONSULTING ENGINEERS STORMWATER
MANAGEMENT REPORT 31131(SWM)

 

ALL SERVICES SHOWN ON THIS PLAN INDICATIVE
ONLY CONTRACTOR TO LOCATE ALL SERVICES
PRIOR TO COMMENCING WORKS ON SITE. ALL

SERVICES ARE TO BE PROTECTED IN
ACCORDANCE WITH THE AUTHORITY

 

RESPONSIBLE FOR THE SERVICE

 

KE

EX. SWPT EXISTING STORMWATER PIT

RC. HW. — REINFORCED CONCRETE HEADWALL
EX. SMH — EXISTING SEWER MANHOLE

E.0.B. EXISTING EDGE OF BITUMEN
K&C EXISTING KERB & CHANNEL

N.S.L. NATURAL SURFACE LEVEL

FH. FIRE HYDRANT

TP TELSTRA PIT

EP. ELECTRICAL POWER POLE

KERB EXISTING KERBING

ROOF DRAINAGE
ROOF DRAINAGE BY HYDRAULICS CONSULTANT,
ROOF DRAINAGE FOR THOI-THO3, TH-17, TH-18,

APT-19 & APT-20 10 BE DIRECTED TO THE
15kL STORAGE TANK AT THE FRONT OF THE SITE,
THE REMAINING ROOFS TOP BE CONNECTED TO
SW PITS WITHIN THE DRIVEWAY

 

 

ALL GRATED STORMWATER PITS WITHIN DIVEWAY
TO BE FITTED WITH OCEANAGUARD GPT INSERTS

 

Revisions for Council RFI

01.06.22

 

Revisions for Council RFI

19.05.22

 

OPERATIONAL WORKS ISSUE

05.04.22

 

THO6/07/08/09 REVISED

09.03.22

 

Dojo /m)7

BINS MOVED TO FRONT OF SITE

22.02.22

 

A

MAINTENANCE RAMP ADDED

11.02.22

 

Revision

 

Description

 

Date

 

Iss

* FOR APPROVAL

 

DO NOT SCALE FROM THIS DRAWING

The design and associated details contained on this and associated
drawings are copyright and are not to be used or reproduced without
the written permission of SCG Consulting Engineers.

 

DEBUILD T/A

he

) sce

Unit 1/11 Project Ave,
Noosa Heads

Ph (07) 5455 5604
email:[email protected]

web:www.scg-engineers.com
ABN 40 098 481 299

 

Title:

SITE STORMWATER
DRAINAGE PLAN

 

Project

89-93 Eumundi Noosa Rd,

 

 

 

 

NOOSAVILLE
Date: Apri 22 Drawn SR Design SR
0 2 4 6 8 10 1-200 @ AT . Checked: Drg No. Rev
Tu 8
1400643 | Smee |) [S1131-SW1.1 | F.

 

 

 

 

 

Page 4

BIO-RETENTION
    BASIN
THIS BIO-RETENTION BASIN REDUCES
THE POLLUTION OF OUR WATERWAYS
BY REDUCING THE AMOUNT OF HEAVY
METALS, LITTER, SUSPENDED SOLIDS
 AND NUTRIENTS DISCHARGED INTO
         OUR WATERWAYS.




                     Issue:




                                              Unit 1/11 Project Ave,
                                              Noosa Heads
                                              Ph (07) 5455 5604




                     DEBUILD T/A
                                              email:[email protected]
                                              web:www.scg-engineers.com
                                              ABN 40 098 481 899




                         Title:




                        Project




                        Date:       Drawn                Design

                         Checked:   Drg No.                        Rev.




   Rev. - 10.06.16


[OCR of page images]
 

 

DRAWING SIZE — At

R12 GALV DOWELS @ 400
400(L) EPOXY GROUTED
100mm MIN INTO PIT.

FINISHED LEVEL
AS PER PLAN.

GATE/UID (HOT DIP GALV

WHERE STEEL) TO
/ ENGINEER'S APPROVAL.

IL. AS NOTED
ON PLAN.

 

 

 

   
   

R10 GALV DOWELS @ 400
400(L) EPOXY GROUTED
100mm MIN INTO PIT.

TELLAM PRE-CAST ——=

 

 

 

PIT OR EQUIV.
THKNESS AS AS NOTED
PER MANU. _ |_| | _ON PLAN

 

PRE-CAST STORMWATER PIT SECTION

  
 

GRADE STONE PITCHING FOR
EVEN FLOW INTO
BIO-RETENTION BED.

BLOCK RETAINING
WALL SURROUNDING
BIO-BED /DETENTION
BASIN

BIO-RETENTION BED
AS PER PLANS &
DETAILS.

RC CONCRETE HEAD WALL
WITH STONE PITCHING
SCOUR PROTECTION FOR
EVEN FLOWS INTO
BIO-RETENTION BED.

SW FLOW DISPERTION — RC _HEADWALL

TIMBER PALING FENCE

TERRACE SLAB PROVIDE SLEEPER ALONG
BASE OF PALING FENCE TO

AS PER PLANS
se [Reva FLOWS WITHIN
re Mh: SWALE

 

 

   
 

 

SWALE DRAIN,
REFER DETAIL

/B\ REAR DRAINAGE SWALE
\CSWATYPICAL SECTION

 

GATE/LID (HOT DIP GALV
-—— WHERE STEEL) TO
ENGINEER'S APPROVAL.
FINISHED LEVEL OCEANGUARD PIT INSTALLED AND

;——— MAINTAINED TO MANUFACTURERS
AS PER | SPECIFICATIONS.

 

i

=- Tfa===4

 

 

 

 

 

 

 

OVERALL
DEPTH

 

 

 

 

 

 

 

 

 

 

 

PIPE TO
OUTLET

cS

\ IL’s AS NOTED

ON PLAN.
/-—\ GPx WITH OCEANGUARD PIT INSERT
\ 7 TPICAL DETAIL

 

 

CLEARANCE
SEE DESIGN TABLE
BAG DEPTH
SEE DESIGN TABLE

 

 

 

 

 

 

 

 

 

DRIVEWAY PAVEMENT. REFER
DRIVEWAY & ACCESS PLAN

[ FOR REINFORCING.

 

st

a

 

 

 

DRAINAGE PIPE SIZES ——
AS NOTED.

 

APPROVED COMPACTED
BEDDING SAND.

———_]

 

 

 

300mm MIN THK COMPACTED
GRANULAR MATERIAL UNDER SLAB.
TRAFFICABLE AREAS

@— MIN 98% FIELD DENSITY THROUGH
BACKFILL DEPTH. D>900mm
NON-TRAFFICALBE AREAS

COMPACT IN 150mm LAYERS D>400mm

VEHICLE GUARD RAIL IN
ACCORDANCE WITH AS2890.

 

 

BIO-RETENTION FILTER MEDIA &
BATTERS TO BE PLANTED IN
ACCORDANCE WITH AUSTRALIAN
STANDARDS.

PROVIDE TURFING OUTSIDE

BLOCK RETAINING WALL BIO-RETENTION FILTER AREA.

SURROUNDING DETENTION
BASIN/BIO-BED : 10

eA

 

 

FILTER MEDIA

TRANSITION

MINIMUM HT OF
BLOCKWALLS (NON WEIR)

180 DIAM. ORIFICE TO
SIDE OF INLET PIT FIT
WITH MESH BASKET

RL11.50 MIN SURROUND

 
   
 
  

900 SQ GRATED SW INLET
PIT WITH RAISED DOME
GRATE, SET TOP OF PIT
1mm ABOVE FINISHED
SURFACE IN BED

Q100 LEVEL RL11.14m
YW

 

 

 

RL10.00

 

 

 

 

BN

 

lon
|=:

LAYER - 400mm 1S
|P «
|

LAYER - 100mm

 

 

 

LZ Zs =
BLN SLLVLLLLY

 

DRAINAGE ~~"

= LS —— FJ

  

PIPE TO GP1.
UPGRADE TO

 

LAYER - 225mm

100mm CLEAN COARSE
SAND TRANSITION
LAYER ABOVE |

GEOFAB
2256 uPVC COLLECTOR

 

 

 

 

PIPE 0.5% GRADE MIN.

AS PER PLAN

SLOTTED 100% uPVC PIPES 0.5%
GRADE MIN 750 CTRS SET IN
225 THICK 5-7mm CLEAN
GRAVEL DRAINAGE LAYER.

 

WALL AND

LL. 9.23m)

  

 

DRAINAGE. LAYER
B (HATCHED).

(A BIO-RETENTION PIT DETAIL

 

\swi7 SECTION

GALVANISED KERB ADAPTOR TO LOCAL
AUTHORITY STANDARDS AND IPWEA
STD. DRG SEQ-RS-081. CUT OUT
LAYBACK KERB AS NECESSARY TO
INSTALL GALVANISED KERB ADAPTOR
WITH NEAT, TIGHT FIT.

 

INSTALL REECE 'RHS TO PVC
ADAPTOR’ (PROD. CODE 304284),
OR APPROVED EQUIVELANT AS PER
MANUFACTURERS SPECIFICATIONS.

 

 

 

 

 

 

 

 

—— 2/125x75 x4.0 RHS
H.D. GALV. PIPES ACROSS

 

 

FOOTPATH/VERGE.

 

 

 

SECTION DETAIL

/-- SW PIPE TRENCH/PIPE BEDDING & BACKFILLING

 

\ / UNDER PAVEMENT TYPICAL SECTION

 

THIS PLAN TO BE READ IN CONJUNCTION WITH
SCG CONSULTING ENGINEERS STORMWATER
MANAGEMENT REPORT 31131(SWM)

 

LOOSE STONE PITCHING WITHIN

1000mm_ WIN SWALE OVER GEOTEXTILE BLANKET

 

TYPICAL SECTION VEGETATED SWALE

 

 

 

 

 

FALL, WW
—_ GP1 a
100 DIAM uPVC CONNECTOR
a _ PPS
TRUNK DRAIN AS INDICATED
_ — ON PLAN

/— REAR OF UNIT DRAINAGE. PIT
\.=/ TYPICAL SECTION

 

LAY BACK KERB ADAPTOR TO
EXISTING KERB DETAIL (RHS).

EXISTING 225 DIAM.

 

300 DIAM

300mm WIDE SCOUR
PROTECTION BETWEEN BLOCK

BOUNDARY

BLOCK RETAINING WALL
SURROUNDING DETENTION
BASIN/BIO-BED WEIR WALL
HT INDICATED

R.P. BOUNDARY

EXISTING GROUND
(APPROX. R.L. 10.25)

 

 

  

 

PROVIDE ABOVE SIGN IN BIO-BASIN

 

 

 

 

 

 

KERB OUTLET (2)

 

B Revisions for Council RFI

01.06.22

 

A Revisions for Council RFI

49.05.22

 

Revision

 

Description

Date

 

 

Iss

* FOR APPROVAL

 

DO NOT SCALE FROM THIS DRAWING

The design and associated details contained on this and associated
drawings are copyright and are not to be used or reproduced without
the written permission of SCG Consulting Engineers.

 

DEBUILD T/A

C) S06

Unit 1/11 Project Ave,
Noosa Heads

Ph (07) 5455 5604
email:[email protected]

web:www.scg-engineers.com
ABN 40 098 481 299

 

Title:

STORMWATER DETAILS

 

Project

89-93 Eumundi Noosa Rd,

 

 

 

 

RPEQ 5835

 

S Richardson at

NOOSAVILLE
Date: Apri 22 Drawn SR Design SR
Checked: Drg No. Rev

31131-SW1.2 | B.

 

 

 

 

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.