Excavation shall include the removal of all materials of whatever nature
encountered including all obstructions of any nature that would interfere with the
proper execution and completion of the work. The removal of these materials shall
conform to the lines and grades shown or ordered. The Contractor shall supply,
place and maintain all supports and shoring that may be required for the sides of the
excavation, and all pumping, ditching or other approved measures for the removal
or excl usion of water, including taking care of storm water and waste water reaching
the site of the work from any source so as to prevent damage to the work or
adjoining property. The walls and faces of all excavations in which workers are
exposed to danger from unstable ground shall be guarded against by a shoring
system, sloping of the excavation, or some other acceptable method. The
Contractor shall supply, install and maintain such sheeting, bracing, etc. as may be
necessary to protect the workers and to prevent any movement of earth which could
cause injury or delay of work.
F6.2 General trenching
Trenches shall be excavated with clean cut sides, free from all protuberances and
with the bottoms evenly graded. Trench widths shall either be 600 or 900 mm as
detailed on the Contract Drawings.
Depths shall also be as detailed on the Contract Drawings except that the Contractor
shall allow for any increase in depth necessary where buried obstructions are
encountered.
Trenches shall be of sufficient depth to allow a mmlmum separation from any
obstruction of 100 mm for cables and 75 mm for all cable conduits. The minimum
trench width shall be 300 mm greater than the outside conduit diameter at any point.
F6.3 Main line trenching
Main line trenches, situated on the mains side of the road shall have the nearside of
the trench 1.5 m from the survey boundary. Accuracy for line shall be +25 mm/-
25 mm.
Where the line is not clearly defmed, either by the survey boundary or on the
Contract plans (e.g. at road junctions and corners), the Contractor shall obtain
direction from the Superintendent.
F6.4 Service trenching
Trenches for service connections from the main line, both to the mains side and the
service side shall be positioned in accordance with the Contract Drawings showing
the
required or typical connection layout. Unless otherwise directed by the
Superintendent on the mains side, the trench shall be at right angles to the main line
to the side of service pillar (or pit) and on the service side the service trench shall
join the main trench to the side of the service pillar (or pit) in a straight line from the
main trench. Where there is any doubt as to the intended location of any service
connection the Contractor shall obtain direction from the Superintendent.
If the Contractor elects to construct roadways before digging the main cable
trenches, he shall install conduits provided by ETSA for all road crossings prior to
road construction.
AEVI07.201-TD-CV-SPC-000J Rev. A F-4
10 July 2012 KBR.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application IDAS Form 1 & 6 - OPW12/0439Related documentApplication case desk ↗
About this file
- File size
- 12.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.