2021-09-13 GC Agenda - Item 11 - Attachment 1 - Noosa Oyster Project Annual Report 2

of 68

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Table 7: Total project expenditure

                                                  Total        FY20          FY21          Total      Remaining
 PROJECT COSTS                                   Budget     Expenditure   Expenditure   Expenditure    Budget
                                                    $            $             $             $           $

 Reef Building
 Bathymetric, hydrological assessments,
 oyster bed engineering, rock and shell          861,982       100,915       256,678       357,593      504,389
 material procurement, construction and
 engineering assessments.

 Hatchery and seeding
 Procurement of oysters, hatchery/farmer
 engagement, shell transport, recycled           293,332        29,575       104,913       134,488      158,844
 shells collection, permitting, record
 keeping and reporting.
 Reef integrity and performance
 assessment
 Pre-substrate deployment site
 assessments (bottom ecology, surface
 profiles, oyster densities, vulnerable          580,289        24,325       140,001       164,326      415,963
 habitats mapping (e.g. seagrass), river uses
 analysis (e.g. boating, fishing), data
 analysis, WHS and safety plans,
 operational equipment, periodic reports.
 Community engagement, volunteering and
 media
 Community engagement products,
 engagement coordination, sub-contractor
 identification, contracting and
 management, volunteer briefings,                424,397       177,722       171,912       349,634       74,763
 volunteer recruitment, stakeholder
 meetings, personal protective equipment,
 media statements, media management
 and education material production and
 distribution.
 Project Management
 Production of Project Management Plan,
 Monitoring Evaluation and Reporting Plan,
 Communications Plan, project risk               240,000       102,017       135,947       237,964        2,036
 assessments, plan and risk refinements
 and revisions, government permitting,
 legal, technical science support

 Total expenditure                              2,400,000      434,554       809,452     1,244,006    1,155,994




                                                                                                              49
Log in to download the original file

2021-09-13 GC Agenda - Item 11 - Attachment 1 - Noosa Oyster Project Annual Report 2(PDF, 8MB).pdf · 8.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.