Annex 1: Goals, objectives and deliverables of the project
                      To improve the environmental health of the Noosa River Estuary through active
Project Goal          restoration and conservation activities that engage the Noosa Community in meaningful
                      conservation and support economic and community wellbeing.
                                                  Expected
                                                  completion date                                 Party
Objectives            Deliverables                (from 1 July 2019 Measurable outcomes           responsible for
                                                  unless otherwise                                Deliverable
                                                  stated)
                      (A1.1) A Technical
                      Advisory Group (TAG) is
                      established to provide                          Terms of reference for
                                                                                                  TNC
                      project oversight. This                         the TAG developed, TAG
                                                   3 months from
                      will include a clear terms                      is established and at least
                                                   appointment of
                      of reference and consist                        one meeting held.
                                                   Project Manager
                      of representatives from
                      key stakeholders (NSC,                          Evidence of Kabi Kabi
                                                                                                  TNC
                      TNC, Kabi Kabi and at                           involvement.
                      least two other
                      independent parties).
                      (A1.2) Appointment of
A-1 Project           dedicated project
establishment and     manager who is a marine                         Appointment of Project
                                                   6 months
management            biologist with extensive                        Manager to oversee the      TNC
                      project management                              Project.
Establish effective   experience, for the term
project               of the Agreement.
governance,           (A1.3) A Project
management,           Implementation Plan
communication         detailing at a minimum:
and reporting         A detailed risk
sufficient to         assessment associated
successfully          with the project.                               A project
implement shellfish   A communications and                            implementation plan
                                                                                                  TNC
restoration project   media plan, outlining                           produced by TNC and
                      media protocols,                                approved by NSC.
                      opportunities and the        6 months
                      role of TNC and NSC.                            Approval for the plan (if
                      A monitoring, evaluation                        acceptable) provided in
                      and reporting plan which                        writing by NSC by no
                                                                                                  TNC & NSC
                      identified ecological and                       later than two months
                      social monitoring                               after delivery.
                      programs, how they will
                      be reported on and how
                      this will fed back into the
                      project.




                                                                                                                51
Log in to download the original file

2021-09-13 GC Agenda - Item 11 - Attachment 1 - Noosa Oyster Project Annual Report 2(PDF, 8MB).pdf · 8.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.