To improve the environmental health of the Noosa River Estuary through active
Project Goal restoration and conservation activities that engage the Noosa Community in meaningful
conservation and support economic and community wellbeing.
Expected
completion date Party
Objectives Deliverables (from 1 July 2019 Measurable outcomes responsible for
unless otherwise Deliverable
stated)
works/activities for to Noosa Council by TNC
future period. in conjunction with
Noosa Council officers
for its approval for
endorsement within 90
days of the end of each
financial year during the
term of the Agreement,
and (if acceptable)
approved by Noosa
Council.
6 monthly status and
(A1.6) 6 monthly status progress reports, and
and progress reports financial statement, are
which address, at a produced, endorsed by
minimum: the Technical Advisory
Progress against Group, and provided to
deliverables and NSC, within 30 days of
monitoring and 6 monthly end of each six (6) month TNC
evaluation report. period. Reports and
6 monthly financial financial statements due
statements including at the end of the
a statement of Project financial year may be
income/funding and included with annual
expenditure reports and the final
report.
(A2.1) Oyster reef
restoration suitability Habitat suitability model
A-2: Site selection model incorporating which incorporates
physical parameters of 12 months industry, Kabi Kabi
TNC
Identify suitable oysters and public and knowledge and public
restoration sites for industry usage, access interests.
Phase II and Phase etc. to identify priority
III and appropriate sites for restoration.
reef design that Outcomes:
(A2.2) Obtain necessary
minimize estuary- (a) Obtain all required
State government
user conflict whilst State government
permits/authorities 13(a) - TNC
optimizing reef permits/authorities for
including particular 18 months
rehabilitation installation of oyster
resource allocation
reefs.
authority, for oyster reef 13(b) – NSC
(b) Obtain all required
restoration
Local government
53
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.