Request to Change Development Approval
Attached to the e-mail Request to Change Development Approval MCU14/0102.04.
Substantially different development
The statutory guideline 06/09 provides examples of what may be considered to be substantially
different development. These examples are provided below:
A change may result in a substantially different development if the proposed change:
involves a new use with different or additional impacts
results in the application applying to a new parcel of land
dramatically changes the built form in terms of scale, bulk and appearance
changes the ability of the proposal to operate as intended. For example, reducing the size of a
retail complex may reduce the capacity of the complex to service the intended catchment
removes a component that is integral to the operation of the development
significantly impacts on traffic flow and the transport network, such as increasing traffic to the site
introduces new impacts or increases the severity of known impacts
removes an incentive or offset component that would have balanced a negative impact of the
development
impacts on infrastructure provision, location or demand.
In our opinion, the changes proposed do not result in a substantially different development.
Concurrence agencies
There were no concurrence agencies for the original application and no referrals would be triggered by
the changes proposed.
Assessment levels and likelihood of objections
The original application was impact assessable. The proposed changes will not affect the level of
assessment. Only one objection was recorded against the original application. That objection was
primarily concerned with parking supply associated with the possible tyre and mechanical shop. The
changes proposed would not likely cause a person to object.
Prohibited development
The proposed amendments do not involve prohibited development.
For these reasons it is considered that the proposed changes constitute a Permissible Change to the
approved development. On this basis it is considered that the request can be dealt with pursuant to
sections 369 – 377 of SPA. We look forward to Council’s decision on this request.
Should you have any questions with respect to the above, please do not hesitate to contact me direct.
Yours faithfully
PROJECT URBAN
Peter Folker
Director
Email: [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.