07/2555 DECISION NOTICE - Change to Approval [As Published] · 142007.2555.02

of 16

Text shows just the words. Original shows the document exactly as it was published.

      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Council’s CEO and shall forthwith rectify the damage to that property or
      facility at its cost and to the satisfaction of the Council’s CEO.
      All rectification works are to be completed prior to the commencement of the use or,
      alternatively, the Applicant may request the Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to the Council prior to the
      commencement of the use.
      In the case of any emergency the Council shall be entitled to rectify such damage at the cost
      of the Applicant, such cost being paid prior to the commencement of the use.
23.   The development of the site shall be carried out in such a manner as to prevent dust and/or
      sand nuisance to residents and/or tenants in the vicinity of the development.
24.   Construction work and other associated activities are permitted only during the hours of 7.00
      am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
      except where extended hours are approved by the Council’s CEO or his nominee.
25.   All signage, including that for safety during construction shall be in accordance with the
      Manual of Uniform Traffic Control Devices and Transport Infrastructure (Roads) Act.
26.   Sediment and erosion control measures must be in place prior to works commencing. If such
      measures are not in place or are not satisfactory, “on the spot “fines may be issued. Such
      fines can be issued if sediments from the site are found to enter or have the potential to enter
      Council’s stormwater system or natural waterways. Although the sediment and erosion control
      measures have been approved on drawing No. N-B7416-C1-01-02B and Site Based
      Sediment & Erosion Management Plan by Opus Qantec McWilliam revised 25 February
      2008, it is the site's supervising engineer who is responsible for ensuring that the sediment
      and erosion control measures have been designed by an RPEQ or CPESC and constructed:
      a.   i.     In accordance with "best practise" methods,
      b.   ii. Revised by an RPEQ or CPESC to address the issues raised by changes in the
           projected construction schedule and methods,
      c.   iii.   Revised to address predicted rainfall events, and
      d.   iv.    Achieve the desired environmental outcomes.
      Council’s CEO may request further controls to be installed should approved measures be
      inefficient.
27.   The owners of the subject property shall maintain the grease/oil arrestor pits/gross pollutant
      traps in accordance with the manufacturers’ specifications.
28.   The owners of the subject property shall inspect the grease/oil arrestor pits/gross pollutant
      traps on a weekly basis and after each storm event.
29.   The owners of the subject property shall enter into an ongoing maintenance contract with a
      Registered Contractor to clean and maintain the grease/oil arrestor pits/gross pollutant traps
      on a regular three monthly cycle and on a “On Call” basis in the case of an emergency.
30.   The management and maintenance of the grease/oil arrestor pits/gross pollutant traps shall be
      included in the Community Management Scheme for the completed development.
31.   All stormwater drainage lines including private drainage lines (also known as inter-allotment
      drainage lines) or as otherwise approved by Council’s CEO shall be inspected by closed
      circuit television (CCTV) at the completion of all works and immediately prior to acceptance
      ‘On Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of
      this inspection.


                                                                                           Page 4 of 16

Used in these records

About this file

File size
88 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2555 DECISION NOTICE - Change to Approval [As Published].pdf · 88 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.