Council archive · source document
07/2555 DECISION NOTICE - Change to Approval [As Published] · 142007.2555.02
40. Prior to the pre-start meeting a 2-strand wire fence is to be erected around the boundary of the
‘disturbed areas’ shown in the Department of Natural Resources and Water Vegetation
clearing application decision notice – approval 2007/008064 and in accordance with the
conditions of approval 2007/008064 and any trees being retained within the ‘disturbed areas’
at a radius of 3 metres. This exclusion fence is to be adequately signed as such and is to be
maintained until all works have been completed.
41. Prior to any construction / clearing work commencing, a pre-start inspection is to be conducted
with Council’s Planner (Land Use) and Ecologist.
42. Trees authorised for removal shall be clearly marked prior to the commencement of tree
clearing, with the removal operation to be closely monitored by an appropriately qualified
person in accordance with the approved plans.
43. Vegetation removal, tree felling and lopping adjacent to vegetation to be retained in the
environmental covenant areas shall be undertaken in an environmentally sensitive manner to
avoid damaging surrounding vegetation, trees and habitat.
44. A qualified and experienced wildlife spotter shall be on site at all times immediately prior to and
during tree/branch and vegetation removal work. Prior to felling or lopping all trees are to be
checked for wildlife (eg. Koalas, cockatoos, possums). If wildlife are present, the tree shall not
be felled or lopped until the wildlife has left the tree.
45. Prior to vegetation clearing an onsite meeting with the fauna spotter catcher is to be conducted
with Council’s Planner (Land Use) and Ecologist.
46. The fauna spotter catcher shall comply with all conditions of the Decision Notice and the
implementation strategy.
47. Any pruning of limbs on trees being retained shall be in accordance with an arborist’s report
and shall be approved by Council prior to work commencing.
48. Weed growth is to be monitored in the cleared areas during construction, with any emergent
weed species to be removed.
49. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site:-
a. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a minimum
of 10 metres between edges of heaps.
b. Disposal for firewood.
c. Disposal for landscaping purposes.
d. Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
e. The Applicant is advised that burning off is an unacceptable method of disposal.
Weed & Pest Removal
50. In order to protect the ecological values of the site the following apply:
a. prior to first entering the site, all construction machinery and vehicles shall be washed
down to remove soil that may contain weed seeds, soil pathogens and pest species;
b. all imported fill, soil, gravel and other construction and landscaping materials shall be
weed, pest and disease free and certified as such by the supplier;
c. all mulch used on the site shall be weed, pest and disease free and certified as such by
the supplier;
d. all mulch produced on-site by mulching cleared vegetation and trees shall specifically
exclude material (particularly seeds) from weed species (eg. lantana, asparagus fern and
umbrella trees); and
Page 6 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
07/2555 DECISION NOTICE - Change to Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 88 KB (small file)
- File type
No other editions are linked here.