              iii.     proposed fencing to the site during the construction phase of the
                       development;
              iv.      approval of the Traffic Management Control Plan by the Department of
                       Transport and Main Roads (DTMR) for any works on State controlled roads;
                       and
              v.       provision for worker car parking.
       b.     maintenance and protection of water quality and existing drainage lines through
              the construction site, through the implementation of appropriate erosion and
              sediment control measures;
       c.     works programme identifying key components of the works and their respective
              durations;
       d.     establishment of a communication protocol with the general public, adjoining
              owners, emergency services and local businesses to advise of agreed
              construction times, impacts on traffic, services and other relevant issues;
       e.     Include a post out to the local residents and businesses advising of the proposed
              development, the expected time frames and the site contact details;
       f.     Include signage in prominent locations on the boundaries of the site advising of
              the proposed development, the expected time frames and the site contact details;
       g.     identification of complaint management procedures including:
              i.       contact details for the on-site manager; and
              ii.      dispute resolution procedures.
       h.     details on the location of external fill sites/sources, the haulage route, type of
              vehicle to be utilised during filling operations and frequency of usage. NB any
              damage to the existing road system as a result of haulage operations shall be fully
              repaired at the applicant’s expense; and
       i.     it is acknowledged that the preliminary Construction Management Plan will be a
              draft document requiring finalisation upon appointment of the Principal Contractor
              employed to construct the works and a final document will be required to be
              submitted at the Pre-Start Meeting for the project.
       Qualified Person
1.     For the purpose of preparing a Landscape Plan, a qualified person is considered to be
       a landscape architect, landscape designer and/or horticulturist with a minimum of 3
       years current experience in the field of landscape design.
2.     For the purpose of preparing an Arborist Report, a qualified person is considered to be
       a person with either:
       a.     ISA certification; or
       b.     a Diploma of Arboriculture in addition to a minimum of 3 years current experience
              in the field of arboriculture.
3.     For the purpose of preparing a Rehabilitation Plan, a qualified person is considered to
       be a landscape architect or ecologist with a minimum of 3 years current experience in
       the field of landscape design.
4.     For the purpose of preparing a Fauna Management Plan, a qualified person is
       considered to be an ecologist with a minimum of 3 years current experience in the field
       of fauna assessment and management.




                                                                                         8274014_1

3459-9154-4892, v. 1
                                                                                         8309250_1




                                                                                                     13
Log in to download the original file

Sealed Judgement.pdf · 118 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.