The time of concentration (Tc) of 7 minutes was determined using figure 4.4 – Overland sheet flow times (refer to
Figure 2-3) in accordance with Table 4.6.6 of QUDM. This approach provides a reliable estimate of the travel time
for runoff from the hydraulically most distant point in the catchment to the outlet.
A maximum flow path length of 34.0 m was adopted, based on survey data collected by Eagle Survey Pty Ltd in
2025 (refer to Figure 2-2).
To refine the analysis, the following factors were incorporated to ensure accuracy and representativeness of the
stormwater design:
• Surface roughness and vegetation cover, which influence flow resistance and travel time
• Topographic gradients, confirming alignment between flow velocities and assumed conditions
• Site hydraulic connectivity, including potential depressions or ponding areas, verifying the
appropriateness of the adopted Tc.
Figure 2-2 Max overland flow path
Figure 2-3: Overland sheet flow times (QUDM, 2025)
17 BOTTLEBRUSH AVENUE, NOOSA HEADS
7 January 2026 P a g e |7
Stormwater Management Plan
Client Reference: P0433-25-001
Prepared for Made Capital PTY LTD
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
P0433-25-001_17_Bottlebrush_Avenue_SWMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 15.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.