Key Observations
1. Increase in Flow Depths and Velocities
• The developed scenario shows higher water levels across all storm events, particularly at
constricted sections of the drainage network.
• Flow velocities have increased, indicating a higher runoff volume due to reduced permeability.
2. Peak Discharge Variations
• Peak discharge rates in the developed scenario have increased substantially, particularly for
higher return period storms (e.g., 1% AEP).
• The most significant changes occur at sections with concentrated overland flow paths,
suggesting increased runoff from new impervious surfaces.
3. Impact of Increased Impervious Area
• The development introduces more impervious surfaces (e.g., roads, driveways, rooftops),
reducing infiltration and increasing direct runoff.
• The loss of natural detention and permeability results in quicker times of concentration and higher
peak flows.
Table 3-1: Comparison of Pre-Development vs. Unmitigated Post-Development Peak Flows
Storm Event (AEP) Pre-Development Peak Flow Post-Development Peak Increase %
(m³/s) Flow (m³/s)
63.2% 0.011 0.013 8%
50% 0.013 0.015 7%
20% 0.020 0.022 5%
10% 0.024 0.027 6%
5% 0.028 0.031 5%
2% 0.034 0.037 4%
1% 0.038 0.042 5%
17 BOTTLEBRUSH AVENUE, NOOSA HEADS
7 January 2026 P a g e | 13
Stormwater Management Plan
Client Reference: P0433-25-001
Prepared for Made Capital PTY LTD
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
P0433-25-001_17_Bottlebrush_Avenue_SWMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 15.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.