2021-07-12 General Committee Meeting Agenda

of 28

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

                       AGENDA


             General
         Committee Meeting


                Monday, 12 July 2021

                   commencing at 10am
         Council Chambers, 9 Pelican Street, Tewantin



Committee:   Crs Frank Wilkie (Chair), Karen Finzel, Joe Jurisevic, Amelia
             Lorentson, Clare Stewart, Brian Stockwell, Tom Wegener



                    “Noosa Shire – different by nature”
Log in to download the original file

2021-07-12 General Committee Meeting Agenda(PDF, 2MB).pdf · 1.7 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 27 sections

Section 2

GENERAL COMMITTEE MEETING AGENDA                                   12 JULY 2021


TABLE OF CONTENTS

ITEM                                                                    PAGE

1      ATTENDANCE & APOLOGIES                                               3

2      CONFIRMATION OF MINUTES                                              3

3      PRESENTATIONS                                                        3

4      DEPUTATIONS                                                          3

5      ITEMS REFERRED FROM COMMITTEES                                       3

       1   MCU19/0119.02 OTHER CHANGE TO A DEVELOPMENT APPROVAL FOR A
           MATERIAL CHANGE OF USE FOR MULTIPLE HOUSING - TYPE 2 DUPLEX
           AND SHORT-TERM ACCOMMODATION AND OPERATIONAL WORKS
           (DRAINAGE WORK, STORMWATER, EARTHWORKS, LANDSCAPING,
           CARPARKING & ACCESS) 2 NOLA STREET, NOOSAVILLE                   3

       2   RAP21/0016 APPLICATION FOR A REFERRAL AGENCY RESPONSE FOR A
           DWELLING HOUSE (FILLING BEYOND 3M OF THE FOOTPRINT OF
           BUILDING) AT 11 CHURCH ST, POMONA                                3

       3   MCU20/0149 APPLICATION FOR MATERIAL CHANGE OF USE FOR SHORT-
           TERM ACCOMMODATION AT 29 FERGUSON ST, SUNSHINE BEACH             3

       4   MCU15/0069.01 OTHER CHANGE TO A DEVELOPMENT APPROVAL FOR A
           MATERIAL CHANGE OF USE FOR MULTIPLE HOUSING - TYPE 2 DUPLEX
           AND SHORT-TERM ACCOMMODATION AT 1/39 DUKE STREET, SUNSHINE
           BEACH                                                            3

       5   NOOSA CYCLING AND WALKING STRATEGY AND IMPLEMENTATION PLAN
           ENDORSEMENT                                                      3

6      REPORTS DIRECT TO GENERAL COMMITTEE                                  4

       6   MCU21/0046 – APPLICATION FOR A MATERIAL CHANGE OF USE – SHORT-
           TERM ACCOMMODATION AT 2 LOWRY ST, PEREGIAN BEACH                 4

       7   T000042 – TEWANTIN BYPASS STAGE 1 – WATERMAIN RELOCATION         17

       8   TOURISM FUNDING AGREEMENT REVIEW PROCESS                         24

7      CLOSED SESSION                                                 28




                                                                  Page 2 of 28

Section 3

GENERAL COMMITTEE MEETING AGENDA                                                       12 JULY 2021



1   ATTENDANCE & APOLOGIES


2   CONFIRMATION OF MINUTES
    The Minutes of the General Committee Meeting held on 14 June 2021 be received and
    confirmed.

3   PRESENTATIONS
    Nil.

4   DEPUTATIONS
    Nil.

5   ITEMS REFERRED FROM COMMITTEES

    PLANNING & ENVIRONMENT COMMITTEE

    1      MCU19/0119.02 OTHER CHANGE TO A DEVELOPMENT APPROVAL FOR A
           MATERIAL CHANGE OF USE FOR MULTIPLE HOUSING - TYPE 2 DUPLEX AND
           SHORT-TERM ACCOMMODATION AND OPERATIONAL WORKS (DRAINAGE
           WORK, STORMWATER, EARTHWORKS, LANDSCAPING, CARPARKING &
           ACCESS) 2 NOLA STREET, NOOSAVILLE
           (Planning & Environment Committee Agenda, 6 July 2021, Item 1, Page 4)
           Reason for referral – significance of the issue.

    2      RAP21/0016 APPLICATION FOR A REFERRAL AGENCY RESPONSE FOR A
           DWELLING HOUSE (FILLING BEYOND 3M OF THE FOOTPRINT OF BUILDING) AT
           11 CHURCH ST, POMONA
           (Planning & Environment Committee Agenda, 6 July 2021, Item 2, Page 22)
           Reason for referral – for further consideration.

    3      MCU20/0149 APPLICATION FOR MATERIAL CHANGE OF USE FOR SHORT-TERM
           ACCOMMODATION AT 29 FERGUSON ST, SUNSHINE BEACH
           ((Planning & Environment Committee Agenda, 6 July 2021, Item 3, Page 35)
           Reason for referral – significance of the issue.

    4      MCU15/0069.01 OTHER CHANGE TO A DEVELOPMENT APPROVAL FOR A
           MATERIAL CHANGE OF USE FOR MULTIPLE HOUSING - TYPE 2 DUPLEX AND
           SHORT-TERM ACCOMMODATION AT 1/39 DUKE STREET, SUNSHINE BEACH
           (Planning & Environment Committee Agenda, 6 July 2021, Item 3, Page 60)
           Reason for referral – significance of the issue.


    SERVICES & ORGANISATION COMMITTEE

    5      NOOSA CYCLING AND WALKING STRATEGY AND IMPLEMENTATION PLAN
           ENDORSEMENT
           (Services & Organisation Committee Agenda, 6 July 2021, Item 11, Page 28)
           Reason for referral – significance of the issue.

                                                                                       Page 3 of 28

Section 4

GENERAL COMMITTEE MEETING AGENDA                                                        12 JULY 2021


6   REPORTS DIRECT TO GENERAL COMMITTEE

    6      MCU21/0046 – APPLICATION FOR A MATERIAL CHANGE OF USE – SHORT-TERM
           ACCOMMODATION AT 2 LOWRY ST, PEREGIAN BEACH

    Author      Development Planner, Blake Coulston
                Environment and Sustainable Development Department

    Index       ECM / Application / MCU21/0046

    Attachments         1.     Floor Plans


    APPLICATION DETAILS

    Applicant                       Kathryn Elisabeth Payne TTE
                                    Simon Alan Payne TTE

    Proposal                        Material Change of Use - Short-term accommodation
    Properly Made Date              18 March 2021

    Information Request Date        Not applicable

    Information Response Date       Not applicable

    Decision Due Date               9 July 2021

    Number of Submissions           Eighty-six (86)

    PROPERTY DETAILS

    Property Address                2 Lowry St Peregian Beach Qld 4573

    RP Description                  Lot 15 P 93124

    Land Area                        607.0000 m²

    Existing Use of Land            Dwelling House

    STATUTORY DETAILS

    SEQRP Designation               Urban Footprint

    Zone                            Medium Density Residential Zone

    Precinct                        Not applicable

    Local Plan Area                 Coastal Communities

    Overlays                        Acid Sulfate Soils (Above 5 metres AHD to 20 metres AHD); and
                                    Bushfire Hazard (Potential Impact Buffer).
                                    (Not Applicable)

    Assessment Type                 Impact

    RECOMMENDATION
    That Council note the report by the Development Planner to the General Committee Meeting
    dated 12 July 2021 regarding Application No. MCU21/0046 for a Development Permit for
    Material Change of Use - Short-term Accommodation situated at 2 Lowry St Peregian Beach
    and:

                                                                                     Page 4 of 28

Section 5

GENERAL COMMITTEE MEETING AGENDA                                                      12 JULY 2021


   A.   Refuse the application in accordance with the following conditions:
        1.    The proposal is not consistent with 3.2.4 Housing to meet diverse needs of the
              community and 3.3.3 Housing Choice (n) of the Strategic Framework, as increased
              visitor accommodation is not sought or needed for the area and visitor
              accommodation will further erode the permanent housing in the area, impacting
              permanent resident amenity.
        2.    The proposal is not consistent with 7.2.6.2 Purpose and Overall Outcome (2)(o)
              and Performance Outcome PO1, PO2 & PO15 of the Coastal Communities Local
              Plan Code as:
              i.     The extent of visitor accommodation has started to erode the available
                     supply of permanent housing in the local plan area.
              ii.    The proposal seeks to establish a short-term accommodation in an area
                     which is predominantly permanent residential dwellings; and
              iii.   Additional visitor accommodation in the area is likely to result in detrimental
                     impacts on the residential neighbourhood and amenity of permanent
                     residents.
        3.    The proposal is not consistent with 9.3.5.2 Purpose and Overall Outcomes (1) and
              (2)(f) of the Visitor Accommodation Code as:
              i.     The proposed visitor accommodation is not appropriately located in Peregian
                     Beach being in an area that is predominantly home to permanent residents
                     and consequently does not integrate well into the area.
              ii.    The proposed visitor accommodation is likely to detract from the amenity
                     enjoyed by residents given resident’s reasonable expectations for the area.
        4.    The proposal is not consistent with 6.3.2.2 Purpose and Overall Outcomes (2)(a)
              and (h) of the Medium Density Residential Zone Code as:
              i.     The proposal seeks to establish a new short-term visitor accommodation
                     facility within a dwelling and is not located within a well-established resort or
                     holiday units.
              ii.    There are a number of sites advertised as being available for visitor
                     accommodation in the immediate neighbourhood and zoned medium density
                     residential.
        5.    There is no need for additional short term accommodation in the area.
   B.   Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.


   REPORT
   1.   PROPOSAL
   The application is seeking to obtain a Development Permit for Material Change of Use – Short-
   term Accommodation for 2 Lowry Street, Peregian Beach formally known as Lot 15 of P93124.
   The development consists of repurposing the existing two storey dwelling house for Short-term
   Accommodation, with no additions or alterations to the building itself. The key components of
   the use are:
       The Short-term Accommodation use will utilise 4 bedrooms;
       Two (2) persons per bedroom, and eight (8) in total;
       A local property manager will oversee the letting, management and maintenance of the
        premises;


                                                                                      Page 5 of 28

Section 6

GENERAL COMMITTEE MEETING AGENDA                                                    12 JULY 2021


      Management of the property will be in line with Noosa Council Local Laws regulations
       for short-term rental properties;
      A Code of Conduct and Management Agreement will be provided to all guests;
      All guests must agree to the rules of the property at the time of booking;
      The 2 bay garage and associated driveway is provided to guests for parking;
      No events, weddings, parties, or the like are to occur on the premises;
      The alfresco and pool are located at the rear of the property and screened from view by
       existing landscaping and fencing;
      The property is fully fenced and landscaped.




                                     Figure 1 – Locality




                                                                                    Page 6 of 28

Section 7

GENERAL COMMITTEE MEETING AGENDA                                                 12 JULY 2021




                                      Figure 2 – Floor Plan

   2.   SITE DETAILS
   2.1. Background
   A Private Building Certifier has approved the dwelling house on the 9 June 2006. The dwelling
   house contains: 4 bedrooms, 2 bay garage, study room, dining room, living room, home
   theatre, kitchen, and an alfresco area.
   A copy of the approved site plan is detailed below:



                                                                                 Page 7 of 28

Section 8

GENERAL COMMITTEE MEETING AGENDA                                                  12 JULY 2021




                                      Figure 3 – Site Plan

   2.2. Site Description
   The subject site is located on the corner of Lowry St and David Low Way, gaining vehicle
   access from Lowry Street.
   The four bedrooms are located on the top floor whilst the garage, living and dining areas are
   located on the ground floor of the premises.
   Private open spaces associated with the dwelling house are located at the rear of the property
   (opposite to the Lowry Street frontage).
   2.3. Surrounding Land Uses
   The subject site has two adjoining neighbours: 4 Lowry Street & 53 Kestrel Crescent, both of
   which are used as Dwelling Houses. The site is also in proximity to the following holiday
   accommodation (located on the other side of David Low Way): Peregian Court, Beachcomber
   Peregian Beach, Hideaway Noosa Men’s Only Beach resort, Glen Eden Beach Resort, and
   The Retreat Beach Houses.




                                                                                 Page 8 of 28

Section 9

GENERAL COMMITTEE MEETING AGENDA                                                          12 JULY 2021




        Figure 8 - Zone Map, with the area zoned Medium Density Residential shown in darker pink

   3.     ASSESSMENT
   3.1. Instruments for Statutory Assessment
   Under the Planning Act 2016 the application must be assessed against each of the following
   statutory planning instruments to the extent they are relevant to the development:
         State Planning Policy;
         South East Queensland Regional Plan;
         Planning Regulation 2017;
         Noosa Plan 2020.


                                                                                          Page 9 of 28

Section 10

GENERAL COMMITTEE MEETING AGENDA                                                   12 JULY 2021


   3.2. State and Other Statutory Instruments
   State Planning Policy
   Noosa Plan 2020 is generally consistent with the State Planning Policy July 2017 (SPP) and
   the SPP raises no further issues relevant to the proposed development.
   South East Queensland (SEQ) Regional Plan
   The site is located within the Urban Footprint of the SEQ Regional Plan. The proposal is
   consistent with the regional policies of the SEQ Regional Plan.
   Planning Regulation 2017
   The proposal is for an urban activity within the Urban Footprint and is consistent with the
   assessment benchmarks contained in the Planning Regulation 2017 for the SEQ Region.
   3.3. Statutory Instruments – Planning Scheme
   The application must be assessed against the entire Noosa Plan 2020 to the extent the
   provisions are relevant to the development.
   Strategic Framework
   The Noosa Plan 2020 includes Strategic Outcomes which seek that neighbourhoods of
   permanent housing are protected from short term visitor accommodation that would impact on
   the amenity enjoyed by residents. The planning scheme also seeks to protect areas for visitor
   accommodation with a range of accommodation styles envisaged to support the local tourism
   industry.
   The strategic intent outlines that tourism is a key sector of the Noosa economy and will
   continue to be so into the future. Key visitor areas includes: Hastings Street, Gympie Terrace,
   Noosa River, Tewantin Marina, Noosa National Park, Sunshine Beach, Peregian Beach,
   Noosa North Shore and the Hinterland. While sustainable tourism is supported as an ongoing
   economic driver, the planning scheme identifies that encouraging and developing new priority
   sectors is required to develop an economy less reliant on tourism and population driven
   industries.
   Growing of the economy is not a ‘development at all cost’ scenario but rather a dedicated plan
   to grow the value of priority industry sectors, support the social and environmental values of
   the community, and enhance quality of life.
   The proposed short term accommodation supports the strategic intent of Noosa’s tourism by
   providing an alternative form of visitor accommodation to resort, motel development etc.
   However, the characteristic of the surrounding area is predominately residential with a sense
   of community. The short-term accommodation cannot be located in such a neighbourhood
   without degrading the amenity enjoyed by residents, as the characteristic of the neighbourhood
   contributes to the amenity.
   Locality Provisions
   The subject site is located in the Coastal Communities Local Plan Area and is zoned Medium
   Density Residential. The proposed use is identified as a consistent use with the zone and is
   required to follow an impact assessable application process.
   The Medium Density Residential Zone Code, the Coastal Communities Local Plan Code and
   Visitor Accommodation Code include provisions which address the potential impacts of short
   term accommodation. The relevant provision are:
   Coastal Communities Local Plan Code
   7.2.6.2 Purpose and Overall Outcomes
           (m)   Sites identified for tourist accommodation are retained and developed for that
                 use to maintain a diversity and choice of visitor accommodation and affordability
                 in the local plan area.

                                                                                 Page 10 of 28

Section 11

GENERAL COMMITTEE MEETING AGENDA                                                     12 JULY 2021


             (o)   Development in the Medium Density Housing zones accommodates a greater
                   diversity in housing types including dual occupancies, multiple dwellings,
                   retirement facilities and residential care facilities.
   PO1
   Development enhances the role of the coastal communities as a beachside residential area
   which also include a considerable amount of visitor accommodation.
   PO2
   Development contributes to the lifestyle and amenity of residents and visitors in the coastal
   communities.
   PO14
   Development provides a diversity of types and styles of visitor accommodation to cater for a
   range of visitor experiences in close proximity to key tourist areas.
   PO15
   Visitor accommodation is not be located in areas which are predominantly permanent
   residential dwellings
   Medium Density Residential Zone code
   6.3.2.2 Purpose and Overall Outcomes
             (a)   Medium density residential neighbourhoods are predominantly home to
                   permanent residents.
             (h)   Short-term visitor accommodation is predominately provided through well-
                   established resorts and holiday units.
   6.3.2.3 Assessment Criteria
   AO6.2
   Short-term accommodation does not:
   a.     constitute a party house;
   b.     create noise that would unreasonably impact on the residential amenity enjoyed by the
          adjoining or surrounding properties.
   PO6
   Visitor accommodation is limited to formats compatible with the character and use of the area
   so as not to cause unreasonable loss of residential amenity, having regard to:
   a.     the privacy of residents on the subject property or adjoining properties;
   b.     any likely increase in noise to adjoining properties;
   c.     the scale of the use and its compatibility with the character and uses within the property
          or surrounding area;
   d.     retention of the primary residential function of an area;
   e.     the residential function and arrangement of common property;
   f.     the impact on the safety and efficiency of the local road network;
   g.     the impact of waste storage areas on the visual amenity of the area;
   h.     the location of waste storage areas in relation to sensitive land uses; and
   i.     any impact on shared vehicular access or parking.
   Visitor Accommodation Code
   9.3.5.2 Purpose and Overall Outcomes
   (b)    Visitor accommodation offers a wide range of experiences for guests both in coastal
          areas and in the hinterland;


                                                                                   Page 11 of 28

Section 12

GENERAL COMMITTEE MEETING AGENDA                                                     12 JULY 2021


   (f)    Visitor accommodation located near permanent residents does not detract from the
          amenity enjoyed by residents;
   (j)    Visitor accommodation provides for a wide range of visitors.
   PO3
   Development has a scale and density that is compatible with the intent of the zone and the
   preferred character for the local area in which it is located.
   PO4
   Visitor accommodation is located such that it preserves the safety of guests and does not
   impact on the function of infrastructure including:
   (a)    the major road network;
   (b)    the North Coast railway line;
   (c)    existing and future electricity supply infrastructure; and
   (d)    water supply and waste water treatment.
   PO12
   Sufficient on-site car parking is provided to accommodate the number and type of vehicles
   likely to be generated by the visitor accommodation having regard to the number of guests,
   staff or visitors.
   PO25
   Short-term accommodation in a single dwelling is limited to formats compatible with the
   character and use of the area so as not to cause unreasonable loss of residential amenity,
   having regard to:
   (a)    the privacy of residents on the subject property or adjoining properties;
   (b)    any likely increase in noise to adjoining properties;
   (c)    the scale of the use and its compatibility with the character and uses within the property
          or surrounding area;
   (d)    retention of the primary residential function of an area;
   (e)    the impact on the safety and efficiency of the local road network;
   (f)    the impact of waste storage areas on the visual amenity of the area or sensitive land
          uses; and
   (g)    any impact on shared vehicular access or parking.
   Officer Assessment:
   The planning scheme priorities the preservation of areas which are predominantly permanent
   residential dwellings and seeks to protect the amenity of surrounding residential areas from
   the impacts of short-term accommodation.
   The following image details the location of holiday letting facilities in the medium density
   residential zone.




                                                                                   Page 12 of 28

Section 13

GENERAL COMMITTEE MEETING AGENDA                                                     12 JULY 2021




     Figure 9 Location of holiday accommodation properties within Medium Density Residential
   Whilst acknowledging that there are a quite a number of holiday letting premises in the
   surrounding neighbourhood of medium density residential zone, there are slightly more
   permanent residential dwellings. Within the surrounding area it is also noted that a number of
   visitor accommodation facilities are located within Peregian Beach locale but located opposite
   the site in David Low Way.
   It is acknowledged that the use of the premises for short term accommodation has the potential
   to have a significant impact on the amenity of the surrounding residential area. These impacts
   are often attributed to noise, car parking and waste disposal. The requirement for a
   development application for short term accommodation provides the opportunity to regulate
   the use of the site so as to mitigate these potential impacts.
   The proposed subject site is situated away from the bulk of the holiday letting premises within
   the medium density residential zone and across David Low Way from the resorts, and the
   location of the subject site is adjacent and leads into areas of low density residential which are
   used predominately for permanent residential dwellings. PO15 of the Coastal Communities
   Local Plan Code, requires that visitor accommodation is not located in areas which are
   predominantly permanent residential dwellings.

                                                                                   Page 13 of 28

Section 14

GENERAL COMMITTEE MEETING AGENDA                                                            12 JULY 2021


   Overall Outcome (2)(o) of the Coastal Communities Local Plan Code states: Development in
   the Medium Density Housing zones accommodates a greater diversity in housing types
   including dual occupancies, multiple dwellings, retirement facilities and residential care
   facilities. The code does not envisage the extent of visitor accommodation in the medium
   density residential zone, as currently exists and there is no demonstrated need for additional
   short term accommodation in the area.
   4.    CONSULTATION
   4.1. Referral Agencies
   Not applicable
   4.2. Internal Council Referrals
   Not applicable
   4.3. Public Notification
   The application was publicly notified for fifteen (15) business days in accordance with the
   Planning Act 2016. 86 properly made submissions were received, all raising objection to the
   proposal. The following table provides a summary and assessment of the issues raised by
   submitters.
    Matters Raised                              Comments
    Concerns for vehicle safety at              The proposed use has a limit to the amount of
    intersection of David Low Way and           persons staying on site (2 persons per bedroom, 8 in
    Lowry Street                                total) and will not have any significant impacts on the
                                                intersection.
    Car parking congestion in Lowry Street      The proposed development can provide for 2 covered
    and Kestrel Crescent                        car parking spaces and 2 uncovered in the driveway.
                                                As the proposed use is only 4 bedrooms, the provided
                                                on-site car parking is likely sufficient and meets the
                                                scheme’s requirements for car parking.
    Short-term Accommodation increases          Agreed, it is likely that at times there will be more cars
    the amount of vehicles entering and         coming and going from the property then if used as a
    exiting of the property                     dwelling house.
    Noise                                       The noise could be regulated with the code of conduct
                                                and property management conditions. Outdoor
                                                entertainment areas could be restricted to minimise
                                                noise at night.
    Subject site is in close proximity to a     This is not a valid development assessment issue as it
    school bus route. (Concern for safety of    relies on the hypothetical scenario of guests
    children from strangers)                    committing criminal actions.
    Break down of the sense of community /      This concern is raised through the assessment of
    Ruining the village environment             PO15 of the Coastal Communities Local Plan Code:
                                                Visitor Accommodation is not be located in areas
                                                which are predominantly permanent residential
                                                dwellings.
    Parties                                     Were the application to be approved, the property
                                                would not be permitted to be used regularly for parties
                                                as this is a separately defined use.
    Reducing values of residential properties   Monetary concerns are not a Planning matter.
    Current lack of long term rental            It is acknowledged short term accommodation utilises
    properties                                  housing supply which could be used for other
                                                purposes and has the potential to impact on rent
                                                prices of the remaining housing stock.




                                                                                          Page 14 of 28

Section 15

GENERAL COMMITTEE MEETING AGENDA                                                     12 JULY 2021




                                     Figure 10 – Submission Locations

   5.    CONCLUSION & REASONS FOR DECISION
   The application seeks to use a dwelling house for short-term accommodation purpose. The
   dwelling house is located on the corner of David Low Way and Lowry Street. The planning
   scheme seeks to prioritise the preservation of medium density residential neighbourhoods for
   predominantly permanent residential dwellings and seeks to protect the amenity of surrounding
   residential areas from the impacts of short-term accommodation. Whilst acknowledging that
   short-term accommodation has been identified as a consistent use within the applicable zone,
   the subject site is located within the Coastal Communities area, under which the Noosa Plan
   provisions require that visitor accommodation is not located in areas which are predominantly
   permanent residential dwellings. As such, the proposal does not comply with a number of
   provisions of the Noosa Plan 2020. Additional visitor accommodation is not needed in the area
   and is likely to further erode the residential amenity for permanent residents in the area.
   Accordingly, the application is recommended for refusal.
   Departments/Sections Consulted:
         Chief Executive Officer          Community Services                      Corporate Services
         Executive Officer                Community Development                   Financial Services
         Executive Support                Community Facilities                    ICT
                                          Libraries & Galleries                   Procurement & Fleet
                                          Local Laws                              Property
                                          Waste & Environmental Health            Revenue Services

         Executive Services           x   Environment & Sustainable Development   Infrastructure Services
         Community Engagement             Building & Plumbing Services            Asset Management
         Customer Service             x   Development Assessment                  Buildings and Facilities
         Governance                       Economic Development                    Civil Operations
         People and Culture               Environmental Services                  Disaster Management
                                          Strategic Land Use Planning             Infrastructure Planning,
                                                                                  Design and Delivery



                                                                                   Page 15 of 28

Section 16

GENERAL COMMITTEE MEETING AGENDA    12 JULY 2021




                                   Page 16 of 28

GENERAL COMMITTEE MEETING AGENDA                                                                        12 JULY 2021

                                                                                                    Attachenent 1

                                                                                              S$   CoreLogic

          2 Lowry Street Peregian Beach QLD 4573

                             |
                            tee
                            |                                               =        --     =
                                S7x7m™

                             j                                                                  i
                                  rh      |   |                        woe
                         co)  Pa Po |             -                             7 Oe
                              GARAGE                    DANG                    =
                               60x69M        al    ‘    34x S4nt                     7
                           |)        ey                  =|               1             c=    |
                           ee       ‘a        4           OFFICE                        40xa9M
                           \ er      ~                    2is2™                   4
                         >                 =        ail       —           |        \e
                                          so         fa |                    ase 30M
                                                                          —=
                                         GROUND FLOOR                          FIRST FLOOR
                         SESS LIO                                                  cas A
                         2 LOWRY STREET                                         PEREGIAN BEACH

         2 Lowry Street Peregian Beach GLD 4573                                      CoreLogic Property Profile Report
         © Copyright 2090 | RP Dete Pty . tc tracts et Corel ogi: Ams Pacific (Corel ogic) arct its Bcecwort ere the apie art caches Owners of af rights, ttle anc interest (incheting mtefectual property
         pa =         nin sens pants ey cn   ea mma aa meena   atta caaalatedaanaaaaemimancaa nae tiene mael

                                                                                                      Page 16 of 28

Section 17

GENERAL COMMITTEE MEETING AGENDA                                                   12 JULY 2021


   7    T000042 – TEWANTIN BYPASS STAGE 1 – WATERMAIN RELOCATION

   Author           Designer Capital Works, Aiden Flannery
                    Infrastructure Services Department

   Index            ECM/ Project and Contract/ T000042 Tewantin Bypass Stage 1 –
                    Watermain Relocation
                    ECM/ Projects (T1) / Tewantin Bypass – Beckmans Rd – CAP.WORK –
                    100970
                    ECM/ Subject/Contract/Road Construction

   Attachments      1.    Evaluation Spreadsheet


   EXECUTIVE SUMMARY
   This report provides a tender evaluation summary and recommendation for the tender award
   in favour of the preferred contractor M&K Pipelines (QLD) Pty Ltd to carry out the Tewantin
   Bypass Stage 1 Watermain Relocation. This follows a public tender with seven respondents
   providing compliant submissions for Council to assess.
   The tender price is under budget with the cost for the watermain relocation fully funded by the
   Department of Transport and Main Roads under a Funding Agreement, with no funding
   required by Council.

   RECOMMENDATION
   That Council note the report by the Designer Capital Works to the General Committee Meeting
   dated 12 July 2021 and
   A.   Award Contract T000042 for the construction of the Tewantin Bypass Stage 1 –
        Watermain Relocation works to M&K Pipelines Pty Ltd for the lump sum price of
        $554,795 excluding GST;
   B.   Approve expenditure under this Contract up to $767,480 excluding GST, including
        contingency spend.


   REPORT
   1.   Project Background
   The delivery of the Tewantin Bypass Stage 1 – Beckmans Road and Cooroy-Noosa Road
   Intersection Upgrade (upgrade) is funded by Transport and Main Roads (TMR) under
   Funding Agreements for the design phase and for construction executed by TMR and
   Council.
   Through the Funding Agreement it was agreed for Council to undertake the delivery including
   the design development.
   In general, the scope of the upgrade includes:
       Project Management of the design, early works and construction phases.
       Design development including all necessary approvals.
       Design, coordination, liaison with relevant Authorities and the delivery of early works
        packages including the watermain relocation.
       The upgrade of the existing T-intersection to a dual-lane roundabout with the ability to
        tie-in with future staging including the proposed Beckmans Road Duplication.
       All required works including but not limited to earthworks, drainage, pavements, UP
        relocations, electrical and landscaping.

                                                                                 Page 17 of 28

Section 18

GENERAL COMMITTEE MEETING AGENDA                                                        12 JULY 2021


   Early works requirements have been introduced to the delivery methodology to compress the
   overall delivery program by enabling relocations to occur concurrently with the design
   development. Other benefits include reducing the risk of authority interfacing with the main
   contractor (such as Energex and UnityWater) and having the ability to deliver authority
   relocation using specialist contractor’s, reducing risk of program and cost.

   The project consists of the following stages with the current status noted:

                                                                                               Cost
    Stage                        Description                   Timing      Status (%)
                                                                                             to Date

                                 Planning & detailed design   Mar 2020 –
    Planning & Design                                                         90%             $410,000
                                 including approvals           Jul 2021

    Implementation               Internal costs including     Mar 2020 –
                                                                              10%              $50,000
    Costs                        consultants                   Jun 2022

                                 Clearing Works               May 2021        100%             $70,000

                                 Energex relocation           June 2021       100%            $120,000
    Early Works
                                                              Jul 2021 –      This            For
                                 Trunk Watermain
                                                              Sep 2021      contract        approval

    Construction –
                                 All remaining works to       Oct 2021 –                       To be
    Main Civil Contract                                                      Design
                                 complete the upgrade         Jun 2022                       tendered
    (Future Works)

     Total to date                                                                            $650,000

   2.       Budget
   The overall budget for this project, under TMR’s Funding Agreement, is as follows:

                                                                                        Amount (Excl.
                                  Summary Financial Details
                                                                                               GST)

    Funding Agreement – Detailed Design Stage                                                 $600,000

    Funding Agreement – Construction Stage (Council’s Implementation
                                                                                              $485,000
    Costs)

    Funding Agreement – Construction Stage
                                                                                            $6,980,000
    (see breakdown below)

           Clearing                                                                           $80,000

           Energex relocation                                                                $313,500

           Trunk Watermain (This Contract)                                                   $767,480

           Main civil works                                                                $5,334,020

    Funding Agreement – TMR Costs                                                             $100,000

    Approved Variations                                                                             $0

    Contingency                                                                             $1,645,000

    TOTAL                                                                                   $9,810,000



                                                                                     Page 18 of 28

Section 19

GENERAL COMMITTEE MEETING AGENDA                                                      12 JULY 2021


   Under the terms of the Funding Agreement, amounts exceeding the budget items requires
   TMR approval to use the contingency. Under this Contract, any amount exceeding $767,480
   requires TMR approval to access additional funds within the Contingency amount of
   $1,645,000.

   3.          Tender Process
   Due to the budget for the watermain relocation works being greater than $200,000, staff
   prepared and called for public tenders in accordance with the Local Government Act 2009.
   Tender T000042 was released via VendorPanel on 17 May 2021, and advertised in Noosa
   Today on 21 May 2021. The tender closed on 15 June 2021 with seven (7) conforming
   submissions received.

   4.          Tender Assessment
   The tender evaluation panel undertook an assessment of the following conforming tender
   submissions, listed in alphabetical order:
              Diona Pty Ltd
              Dormway Pty Ltd
              GCE Contractors Pty Ltd
              M&K Pipelines (QLD) Pty Ltd
              Offaly Civil Pty Ltd
              SGQ Pty Ltd
              Silverstrand Development Pty Ltd
   One additional submission was received and assessed as non-conforming and was not
   considered.
   The conforming tenderers were evaluated using the following evaluation criteria and
   weightings:

       Evaluation Criteria                                               Weightings
       Price                                                                30%
       Capability & Resourcing                                              15%
       Contract Experience & Capacity                                       15%
       Methodology                                                          20%
       Quality                                                              10%
       Health & Safety                                                       5%
       Contribution to Local Economy                                         5%

   Note: Attachment 1 presents the evaluation outcome of the conforming submissions against
   the above criteria.
   The tender evaluation panel completed the evaluation process and considered M&K Pipelines
   (QLD) Pty Ltd to be the most advantageous to Council, presenting the best value for money.
   M&K Pipelines (QLD) Pty Ltd tender submission is most favourable based on their tender
   demonstrating the following:
              High level of experience and capability to construct trunk watermains for water
               authorities, such as UnityWater.
              A detailed methodology demonstrating their understanding of the scope.
              Resourcing to commence as soon as awarded.
              An advantageous program to complete work in a timely manner to enable the main civil
               contract to commence as planned.
              Certified Quality System.


                                                                                   Page 19 of 28

Section 20

GENERAL COMMITTEE MEETING AGENDA                                                            12 JULY 2021


           Certified Workplace Health and Safety systems.
           Overall best value for money benefit for Council.

   5.           Program & Next Steps
   M&K Pipelines (QLD) Pty Ltd propose to commence procurement immediately in July with
   Practical Completion towards the end of September 2021 inclusive of a wet weather allowance.
   M&K Pipelines (QLD) Pty Ltd program duration is 10 weeks.

   6.       Construction Management & Inspections
   The current delivery model has Council in the project management and Superintendent roles.
   Council resourcing to support the project are in place with specialist consultants available to
   provide technical advice and inspections if necessary.

   Previous Council Consideration
   Nil.

   Finance
   The estimated construction cost is fully funded by TMR under the Funding Agreement and
   there will be no requirement to cashflow the costs.
   As per the milestone payments nominated in the Funding Agreement, the first milestone
   payment of $1.493M (ex GST) has been invoiced and will be paid to Council prior to the first
   payment claim by the proposed contractor.
   The total construction cost estimate is as follows:

                                         Item                                   Budget (Excl. GST)

       M&K Pipelines (QLD) Pty Ltd (This contract)                                         $554,795

       Engineering consultants (if required, refer below)

           Callaghan & Toth (engineering / designer)                                        $5,000

           Native Foresters (Fauna)                                                         $5,000

           Archeo (Cultural Heritage)                                                      $10,000

           Plant, equipment & labour (significant tree retention)                           $5,000

       SUB-TOTAL                                                                           $579,795

       Budget                                                                              $767,480

       REMAINING BUDGET – Contingency Against Original Estimate
                                                                                           $187,685
       under the Funding Agreement

   Risks & Opportunities
       Finance Risks                                    Mitigation
       Final contract value exceeds budget.             Risk partly mitigated by a lumpsum contract.
                                                        Contingency using the original estimate under the
                                                        Funding Agreement is at 24% or $187,685. Under
                                                        the Funding Agreement, overall project contingency
                                                        (an additional $1.65M) is available if required
                                                        subject to TMR approval.



                                                                                          Page 20 of 28

Section 21

GENERAL COMMITTEE MEETING AGENDA                                                           12 JULY 2021


    Time (program) risks                             Mitigation
    Delays due to UnityWater live connection         M&K Pipelines (QLD) Pt Ltd scope is to submit the
    works (UnityWater self-performs live             Private Works Application within 10 business days
    connections as required by their policy and      from Contract Award, which provides UnityWater as
    conditions).                                     much time as possible to plan and resource their
                                                     scope for live connections.
                                                     M&K Pipelines (QLD) Pty Ltd scope is to procure all
                                                     materials to avoid risk of material supply issues for
                                                     live connection works.
                                                     M&K Pipelines (QLD) Pty Ltd is highly skilled in
                                                     constructing watermains and have extensive
                                                     experience working for water authorities including
                                                     UnityWater and understands their requirements.
    Delays affecting the main civil contract.        M&K Pipeline (QLD) Pty Ltd) program was the
                                                     shortest duration compared with all other tenderers.
                                                     Using the tender program submitted, the current
                                                     float until the watermain contract affects the main
                                                     civil contract is in the order of 4 weeks.
                                                     M&K Pipelines (QLD) Pty Ltd can add additional
                                                     resources if required should the program require
                                                     acceleration or mitigation of delays.



    Safety Risks                                     Mitigation
    M&K Pipelines (Qld) Pty Ltd fails to ensure      M&K Pipelines (QLD) Pty Ltd will be appointed as
    the work is conducted safely and in              the Principal Contractor responsible for workplace
    accordance with minimum standards.               health & safety for the site.
                                                     Prior to commencement of construction, M&K
                                                     Pipelines (QLD) Pty Ltd management plans, Safe
                                                     Work Method Statements, Job Hazard Analysis (or
                                                     similar) and other documentation will be submitted,
                                                     reviewed, and accepted by Council.
                                                     Council will undertake surveillance, regular safety
                                                     audits and inspections throughout the construction
                                                     period.



    Scope & Quality Risk                             Mitigation
    The Contractor fails to construct the scope of   M&K Pipelines (QLD) Pty Ltd is highly skilled with
    work to the minimum standard.                    constructing watermains and have extensive
                                                     experience working for water authorities.
                                                     The quality of workmanship in the field will be
                                                     monitored with regular Council surveillance with
                                                     availability of technical support from the
                                                     engineering consultant if required.
                                                     UnityWater requires M&K Pipelines (QLD) Pty Ltd
                                                     to submit quality documentation, test reports etc
                                                     prior to undertaking live connections and all quality
                                                     documentation needs to be submitted prior to
                                                     Practical completion achieved.




                                                                                          Page 21 of 28

Section 22

GENERAL COMMITTEE MEETING AGENDA                                                          12 JULY 2021


    Resource Risk                                   Mitigation
    Scope, quality, safety, and program are         M&K Pipelines (QLD) Pty Ltd) have nominated a
    affected due to resource shortages.             highly capable team for this project and can add
                                                    additional and appropriately skilled resources as
                                                    required.
                                                    Council have added an external resource (Capital
                                                    Works Consultant) who has been procured as a
                                                    dedicated resource to provide project management,
                                                    surveillance, and contract administration support.
                                                    Council can engage the engineering consultant
                                                    responsible for the design to attend inspections if
                                                    required.
                                                    Council can utilise internal resources to attend
                                                    inspections or assist with documentation if required.

   Consultation
   External Consultation - Community & Stakeholder
   Roadpro have been engaged to provide community and stakeholder communication support.
   Early works (including the watermain relocation) have been communicated since the initial
   stages of the final design process, updating the community and stakeholders about upcoming
   activities and their impacts. Communication material includes project newsletters, Facebook
   posts and stakeholder emails.
   Further communication activities are planned in conjunction with TMR to coincide with the
   contract award to M&K Pipelines (QLD) Pty Ltd and the completion of the detailed design.
   Separate consultation has been made with TMR (party to the Funding Agreement) regarding
   this tender, program, and budget.

   Internal Consultation
   Corporate Services (Procurement)
   Infrastructure Services (Infrastructure Planning, Design and Delivery)

   Departments/Sections Consulted:

       Chief Executive Officer       Community Services                          x   Corporate Services
       Executive Support             Director                                        Director
                                     Community Development                           Financial Services
                                     Community Facilities                            Fleet
                                     Libraries & Galleries                           ICT
                                     Local Laws                                  x   Procurement
                                     Waste & Environmental Health                    Property
                                                                                     Revenue Services

       Executive Services            Environment & Sustainable Development       x   Infrastructure Services
       Director                      Director                                        Director
       Community Engagement          Building & Plumbing Services                    Asset Management
       Customer Service              Development Assessment                          Buildings and Facilities
       Governance                    Economic Development                            Civil Operations
       People and Culture            Environmental Services                          Disaster Management
                                     Strategic Land Use Planning                 x   Infrastructure Planning,
                                                                                     Design and Delivery




                                                                                        Page 22 of 28

Section 23

GENERAL COMMITTEE MEETING AGENDA    12 JULY 2021




                                   Page 23 of 28

GENERAL COMMITTEE MEETING AGENDA                                  12 JULY 2021

                   NOOSA SHIRE COUNCIL —_ Weighted Attribute Evaluation Spreadsheet - Final Evaluation ATTACHMENT 1
           Peewee                 Yemrrtipeineetiwnemanteeron |

                   (Conforming Tenders Only) {excl of GST)
                 1
                 2|scaPyleSCSC™C™~CSSSCSCCOCCC*dYC‘“‘;C‘#SS 9416
                 3
                 4 |OfayGwlPyle SCOC™C™CSOCSCOCOCSC*SYCCSC*C*~*«S OS S|
                 5
                 6
                 7
                                               1        2        3       4        5       6       7
                                                Py isd          ra   | Ofer cnteey tet | evctopmene | Dione Pryted | Dormmay Pry Ld |
                   spatisyanesorcng | tse  | | soso | wo | so | oo | om | ss | ex | wo | so | oo | uso | os | 27s |
                  fonractapevience Bcapecty | asx | wo | zo | so | 750 | so | 750 | 7m | sso | as | 67 | 10 | 500 | oo | 2350 |
                  Metrodstosy     |   me   || sso | sr | tao | strs | cas | oe | seo | a | rao | oa | rao | oe | 2720 |
                  cusey        Tm             | co | mm | rm | os | cso | co | so | o | cm | oo | soo | co | so |
                  fcsnwaseey || | tm |                 | as | ms | ame | ms | ae | os | ae | | a0 | © | 355 |
                  Contitutontotecsitconomy ||? | as | sy | ees | 2 | om | ss | 20 | 2 | tos | oe | am | ov | aes |
                   Feet Tectnicatscore | me | ots, |   ws   |e |        ease | sass | sono   | ss

                   rotal Fees (Pc)    30%             $589,466 $649,200 $709,586        $923,920 $999,453
                    erage Fees (PAV) $e $740,224
                  Price Score                            ee
                   a                          a ee

                                                                Page 23 of 28

Section 24

GENERAL COMMITTEE MEETING AGENDA                                                12 JULY 2021


   8      TOURISM FUNDING AGREEMENT REVIEW PROCESS

   Author      Chief Executive Officer, Brett de Chastel
               CEO’s Office

   Index       ECM/ Subject/ Tourism

   Attachments       Nil


   EXECUTIVE SUMMARY
   Nil.

   RECOMMENDATION
   That Council note the report by the Chief Executive Officer to the General Committee Meeting
   dated 12 July 2021 and note that the CEO will work through a review process with Tourism
   Noosa with the intent of finalising a new Funding Agreement for consideration by Council by
   the end of 2021 noting that any new agreement will not commence until 1 July 2022.


   REPORT
   The purpose of this report is to put in place a process to review and develop a new funding
   agreement between Noosa Council and Tourism Noosa. This report will set out the background
   and history of funding agreements between the two organisations and a suggested process
   and timing for the development of a new funding agreement. The current funding agreement
   expires on 30 June 2022.

   1.     Background and History of Funding Agreements between Noosa Council and
          Tourism Noosa
   Tourism Noosa and Noosa Council entered into their first funding agreement in 2000/01,
   shortly after the establishment of Tourism Noosa. That organisation was established in 2000
   jointly by the tourism sector and Council to take the lead on marketing and promotion of the
   Noosa region and ongoing development of the Noosa brand. Council assisted in the
   establishment of the Constitution for Tourism Noosa which was based on a representation
   model.
   During the 2000’s Council and Tourism Noosa had a series of funding agreements setting out
   how the funds were to be used. Tourism Noosa acted as the Local Tourism Organisation
   (LTO) and has become recognised as one of Australia’s premier LTO’s. (The Regional
   Tourism Organisation (RTO) for the broader Sunshine Coast region is Visit Sunshine Coast
   which covers the Sunshine Coast Council, Noosa Council and Gympie Council areas.)
   During the amalgamation years, Tourism Noosa continued to operate under the Sunshine
   Coast Regional Council with funding provided via a formal agreement.
   At de-amalgamation in 2014, Noosa Council inherited a number of agreements from the
   Sunshine Coast Regional Council (SCRC), namely:-
         A funding agreement between Council and Tourism Noosa for funding of $1,745,928 pa
          to undertake marketing and tourism promotion for the Noosa area;
         A funding agreement between Council and Sunshine Coast Destinations Limited (SCDL)
          (now called Visit Sunshine Coast) as the RTO for funding of $500,000 pa to support
          regional tourism marketing; and
         A funding agreement between Council and Ironman Australia for funding of $270,000 pa
          as sponsorship of the Noosa Triathlon.

                                                                               Page 24 of 28

Section 25

GENERAL COMMITTEE MEETING AGENDA                                                     12 JULY 2021


   The above agreements were entered into by SCRC prior to amalgamation and effectively
   transferred to Noosa Council on de-amalgamation on 1 January 2014.
   On 1 July 2015, Noosa Council terminated the RTO funding agreement with SCDL and at that
   time, Council and Tourism Noosa entered into a new 2 year funding agreement that added an
   extra $500,000 of funding to Tourism Noosa to their previous funding level. This agreement
   allowed Tourism Noosa to determine the extent of funding they wished to allocate to regional
   tourism opportunities and projects via the RTO.
   Also, at the end of the 2015 calendar year, the sponsorship agreement with Ironman Australia
   concluded and the $270,000 triathlon sponsorship funding was allocated to Tourism Noosa
   from 2016 for Tourism Noosa to liaise directly with Ironman Australia to determine sponsorship
   arrangements for the Noosa Triathlon.
   On 1 July 2017, Noosa Council entered into a further agreement with Tourism Noosa for
   funding. This was a 3 year agreement with a two year option (which was subsequently
   exercised) and expires on 30 June 2022. The key elements of this agreement were:-
       Total annual funding of $2.52M was provided and the term of the funding agreement was
        linked to the then Noosa Tourism Strategy 2017-22 (hence the total 5 year term).
       The funding agreement provided that the annual funding could not be reduced, thus
        providing certainty of funding for Tourism Noosa to allow for multi-year planning.
       The agreement required Tourism Noosa to maintain a marketing cash contingency of
        $350,000. Essentially, this was to ensure that Tourism Noosa maintained a cash reserve
        in its bank account that could be used in the case of an unforeseen event. Potential
        examples that were given at the time included a pilot strike, weed infestation on main
        beach, major weather events etc. As it turned out, a worldwide pandemic was the trigger
        for that contingency reserve being accessed in 2020. In hindsight, including this
        requirement in the 2017 agreement at that time was a good initiative.
       Improved reporting requirements including:
             Providing an annual report (including a copy of the audited financial statements) to
              Council by 30 November each year. These are reported to Council each year to
              ensure that these are a matter of public record.
             Providing an annual Business Plan to Council by 15 March each year. These
              Business Plans include detailed financial information including a statement of
              comprehensive income, statement of financial position and statement of cash flows
              and key performance measures that link to the Tourism Strategy Noosa 2017–
              2022.
             Twice a year (in February and August) Tourism Noosa were required to present to
              Councillors on their progress in relation to their activities, KPIs, financial progress
              and generally to keep the Councillors informed about Tourism Noosa’s activities.
              This has generally been undertaken over the life of the agreement except for some
              periods during the pandemic.
   Over the life of the 2017-2022 agreement, $12.6M of funding has been allocated to Tourism
   Noosa making this one of Council’s most significant financial agreements.

   2.   Proposed Timing and Process for finalising a new Funding Agreement
   The current funding agreement expires on 30 June 2022. Tourism Noosa have expressed a
   desire to finalise a new agreement as soon as practical. This certainly makes sense as it
   provides funding certainty for forward planning in future years for both Council and Tourism
   Noosa.
   The proposed process to negotiate a new agreement is as follows:
       Timing – it is anticipated that a new funding agreement could be agreed to between

                                                                                   Page 25 of 28

Section 26

GENERAL COMMITTEE MEETING AGENDA                                                  12 JULY 2021


        Council and Tourism Noosa by December 2021. This would provide a 6 month lead time
        before the agreement commenced which would assist both Council and Tourism Noosa
        in planning for future budgets. The new agreement needs to be adopted by both Council
        and the Tourism Noosa board.
       Key Funding agreement issues - there are a range of issues to be negotiated in the
        funding agreement but like any funding agreement, the two key issues are (i) amount of
        the proposed funding and (ii) term of the agreement. There will also be other terms and
        conditions but these are, inevitably, some of the key matters to be determined.
       Opportunities – there is opportunity to improve some of the performance measures and
        reporting compared to the current agreement. This would represent an ongoing maturing
        of the relationship between Tourism Noosa and Council and support enhancement of
        transparency for the funding agreement.
       Transparency – both Tourism Noosa and Council have expressed a desire to make this
        process and funding as transparent as possible. Opportunities to enhance this
        transparency will be explored as part of this process.
       Legal review - there will need to be time for both Tourism Noosa and Council to have the
        draft funding deed reviewed by their respective lawyers before the document is
        presented for consideration by both the Tourism Noosa Board and Council.
       Good Governance and financial management - this funding agreement represents one
        of the most significant financial commitments that the Council makes given the total value
        over the life of the funding agreement. The current agreement involved a total payment
        of $12.6M from Council to Tourism Noosa over the life of that agreement. Both Tourism
        Noosa and Council share a desire for good governance and strong financial
        management associated with the expenditure of these funds. To support this, it is
        proposed that:
             Council, in conjunction with Tourism Noosa re-look at the current governance
              model that has been in place for 20 years to see whether it needs to be updated.
              Previous discussions with the chair of Tourism Noosa indicates that Tourism
              Noosa is looking at this issue already. The governance arrangement are based
              on the Constitution which is largely unchanged from 2000. A review should be
              undertaken to look at the governance arrangements to make sure that they are
              “future fit”.
             Council, in conjunction with Tourism Noosa undertake a review the internal
              financial management processes to ensure that appropriate controls are in place.
              As indicated above, this agreement involves considerable funding and Council
              (and Tourism Noosa) need to be certain that good internal controls are in place to
              manage this.
             In short, these reviews are designed to ensure that Council and Tourism Noosa
              have comfort that the right governance and financial controls are in place so that
              public funds are well managed.

   Previous Council Consideration
   Ordinary Meeting, 7 May 2015, Item 8, Page 10
   That Council note the report by the Chief Executive Officer to the General Committee Meeting
   dated 4 May 2015 and authorise the Chief Executive Officer to enter into a 2 year funding
   agreement with Tourism Noosa in accordance with the proposed terms and conditions outlined
   in the report.
   Ordinary Meeting, 7 August 2017, Item 3 Page 7
   That Council note the report by the Chief Executive Officer to the Services and Organisation
   Committee Meeting dated 8 August 2017 and authorise the Chief Executive Officer to enter

                                                                                 Page 26 of 28

Section 27

GENERAL COMMITTEE MEETING AGENDA                                                   12 JULY 2021


   into a Funding Agreement with Tourism Noosa generally in accordance with the terms and
   conditions set out in the draft Funding Agreement provided at Attachment 1 to the report.
   Ordinary Meeting 19 March 2020 (Mayoral Minute), Item 1 Page 3
   That in relation to the Coronavirus (COVID-19) Pandemic, Council:
   A.    ….
   B.    Approve the request by Tourism Noosa for it to access the Marketing Contingency
         Reserve in accordance with section 7 of the Funding Agreement between Noosa Council
         and Tourism Noosa, noting that Tourism Noosa will determine the timing and approach
         of future marketing in consultation with the tourism sector and Council.

   Finance
   There is no cost in the development of this new agreement. However, as noted in the report,
   there is considerable annual funding provided to Tourism Noosa for promotional activities. That
   funding is currently set at $2.52M pa which is included in the 2021/22 Council budget.

   Risks & Opportunities
   Council has recently been through a process to develop a new agreement with the Noosa
   Biosphere Reserve Foundation (NBRF) that addresses funding, KPIs, ongoing working
   relationships etc. There is an opportunity that such an agreement may provide a good basis
   for the types of issues that need to be addressed in the new agreement with Tourism Noosa.
   Council and Tourism Noosa have always had a strong working relationship. This new funding
   agreement is an opportunity to work closely together to maintain Noosa’s position as a leading
   tourism destination.
   The expenditure of significant public funds on an activity obviously requires good governance
   and financial management practices in place. The renewal of this agreement is an opportunity
   to re-look at the governance and financial controls to ensure that public funds are well
   managed. This can be done in conjunction with Tourism Noosa.

   Consultation
   External Consultation - Community & Stakeholder
   Chairperson of Tourism Noosa
   CEO of Tourism Noosa
   Internal Consultation
   Departments/Sections Consulted:

    x   Chief Executive Officer      Community Services                       Corporate Services
        Executive Support            Director                                 Director
                                     Community Development                    Financial Services
                                     Community Facilities                     Fleet
                                     Libraries & Galleries                    ICT
                                     Local Laws                               Procurement
                                     Waste & Environmental Health             Property
                                                                              Revenue Services

        Executive Services           Environment & Sustainable Development    Infrastructure Services
        Director                     Director                                 Director
        Community Engagement         Building & Plumbing Services             Asset Management
        Customer Service             Development Assessment                   Buildings and Facilities
        Governance                   Economic Development                     Civil Operations
        People and Culture           Environmental Services                   Disaster Management
                                     Strategic Land Use Planning              Infrastructure        Planning,
                                                                              Design and Delivery



                                                                                 Page 27 of 28

Section 28

GENERAL COMMITTEE MEETING AGENDA    12 JULY 2021


7   CLOSED SESSION

    Nil.




                                   Page 28 of 28

GENERAL COMMITTEE MEETING AGENDA                                 12 JULY 2021

7    CLOSED SESSION

     Nil.

                                                                Page 28 of 28

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.