Decision Notice - Approved by Delegation of Authority - DBW26 0027 (As Published)
Land rehabilitation
7. Rehabilitation of the development site must be undertaken post construction to ensure the
site is stabilised, including the following:
a. Be undertaken immediately following completion of the building works.
b. Result in the area being stable, landscaped and revegetated.
c. Be revegetated with a species mix reflective of the local variant of the Regional
Ecosystem, site specific conditions and in accordance with Noosa Landscaping
Planning Scheme Policy (PSP2).
d. Any turfed areas must be free of pest, diseases and weeds.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
- - Concise ecological Assessment Report prepared Received 16
by Equilibrium Ecology March 2026
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. Council has undertaken an audit check of the drawings in relations to the proposed works. A
detailed check of the calculations and drawings has not been undertaken. The RPEQ bears
full responsibility for all aspects of the engineering design. Council reserves the right to
require further amendments and/or additions at a later date should design errors become
apparent.
2. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Erosion and Sediment Control
3. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
4. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
Retention of existing trees and vegetation
5. This development approval does not authorise the removal/clearing of vegetation from the
site.
Page 3 of 6
Document Set ID: 24810169
Version: 5, Version Date: 22/05/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original