Council archive · source document
SUPERSEDED - Change to an Existing Approval 51994.1263.01
Officer: Wilhelm Koschade Direct Telephone: 07 53296215 Our Reference: 51994.1263.01 Your Reference: N/A 7 December 2016 Pacific BCQ PO Box 1901 NOOSAVILLE BC QLD 4566 [email protected] Dear Sir/Madam Change to an Existing Approval Sustainable Planning Act 2009 I refer to your request to make a permissible change to an existing approval. On 5 December 2016, Council decided your requested changes. Details of the decision are as follows: application details Application No: 51994.1263.01 Street Address: 11 Sunseeker Cl NOOSAVILLE QLD 4566 Real Property Description: Lot 167 P 845980 Decision details Council on 21 September 1994 decided to issue the following type of approval: Town Planning Consent for Duplex dwelling. (TPC 2730) In relation to the request to make a change to the existing approval, Council on 5 December 2016 decided to: Agree to amend the list of approved plans to include: Plan No. Rev. Plan/Document Name Date Sheet 1 0f 3 D Site Plan, drawn by Mandy’s Design & Drafting December, 2016 Sheet 2 0f 3 D Floor Plan, drawn by Mandy’s Design & Drafting December, 2016 Sheet 3 0f 3 D Elevations, drawn by Mandy’s Design & Drafting December, 2016 B. Include additional conditions 21 relevant period of approval The relevant period for this development approval is in accordance with that stated in the Decision Notice dated 21 September 1994, unless an application to extend the period is approved by Council under s 383 of the Sustainable Planning Act 2009. CONSOLIDATED ASSESSMENT MANAGER CONDITIONS Submission to and approval by Council of building plans in accordance with the Building Act, Council's By-laws and Policies, the conditions of this approval and substantially in accordance with plans submitted by the applicant on the 24th June 1994, and the Shire of Noosa Planning Scheme apart from where amendments are required or dispensations have been granted in conjunction with this approval. The plans submitted for building approval are to increase the clear width of the garages to 6.0 metres to be consistent with Council's provisions. Provision of at least 4 covered off-street car parking spaces, and access thereto which are to be provided with a sealed pavement and designed, drained, constructed and maintained in accordance with the Planning Scheme, Council's Policies and to the reasonable satisfaction of the Shire Engineer. Plans and specifications for these works are to be submitted to the Shire Engineer for approval in conjunction with the Building Application. A Building Approval shall not be granted until the Shire Engineer has approved of the carparking and access scheme. There is to be no detrimental effect upon the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions. The open space and setback areas are to be landscaped in accordance with Council's Policy on Landscaping Guidelines and a properly prepared landscape plan to be submitted to and approved by the Shire Planner, prior to the issue of a Building Approval. Such landscaping is to be completed in accordance with the approved landscape plan, prior to the premises being occupied and maintained at all times thereafter to the reasonable satisfaction of the Shire Planner. Any fencing provided in conjunction with the development is to be setback an average of two (2) metres to any road frontage pursuant to clause 36 (6) (c) of the Schedule to the Planning Scheme. Construction work and other associated activities are permitted only during the hours of 7.00 a.m. to 6.00 p.m. Monday to Saturday. No work is permitted on public holidays, except where extended hours are approved by the Building Surveyor. Payment of contributions in accordance with Council's Policy on Water Supply and Sewerage Headworks. An estimate only of the charges as at May 1994 under the current policy is as follows:- Water Supply $3,203 Sewerage $2,931 ______________________ TOTAL: $6,134 Please note that the headworks charges will alter in accordance with Price Index variations of if any amendment is made to Council's policy. Headworks contributions shall be calculated and paid in accordance with one of the following alternatives:- Prior to the issue of a Building Approval, in the amount calculated under the Policy at that date: or Deferred to the soonest of the following dates:- (i) prior to Council sealing plans of the development for titling purposes; (ii) prior to the issue of a Certificate of Classification for any building approved under this application; or (iii) prior to commencement of the approved use at the relevant premises. Where the option of a deferred payment is used in accordance with b. above, the following conditions shall also apply:- Prior to the issue of a Building Approval, a trading bank guarantee is to be submitted to the value of the headworks which are due, plus 20%. The subsequent payment of headworks shall include interest charged at the rate set by the Queensland Treasury Corporation for Local Government borrowings as they apply to Noosa Shire and current at the time the trading bank guarantee is submitted. Should the contributions not be paid at the due time, Council shall call upon the sum secured by the trading bank guarantee. The trading bank guarantee will be returned on payment of the required contributions plus interest or on expiry of the relevant Building Approval, whichever is the sooner. The footpath across the frontage of the site is to be upgraded by the provision of a 1.2 metres wide concrete footpath and the forming, grassing and topsoiling of the remaining area to the standards and requirements of the Shire Engineer. The applicant is to contact Council's Engineering Department to determine the footpath alignment prior to the commencement of any works. The developer shall bear the cost of alteration of any public utility or other facilities necessitated by the development of the land or associated construction works external to the site. Connection to Council's existing water supply and sewerage reticulation systems at the developer's expense to the standards and requirements of the Shire Engineer. The developer shall provide metered water connections from the water supply system to the proposed development, in accordance with Council's standards and to the satisfaction of the Shire Engineer. Roof and surface water is to be collected on site and is to be discharged through a single underground drain line into existing drainage in Sunseeker Close to the satisfaction of the Shire Engineer. A Building Approval shall not be granted until the Shire Engineer has approved of the drainage scheme. Provision of approved refuse containers in accordance with the requirements of the Refuse Management Regulations of 1983 for the storage and collection of refuse to the satisfaction of Council's Environmental Health Officer. Provision of an imperviously paved area upon which to stand all refuse containers together with a suitable enclosure, if required, to enclose the refuse container area to the satisfaction of the Environmental Health Officer. Any flat or unit intended to be let out for fee or reward is to be licensed annually with Council's Health Department in accordance with the provisions of Chapter 43 of Council's By-Laws prior to such letting. Submission of a cash bond or trading bank guarantee to the sum of $3,000 to secure performance of conditions, prior to the issue of Building Approval. The cash bond or trading bank guarantee will be returned upon performance of the conditions of approval. The provisions of this approval are to be effected, prior to the commencement of the approved use. Council reserves the right to call upon the bond or guaranteed sum referred to in this approval to effect compliance with conditions. The Town Planning Consent Permit may be revoked pursuant to Section 4.14 of the Local Government (Planning and Environment) Act if commencement of erection or works have not been made in accordance with that Permit or the rights conferred by that Permit are not exercised within two (2) years of the date of issue of the Permit. The Town Planning Consent Permit lapses where:- the use or erection of a building or other structure associated with the use, has not been commenced within four (4) years of the date of issue of the Town Planning Consent Permit, unless application is made and approved by Council for an extension; or the use of any premises pursuant to the Town Planning Consent Permit ceases for a period of twelve (12) months Additional Condition – 5 December 2016 The approved roofed deck extension must remain of open construction and is not permitted to be enclosed. further development permits required Development Permit for Building Works (All Building Works) rights of appeal You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached. other details If you wish to obtain more information about Council’s decision, electronic copies of which are available on line at www.noosa.qld.gov.au, or at Council offices. DECISION NOTICE HISTORY Original Decision Notice 24 June 1994 Changes to an Existing Approval 5 December 2016, with an amendment to list of approved plans and additional condition 21. Yours faithfully, Wilhelm Koschade Development Planner Encl. Approved Plans/Documents Appeal Rights Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009 The following is an extract from the Sustainable Planning Act 2009 (Chapter 7) 466 Appeals about decisions relating to permissible changes (1) For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval— (a) if the responsible entity for making the change is the assessment manager for the application— (i) the person who made the request; or (ii) an entity that gave a notice under section 373 or a pre-request response notice about the request; (b) if the responsible entity for making the change is a concurrence agency for the application—the person who made the request. (2) The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376. (3) Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request. (4) An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made. [word/footer1.xml] Page 6 of 6 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 6 [word/header3.xml] .51994.1263.01 [Attachment: image4.png (image text)] a mm NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Change to an Existing Approval 51994.1263.01Related documentApplication case desk ↗
About this file
- File size
- 94 KB (small file)
- File type
- DOCX
No other editions are linked here.