Original source · versioned page text
Approved Decision Notice - OPW25/0190 [As Published]
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
25-0316-EGX-01 A S1302554 Sheet 1 of 4 Prepared by PE 12/11/2025
Consulting Engineers
25-0316-EGX-02 A S1302554 Sheet 2 of 4 Prepared by PE 12/11/2025
Consulting Engineers
25-0316-EGX-03 A S1302554 Sheet 3 of 4 Prepared by PE 12/11/2025
Consulting Engineers
25-0316-EGX-04 A S1302554 Sheet 4 of 4 Prepared by PE 12/11/2025
Consulting Engineers
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 9 December 2027 unless an application to extend the currency
period is approved by Council.
Site Specific Conditions
3. Electrical conduits proposed to be installed within existing and proposed road reserves under
existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant
vegetation must be installed by boring. Trenching is not permitted, unless specifically
approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
4. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
5. Copies of the approved plans, duly signed by the consultant Registered Professional
Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
Construction at the “pre start” meeting.
6. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
7. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
8. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Electrical reticulation works;
9. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
Page 2 of 7
Document Set ID: 24373199
Version: 2, Version Date: 11/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original