Council archive · source document
Delegated Report MCU26 0034 & OPW26 0056 (As Published) · OPW26/0056
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for a Material Change of Use - Landing – Residential
• Operational Works – Jetty & Boatlifting Device
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
Sheet 1 of 2 A Site Plan 02/04/2026
Prepared by Kunkel Building Design
Sheet 2 of 2 A Floor Plan, Floor Framing Plan & Typical Section 02/04/2026
Prepared by Kunkel Building Design
Currency Period
2. The Currency Period for this development approval lapses if all conditions have not been
complied with, and the plan of survey lodged with Council for endorsement by 25 June 2028,
unless an application to extend the currency period is approved by Council.
Site Specific Conditions
3. All elements of the existing jetty, both above and below water level, must be wholly removed
as part of these works.
Performance Bond
4. Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
submitted to Council, to secure performance of all conditions of this approval, prior to the
commencement of the works. The cash bond or trading bank guarantee will be returned on
performance of the conditions of this approval less any costs incurred by Council in respect
of enforcing performance of this permit. Council reserves the right to call upon the bond or
guaranteed sum to effect compliance with conditions.
Bonds
5. Bonds must:
a. meet the requirements of Council’s relevant Planning Scheme Policy for performance
and uncompleted works.
b. be lodged with Council and accompanied by the Bond Administration Fee/s.
c. be requested for release by writing to Council, when relevant approval requirements
have been met.
General Conditions
6. The maximum number of vessels that may be berthed, moored, attached or stored on the
structure must not exceed 2 vessels.
Page 5 of 8
Document Set ID: 24812865
Version: 6, Version Date: 25/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report MCU26 0034 & OPW26 0056 (As Published).pdfRelated documentApplication case desk ↗
Delegated Report MCU26 0034 & OPW26 0056 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.8 MB (small file)
- File type
No other editions are linked here.