RAL210017
Officer: Patrick Murphy
Direct Telephone: 61753296436
Our Reference: RAL21/0017
Your Reference: 0305
4 February 2022
JNE Developments
C/- Pivotal Perspective Pty Ltd
4/59 Mary St
NOOSAVILLE QLD 4566
[email protected]
Dear Sir/Madam,
Decision Notice
Planning Act 2016
I refer to your application and advise that on 3 February 2022, Council decided to approve the
application, subject to conditions.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: RAL21/0017
Street address: 25 Pavilion Street Pomona Qld 4568
Real property description: Lot 21 SP 316902
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
Council decided to issue the following type of approval:
Development Permit for Reconfiguring a Lot – 1 Lot in to 10 lots
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
submission of plans for plan sealing, and then compliance maintained at all times while the
use continues.
PO Box 141 P. (07) 5329 6500 [email protected]
TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au
Page 1 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 12 pages
Page 2
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
13010-PRO-10 H Proposed Subdivision of 25 Pavilion Street 17.12.2021
Pomona RPD: Lot 21 on SP316902,
prepared by LSD
N/A V2 Ecological Assessment Report prepared by 09/08/2021
North Coast Environmental Services
N/A V2 Bushfire Hazard Assessment prepared by 09/08/2021
North Coast Environmental Services
3. All lot numbering on the subdivision plan to be submitted to Council for the plan sealing
application must remain as shown on the Approved Plans.
Currency Period
4. This development approval lapses if the requirements of the conditions have not been
completed and an application for plan seal is not lodged with Council by 3 February 2026,
unless an application to extend the currency period is approved by Council.
Performance Bond
5. Prior to arranging a Prestart meeting for the operational works, a security bond in the form
of a cash bond or trading bank guarantee to the sum of $30,000 must be submitted to
Council, to secure the performance of all conditions of this approval. The cash bond or trading
bank guarantee will be returned on performance of the conditions of approval less any costs
incurred by Council in respect of enforcing performance of this permit. Council reserves the
right to call upon the bond or guaranteed sum to effect compliance with conditions.
Covenant
6. A vegetation protection covenant must be registered against the title of the property over the
land area defined as the Riparian Buffer Overlay (Riparian Buffer Area and Waterways)
(Noosa Plan 2020) on the subject site identified for rehabilitation on the Approved Plans and
Ecological Assessment Report v2 and must be rehabilitated* pursuant to Section 97A of the
Land Title Act 1994. The covenant document and a survey plan must be submitted to Council
for endorsement prior to lodgement with the relevant titles authority for registration of title.
The covenant document must:
a. incorporate the requirements of this Decision Notice;
b. include Noosa Council as Covenantee;
c. reference Queensland Land Title Registry Standard Terms Document No. 715597513;
d. reference the Ecological Assessment Report (9 August 2021 v2 North Coast
Environmental Services);
e. reference the Covenant Area Management Plan (or similar); and
f. reference the Bushland Rehabilitation Program (or similar).
7. If a provision included in the covenant document is requisitioned or refused registration by
the relevant titles authority, a substitute provision must be included in the document which
as nearly as practicable addresses the objective sought by the requisitioned or refused
provision. The wording of the substitute provision must be agreed by Council.
Page 2 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 3
8. The Vegetation Protection Covenant must result in an area of not less than 0.40ha within Lot
10 over the mapped riparian buffer area as detailed within the Ecological Assessment Report
v2 and an area of not less than 912m2 within Lot 10 over the mapped waterway area as
detailed within approved Plan 13010-PRO-10 (Proposed Subdivision of 25 Pavilion Street
Pomona RPD: Lot 21 on SP316902, prepared by LSD) Rev H dated 17.12.2021.
Land Rehabilitation
9. Rehabilitation works must be undertaken in accordance with an Operational Works approval
and Planning Scheme Policy - PSP 2 Landscaping. An ecological rehabilitation plan must be
submitted, prepared by a suitably qualified person* (* refer Advisory Notes) for the waterway
and park area and must include in particular:
a. Rehabilitation of the Waterway – the area to be rehabilitated must be:
i. 5m from the centreline of the waterway; from the proposed new driveway of Lot
10 to the southern extent of the covenant area as shown on drawing number
13010-PRO-10 (Proposed Subdivision of 25 Pavilion Street Pomona RPD: Lot
21 on SP316902, prepared by LSD) Rev H dated 17.12.2021.
ii. 10 metres wide north of the proposed new driveway for Lot 10 to the northern
boundary of the subject site as shown on drawing number 13010-PRO-10
(Proposed Subdivision of 25 Pavilion Street Pomona RPD: Lot 21 on SP316902,
prepared by LSD) Rev H dated 17.12.2021.
b. Rehabilitation to the full extent of the Riparian Buffer Area adjacent to the western
boundary of the subject site as identified on map OM-BWW-(ii)-9 – Pomona Village –
Riparian Buffer (Noosa Plan 2020)
c. Retention of existing bed and banks of the waterway unless required to be modified to
ensure function of the approved stormwater system, which may include reshaping into
a vegetated swale with stone low flow base and vegetated banks with coir mesh.
d. The waterway must be rehabilitated to reflect natural function and form, and include
riffles and ponds to provide variability in flow depth and refugia for fauna to live in during
dry periods.
e. Details of the treatment to all batters, armoury, plantings, weed treatment, location of
services/utilities and rehabilitation.
10. A Covenant Area Management Plan (or similar) and a Bushland Rehabilitation Program (or
similar) must be prepared by a qualified person* and endorsed through an Operational Works
approval.
11. The land area defined as the Vegetation Protection Covenant within the Riparian Buffer
Overlay and adjacent to the waterway (Noosa Plan 2020) on the subject site identified for
rehabilitation on the Approved Plans must be rehabilitated* and removed of all weeds species
listed in the following standards and legislation:
a. Declared plants under the Land Protection (Biodiversity Act 2014 and sub-ordinate
Regulation 2016).
b. Noosa Local Government Area Pest Management Plan 2015-2019.
c. Undesirable Species as listed in Planning Scheme Policy 3 Landscaping Plants and
Guidelines.
The works must be undertaken in accordance with an Operational Works approval.
*(Refer to Advisory Note)
12. A “no clearing zone” must be established and maintained over the land area defined as being
excluded from access and building envelopes on the subject site. The following activities
must not be carried out within the no clearing zone:
a. clearing, cutting down, poisoning, lopping or pruning of native vegetation which is
indigenous to, or planted within, the zone
Page 3 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 4
b. soil/spoil dumping and/or compacting
c. soil excavation, other than for planting indigenous native plants or for works which are
a natural consequence of this approval.
The following exceptions apply:
a. declared plants under the Biosecurity Act 2014, and any Council Listed Environmental
Weeds, Undesirable species, Exotic Grasses and other plants identified in writing by
Council
b. indigenous native trees which pose a well-founded threat to persons or property as
approved in writing by Council
c. controlled bushfire burns to maintain ecological processes subject to submission of a
Bushfire Management Plan and agreed in writing by Council.
13. All rehabilitation and re-vegetation of the waterway and Riparian Buffer area must be
completed prior to Council endorsement of the Plan of Survey.
Works within Protected Land
14. The following works must be undertaken within the land to be covered by a vegetation
protection covenant prior to the submission of the sealing of the survey plan:
a. Treatment and control of declared plants under the Biosecurity Act 2014 and all
undesirable species as listed in Planning Scheme Policy 3 Landscaping Plants and
Guidelines to prevent regrowth.
b. Plantings in accordance with a Covenant Area Management Plan (or similar) and a
Bushland Rehabilitation Program (or similar) prepared by a qualified person* and
endorsed through an Operational Works approval.
c. Removal of any structures, debris or materials foreign to a natural environment
The works must be undertaken in accordance with an Operational Works approval.
*(Refer to Advisory Note)
Fencing to Protected Land
15. A permanent fence must be constructed around the entire perimeter of a vegetation
protection covenant area. The fence must be constructed in accordance with an Operational
Works approval and must be to the following specification:
a. 1.2 metres high;
b. 3 strand plain wire (no barb);
c. Bottom strand no less than 300mm off the ground;
d. Include a pedestrian access gate; and
e. Include A5 sized signage with the wording “Vegetation Protection Covenant Area – No
domestic animals” every 15m, durable, weather resistant and visually complementary
to the natural environment.
Fauna Management
16. Vegetation must only be removed or disturbed in accordance with a Fauna Management
Plan (or part thereof) prepared by a qualified person* and endorsed through an Operational
Works approval.
*(Refer to Advisory Note)
17. Any domestic cats kept at all Lots must be permanently confined within buildings and/or cat
enclosures for the purpose of protecting proximate wildlife. A clause must be included in the
contract of sale which alerts purchasers to the requirement of this condition.
Page 4 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 5
Landscaping Works
18. The development site must be landscaped. The works must be undertaken in accordance
with an Operational Works approval and the Noosa Plan for that specific area and must
include in particular:
a. Provision of 32 street trees along the frontage of Lots, planted within the road reserve
and suitably located for sight lines, specifically:
i. 5 street trees on the southern boundary of Lot 1 RP189023,
ii. 7 street trees on the northern boundary of Lot 20 SP316902,
iii. 2 street trees for each of the following Lots: 1, 2, 3, 4, 5, 8 and 9,
iv. 2 street trees on the eastern boundary of Lot 6 only,
v. 4 street trees, 2 on each road reserve of Lot 7,
vi. No street trees required for Lot 10,
b. Provision of turfed area to road frontages;
c. Street trees must be local native species suitable for the locality and established in
accordance with Noosa Plan Planning Scheme Policy 3 Landscaping Plants and
Guidelines;
d. Street trees must be a minimum 45 litre pot size; and
e. Control of all weeds species listed in the following standards and legislation:
i. Declared plants under the Land Protection (Biodiversity Act 2014 and sub-
ordinate Regulation 2016).
ii. Noosa Local Government Area Pest Management Plan 2015-2019.
iii. Undesirable Species as listed in Planning Scheme Policy 3 Landscaping Plants
and Guidelines.
19. All landscape works must be established and maintained over the one-year maintenance
period and in a manner that ensures healthy, sustained and vigorous plant growth. All plant
material must be allowed to grow to full form and be refurbished when its life expectancy is
reached.
20. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
21. All entry statements, fences, retaining walls and buffer/screen plantings must be located
entirely within private land and not within the public road reserve.
Vegetation Management
22. An arborist’s report is to be submitted for approval as part of the operational works
application. The purpose of the arborist’s report is to identify the native vegetation to be
retained on site, whilst recognising the need for vegetation clearing to occur in order to carry
out the development. The vegetation to be retained must be clear of proposed services, not
present a nuisance to neighbouring properties and be generally suitable for the proposed
location. The report is to be prepared by a suitably qualified person*.
(*Refer Advisory Note)
Bushfire Management
23. All reconfiguration works must be carried out in accordance with the Bushfire Hazard
Assessment v2 report listed within this Decision Notice.
24. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the bushfire management conditions
of this Decision Notice.
Page 5 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 6
*(Refer Advisory Note)
25. A clause must be included in the contract of sale for lot 10 which requires any future dwelling
to be constructed within the building envelope shown on the Approved Plans and in
accordance with Bushfire Hazard Assessment v2 report listed within this Decision Notice.
Flooding
26. The surface levels of all lots (excluding drainage reserves) must be constructed to provide
flood immunity. The works must be undertaken in accordance with an Operational Works
approval and must include in particular surface levels that are higher than each of the
following:
a. the local 1%AEP flood level at year 2100 (plus freeboard)
b. the regional 1%AEP flood level at year 2100 (plus freeboard)
27. An easement for drainage purposes must be registered against the title of proposed Lot 10
in favour of Council over the land area identified for easement South of the building envelope
on proposed Lot 10 on Plan 13010-PRO-10G, prepared by LSD, dated 17th December 2021
28. All works, including filling and compensatory excavation for floodplain storage, are to be
carried out generally in accordance with Section 2.2 of the Stormwater Management Report
prepared by Peak Urban dated 28 October 2021
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works approval
and the Queensland Urban Drainage Manual, and must include in particular:
a. extension of the site stormwater system to accommodate stormwater from Pavilion
Street;
b. cut off drains at the eastern interface of Lots 1 and 9 to intercept runoff from external
properties, including registration of drainage easements over these drains in favour
of the upslope properties;
c. collection and discharge of stormwater to the proposed detention basin, including
the provision of Level II inter-allotment drainage for lots which do not fall to the street
and provision of kerb adapters for all new lots which do fall to the street
d. the use of gravity stormwater drainage and not surcharge pits.
e. Stormwater runoff from the development must be disposed of on-site without
causing scour or damage to the subject site or any adjoining property.
Stormwater Quality
30. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and the latest version
of the Water Sensitive Urban Design Technical Design Guidelines for South East
Queensland, and must include in particular:
a. stormwater quality treatment devices of a size and location generally in accordance
with those shown in Stormwater Management Report prepared by Peak Urban
dated 28 October 2021
b. bioretention devices which:
i. are designed generally in accordance with the Bioretention Technical Design
Guidelines (Water by Design, 2012)
ii. are designed generally in accordance with IPWEQA Standard Drawing No. DS-
073, DS-075, DS-076, and DS-078
iii. are provided with a free-draining outlet from the sub-soil drainage system
Page 6 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 7
iv. incorporate a coarse sediment forebay designed generally in accordance with
IPWEQA Standard Drawing No. DS-075
31. Permanent educational signage must be erected to educate the residents of the development
about the function of the bioretention device(s). The dimensions, standard, presentation and
location of the educational signage must be in accordance with an Operational Works
approval.
Stormwater easement
32. Stormwater entering the 3-metre-wide easement adjacent to the southern boundary must be
directed to the waterway, the works must be undertaken in accordance with an Operational
Works approval
ENGINEERING
External Works
33. Pavilion Street must be upgraded for the length of its frontage to the subject site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
a. construction of kerb and channelling for the full frontage of the development site.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
New Roads
34. The new road shown on the Approved Plans must be constructed in accordance with the
conditions of this Decision Notice and dedicated as road reserve at no cost to Council.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
35. The new road must join smoothly with the existing formation of Pavilion Street. The works
must be undertaken in accordance with an Operational Works approval, generally in
accordance with TOD Consulting’s plan 21556-SK101: “Preliminary Design – General
Arrangement”, Rev C, dated 11/11/2021 and be designed and constructed in accordance
with Council’s Planning Scheme Policy 6 – Engineering Design Standards. The works must
include in particular:
a. reserve and formation widths to a “Local Road” standard;
b. sealing, drainage, kerbing and channelling;
c. construction of pedestrian footpaths in accordance with the conditions of this Decision
Notice;
d. installation of street and pathway lighting;
e. provision of sight distances adequate for the design speed of the road; and
f. signage and linemarking.
Property Access and Driveways
36. A residential driveway must be constructed to proposed Lots 4, 5, 6 and 10. The works must
be undertaken in accordance with an Operational Works approval.
37. Maintenance vehicle access to the proposed bio-basin must be constructed. The works must
be undertaken in accordance with an Operational Works approval.
Pedestrian and Bicycle Facilities
38. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. a 2 metre wide footpath within one side of the new road’s verge for the entire length of
the new road, connecting to the existing footpath on Pavilion Street;
Page 7 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 8
b. 2 pram ramps in accordance with Council’s standard drawing SD:9006-Rev E, or the
revision applicable at the time of construction, allowing for safe pedestrian crossing of
the new road along Pavilion Street.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Services
39. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with an approval for Operational Works and the standards and requirements of
the relevant service provider.
40. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
41. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Easements
42. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
43. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
44. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Geotechnical Stability
45. All subdivisional works must be carried out in accordance with a Geotechnical Report (or part
thereof) prepared by a qualified person* and endorsed through an Operational Works
approval.
*(Refer to advisory Note)
Earthworks
46. All fill and associated batters must be undertaken in accordance with an Operational Works
approval and contained entirely within the subject site unless written permission from the
respective landowner(s) is provided to Council.
47. No retaining walls/earthworks are to be undertaken and/or constructed or occur, with only
minor works permitted that are necessary to facilitate the roadworks, stormwater
management, flood immunity for lot 10 and connection to services. The development must
be undertaken in a manner which responds to the site’s constraints such that the natural
landform is generally maintained. Any earthworks proposed must be detailed clearly in the
application for Operational Works and be limited in extent to the reasonable satisfaction of
Council.
Damage to Services and Assets
48. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Page 8 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 9
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Water & Sewer Connections
49. An underground connection to reticulated water and sewerage must be provided to each lot
in accordance with the standards and requirements of Northern SEQ Distributor–Retailer
Authority (Unitywater). No lower-pressure sewer system (private pump systems) are
permitted in order to provide sewer connection to the lots.
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to each lot.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Building and Construction Industry (Portable Long Service Leave) Levy
1. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Co-ordination of Operational Works Assessment
2. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Qualified Person
3. For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
for the development, a qualified person is considered to be a person who:
a. is a Registered Professional Engineer of Queensland (RPEQ); and
b. has a degree in civil engineering or engineering geology; and
c. has a minimum of 5 years’ experience in the field of geotechnical engineering or
engineering geology.
Preparation of a Preliminary Construction Management Plan
4. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. maintenance of safe pedestrian access for the areas affected by the works during
and after daily construction has ceased;;
iii. proposed fencing to the site during the construction phase of the development;
iv. approval of the Traffic Management Control Plan by the Department of Transport
and Main Roads (DTMR) for any works on State controlled roads;
v. provision for worker car parking.
Page 9 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 10
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures;
c. works programme identifying key components of the works and their respective
durations;
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic, services and other relevant issues;
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details;
g. identification of complaint management procedures including:
i. contact details for the on-site manager;
ii. dispute resolution procedures.
h. details on the location of external fill sites/sources, the haulage route, type of vehicle
to be utilised during filling operations and frequency of usage. NB any damage to the
existing road system as a result of haulage operations shall be fully repaired at the
applicant’s expense
i. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Community Title Scheme - Private Infrastructure
5. All private infrastructure for the development must be designed to meet the planning scheme
requirements unless otherwise agreed by the relevant authority.
6. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
7. For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
current experience in the field of landscape design.
8. For the purpose of preparing a Rehabilitation Plan and/or Covenant Area Management Plan,
a qualified person is considered to be a landscape architect or ecologist with a minimum of
3 years current experience in the field of landscape design.
9. For the purpose of preparing an Arborist Report, a qualified person is considered to be a
person with either:
a. ISA certification; or
b. a Diploma of Arboriculture in addition to a minimum of 3 years current experience in
the field of arboriculture.
10. For the purpose of preparing a Fauna Management Plan, a qualified person is considered to
be an ecologist with a minimum of 3 years current experience in the field of fauna assessment
and management.
Page 10 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 11
7. PROPERTY NOTES
RAL21/0017 – Vegetation Protection Covenant
1. The following notation applies to approved Lot 10:
A Vegetation Protection Covenant applies to this lot. No clearing of vegetation is to occur
within the covenanted area, except where in accordance with the terms of the covenant.
RAL21/0017 – Ecological Preservation
2. The following notation applies to approved Lot 10:
To ensure the protection of vegetation on this lot, any dwelling on this lot is required by
Council Approval RAL21/0017 to be constructed within the building envelope nominated on
the approved Lot Reconfiguration proposal plan (see Council file reference RAL21/0017).
3. A “no clearing zone” applies to this property for the purpose of vegetation protection. The
landowner must maintain the property in accordance with the ecological preservation
conditions of Council Approval RAL21/0017.
RAL21/0017 – Control of Domestic Cats
4. The following notation applies to all approved lots:
Domestic cats are permitted on this lot provided that they are permanently confined within
buildings and/or cat enclosures. This requirement is designed to protect lower canopy and
ground nesting and feeding birds which occur proximate to the lot.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Operational Works Drainage work, Landscaping, Stormwater,
Earthworks, Civil works, Access, Frontage
works, Roadworks
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
Page 11 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 12
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Patrick Murphy
Coordinator Planning
Enc: Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents
Page 12 of 13
Document Set ID: 21808186
Version: 3, Version Date: 04/02/2022
Page 13
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 13 of 13
Document Set ID: 21808186