Original source · versioned page text
Decision Notice - Approved by Delegation of Authority OPW21 0187
Officer: Laurie Schreck Direct Telephone: 07 53296223 Our Reference: OPW21/0187 Your Reference: 2103 23 July 2021 Callaghan & Toth Consulting Engineers PO Box 2305 NOOSA HEADS QLD 4567 [email protected] Dear Applicant Decision Notice Planning Act 2016 I refer to your application and advise that on 20 July 2021, Council decided to approve the application subject to conditions. Details of the decision are as follows: Development Permit for approval for Operational Works - Drainage Works, Stormwater and Vehicle Crossover CURRENCY PERIOD of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date 2103-01 C Proposed Lot Configuration Key Court, Noosa Heads – Site Plan & Drawing Index as prepared by Callaghan and Toth June 2021 2103-03 C Proposed Lot Configuration Key Court, Noosa Heads – Easement Overland Flow Path Detail as prepared by Callaghan and Toth June 2021 2103-04 C Proposed Lot Configuration Key Court, Noosa Heads – Swale Longitudinal Section as prepared by Callaghan and Toth June 2021 2103-05 C Proposed Lot Configuration Key Court, Noosa Heads – Easement Cross Sections as prepared by Callaghan and Toth June 2021 N/A N/A Arboricultural Report and Tree Protection Methodology/Plan as prepared by Australian Tree Contractors & Arboricultural Consultants Pty Ltd 22 June 2021 CURRENCY PERIOD The Currency Period for this development approval lapses if the development has not substantially started by 27 July 2023, unless an application to extend the currency period is approved by Council. SITE SPECIFIC CONDITIONS Any disturbance to the verge area during the works must be reinstated to match the existing verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. PRIOR TO COMMENCEMENT OF WORKS Engineering Tree protection fencing must be installed under the supervision of the Project Arborist in accordance with the approved Arboricultural Report. Copies of the approved plans, duly signed by the consultant Registered Professional Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer at the “pre start” meeting. A condition report of the drainage system must be completed for agreement at the prestart meeting. The condition report is to include a CCTV inspection of the existing pipe and must include at least the section of RCBC between the pit on Key Court and the outlet. A condition report consisting of photographs of the frontage of the site and the property boundary adjacent the proposed drainage swale must be completed and submitted to Council at the prestart meeting / prior to any works commencing. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties or their proxy for the following aspects of the works: Civil engineering works; Erosion and sediment control works; Other relevant parties A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: Traffic Management during all aspects of the construct phase including: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction; Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased; Proposed fencing to the works during the construction phase of the development; No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off. Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures; and Include a post out to the local residents and businesses advising of the proposed works, the expected time frames and the site contact details. Bonds A site control and/or compliance bond of $5000 is to be submitted to Council prior to the pre-start meeting. The pre-start meeting will only be held once Council's Construction Engineering Officer has confirmation that the bond monies have been received by Council. The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit. Bonds must: Meet the requirements of Council’s relevant Planning Scheme Policy for performance and uncompleted works; Be calculated using a schedule of works and relevant bond equation; Include GST; Have approval of the bond calculations and amount from Council prior to lodgement; Be lodged with Council and accompanied by the Bond Administration Fee/s; and Be requested for release by writing to Council, when relevant approval requirements have been met. Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to Council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. The works associated with the overland flow path must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice; The relevant conditions of the higher order Reconfiguration of Lot approval RAL20/0025 to which this approval relates; All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines; and The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site. Works within Road Reserve/Reinstatement Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Site Access and Driveways Driveway crossovers must be constructed in accordance with Council’s Standard Drawings RS-049 and RS-050. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete; The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties; Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway; and The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Earthworks Slope and batters are a maximum grade of: 1 in 6 where in proximity to waterbodies; 1 in 4 for grassed areas; 1 in 3 for planted areas; and 1 in 2 for combined structural engineering and planting solutions. With the exception of the swale batters which must be constructed generally in accordance with the approved plans. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g. by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Prior to the completion of the development, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes). For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Erosion and Sediment Control Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have: Been duly designed and revised by a suitably qualified person and constructed in accordance with "best practise" methods; Been revised to address predicted rainfall events, and Achieve the desired environmental outcomes. Council may request further controls to be installed should the implemented measures be found inefficient. The erosion and sediment control measures must be designed, installed and maintained in accordance with the Supervising Engineers instructions and the current best practice standards * (Refer to Advisory Note). The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring. The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system or natural waterways due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways. Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. Upon completion of the works and prior to the sealing of survey, a final condition report of the underground drainage system must be provided to Council. The report must include CCTV footage of at least the section of RCBC between the pit on Key Court and the outlet. As Constructed Plans and ADAC XML Files (Council) Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory “As-Constructed” records must be submitted to Council. The bundle of “As Constructed” information shall include: As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and; ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed) prepared in accordance with industry standards and recorded in “MGA - UTM56 / GDA94” projection. Please Note: Further information and advice relating to the as-constructed drawing presentation, as-constructed survey capture and associated guidelines for preparation of a compliant ADAC XML digital file are available on the webpage titled “As-Constructed Guidelines” and accessible at the Noosa Council Website: Planning & Development / Development Tools & Guidelines / As-Constructed Guidelines. The “As-Constructed” drawings will require certification by a: Qualified experienced Civil Engineer (RPEQ) confirming design intent and conformance with applicable standards and specifications, along with the relevant descriptions of assets, services and structures and; Licensed Surveyor in regard to the cadastral and locational information, levels and applicable survey datum. The data must be in accordance with Council’s “Planning Scheme Policy 6 – Engineering Design Standards”, and fully detail the levels for all engineering works including but not limited to the drainage network and structures, finished ground and pavement surface levels. A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection. referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: General Advisory Notes As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-050 and RS-056 (a copy is attached). Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart, On and Off Maintenance Inspections Request Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ). As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection: Methods of stabilisation are: Appropriate for slopes and slope lengths; and Are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination. If at the time of request for plan sealing, the method of short-term stabilisation has not achieved a level of stability that Council's Officers believe will have a high probability of achieving long term stability (i.e. until house construction has occurred on all lots), Council Officers may take the following matters into consideration in determining whether the site is capable of achieving medium to long-term stability: Evidence that the site has been effectively stabilised in the short term; Evidence that soil has been adequately ameliorated; Evidence that seed of annual and perennial grass species has been applied at an adequate rate; and That grass seed has germinated at a density that is likely to achieve an effective grass cover. For example, while hydromulch can provide an immediate and effective stabilising cover to soils, the protective cover can be relatively short-lived if vegetation fails to establish before the thin layer of mulch decomposes. So if hydromulch is selected as the method of temporary short term stabilisation, Council Officers will seek to confirm that perennial as well as annual grasses are well established at the time of plan sealing to reduce the risk of instability of the site in the medium to long term. As a general rule, hydromulch will only be accepted as a “patch” fix and should comprise no more than 20% of the exposed site area due to the high risk of failure. Due to the requirement to progressively stabilise exposed areas, it is not envisioned that this will present any difficulties for an appropriately managed and compliant site property notes Not applicable. VARIATION approval details Not applicable. further development permits required Not applicable. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au Yours faithfully, Laurie Schreck Development Engineer Enc: Appeal Rights Approved Plans/Documents cc. Unity Water Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017 Chapter 6 Dispute resolution Part 1 Appeal rights 229 Appeals to tribunal or P&E Court (1) Schedule 1 of the Planning Act 2016 states – (a) Matters that may be appealed to – (i) either a tribunal or the P&E Court; or (ii) only a tribunal; or (iii) only the P&E Court; and (b) The person- (i) who may appeal a matter (the appellant); and (ii) who is a respondent in an appeal of the matter; and (iii) who is a co-respondent in an appeal of the matter; and (iv) who may elect to be a co-respondent in an appeal of the matter. (2) An appellant may start an appeal within the appeal period. (3) The appeal period is – (a) for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or (b) for an appeal against a deemed refusal – at any time after the deemed refusal happens; or (c) for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or (d) for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or (e) for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or (f) for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person. Note – See the P&E Court Act for the court’s power to extend the appeal period. (4) Each respondent and co-respondent for an appeal may be heard in the appeal. (5) If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal. (6) To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about- (a) the adopted charge itself; or (b) for a decision about an offset or refund- (i) the establishment cost of trunk infrastructure identified in a LGIP; or (ii) the cost of infrastructure decided using the method included in the local government’s charges resolution. 230 Notice of appeal (1) An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that- (a) is in the approved form; and (b) succinctly states the grounds of the appeal. (2) The notice of appeal must be accompanied by the required fee. (3) The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to – (a) the respondent for the appeal; and (b) each co-respondent for the appeal; and (c) for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and (d) for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and (e) each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and (f) for an appeal to the P&E Court – the chief executive; and (g) for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate. (4) The service period is – (a) if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or (b) otherwise – 10 business days after the appeal is started. (5) A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6). (6) A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person. 231 Other appeals (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable. (2) The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error. (3) A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter. (4) In this section – decision includes- (a) conduct engaged in for the purpose of making a decision; and (b) other conduct that relates to the making of a decision; and (c) the making of a decision or failure to make a decision; and (d) a purported decision; and (e) a deemed refusal. non-appealable, for a decision or matter, means the decision or matter- (a) is final and conclusive; and (b) may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and (c) is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground. 232 Rules of the P&E Court (1) A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal. (2) However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court [word/footer1.xml] Page 2 of 9 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 9 [Attachment: image3.png (image text)] ee) NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.