ORDINARY MEETING MINUTES 19 MAY 2016
5 CONSIDERATION OF COMMITTEE RECOMMENDATIONS
PLANNING & ENVIRONMENT COMMITTEE RECOMMENDATIONS
10 MAY 2016 – Crs Joe Jurisevic (Chair), Ingrid Jackson, Brian Stockwell, Tony Wellington
Other Councillors in Attendance: Cr Frank Wilkie, Cr Jess Glasgow
The following Recommendations from the Planning & Environment Committee
were adopted without discussion or further amendment.
Council Resolution
Moved: Cr Jurisevic
Seconded: Cr Glasgow
The Planning & Environment Committee recommendations dated 10 May 2016 be adopted.
Carried.
1 APPLICATION TO CHANGE DEVELOPMENT APPROVAL FOR OPERATIONAL WORK
ENGINEERING WORK VEHICLE CROSSOVER AT 6 HABITAT PLACE NOOSA HEADS
(OPW15/0197.01)
Item not dealt with by Planning & Environment Committee. Referred to General
Committee for consideration.
Reason for Referral: Cr Wellington disagrees with the recommendation.
2 REQUEST TO CHANGE EXISTING DEVELOPMENT APPROVAL FOR A DETACHED
HOUSE AT 38 PARK CRESCENT, SUNSHINE BEACH - MCU15/0070.01
That Council note the report by the Development Planner to the Planning & Environment
Committee Meeting dated 10 May 2016 regarding Application No. MCU15/0070.01 for a
Change to an Existing Development Permit for Material Change of Use of Premises -
Detached House situated at 38 Park Crescent, Sunshine Beach and approve the request in
accordance with the following:
A. Agree to amend Condition 3 to read:
3. Development undertaken in accordance with this approval must generally
comply with the approved plans of development. The approved plans listed in
the following table and may be further amended by the conditions herein.
Plan No. Rev. Plan/Document Name Date
TP01 B Cover Sheet and Site Plan, prepared by NOF 27/04/16
Architects
TP02 B Ground Floor Level, prepared by NOF Architects 27/04/16
TP03 B Lower Floor Level, prepared by NOF Architects 27/04/16
TP04 B Rumpus Level, prepared by NOF Architects 27/04/16
TP05 B Roof Level, prepared by NOF Architects 27/04/16
TP06 B North East Elevation, prepared by NOF Architects 27/04/16
TP07 B North West Elevation, prepared by NOF Architects 27/04/16
TP08 B South East Elevation, prepared by NOF Architects 27/04/16
TP09 B South West Elevation, prepared by NOF Architects 27/04/16
TP10 B Section A, prepared by NOF Architects 27/04/16
TP12 B 3D View, prepared by NOF Architects 27/04/16
Page 3 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.