provision for on-site vehicular manoeuvring space to safely enter and exit the site
regardless of any vehicles queuing at the petrol bowsers.
2. The applicant is to demonstrate that visibility at the proposed/existing access point
achieves the Safe Intersection Sight Distance in the Department of Transport and
Main Roads’ Road Planning and Design Manual (RPDM) and relevant sections of the
AUSTROADS Guide to Road Design, Part 4A – Unsignalised and Signalised Intersection
for a 70km/h design speed (to suit the posted speed of 60km/h).
This must be demonstrated based on the physical survey and detailed on the plans
certified by an appropriate Registered Professional Engineer Queensland (RPEQ) or
Registered Surveyor.
In response to Item 2 of DSDIPs Information Request, DSDIP are advised that due to the
location and formation of the existing on-site service station, the current access
arrangement available to the site will not be altered to facilitate the proposed
development. Keith and Christina Rolton have owned the site for 13 years, and confirm a
zero accident history with regard to vehicles entering and exiting the site.
Due to the nature of the proposed use, resulting from the amendment to the application
from a Shop (Type 2 Retail Business) to Light Industry (Type 2 Industrial Business),
limited customer access will be generated by the proposed development, with
employee/staff traffic being the primary users accessing the site. Accordingly, the existing
access configuration available to the site provides optimal access opportunity to and from
the site when considering the site’s corner lot configuration, existing and proposed on-site
uses and road order hierarchy.
3. The applicant is requested to provide a Stormwater Management and Design (water
quantity and quality) report that demonstrates that the proposed development
addresses potential stormwater impacts on the state-controlled road network. In
particular, the applicant is to demonstrate that the proposed installation of water
tanks will mitigate any increase to drainage on Kin Kin Road and will mitigate any
increase in the width of flow in the kerb or encroach onto the road.
The Stormwater Management Design must:
(a) Be certified by a Registered Professional Engineer Queensland (RPEQ)
(b) Be prepared in accordance with the department’s Road Drainage Manual and the
Environmental Protection Act 1994 and Environmental Protection (Water) Policy
2009.
(c) Demonstrate that the management of stormwater (quantity and quality) post
development can achieve a no worsening impact (on the pre-development
condition) in accordance with the design criteria in the department’s Road
Drainage Manual. Stormwater management for the proposed development must
ensure no worsening or actionable nuisance to the state-controlled road network
caused by peak discharges, flood levels, frequency/duration of flooding, flow
velocity, water quality, sedimentation and scour effects.
(d) Ensure the following are addressed, where applicable:
# All relevant legal points of discharge for the development site are identified. No
new discharge points for stormwater will be permitted on state controlled roads;
# Overland flow paths are identified and hydraulic conveyance is maintained on
the site as part of the proposed development;
# Flood storage capacity is maintained on the site as part of the proposed
development;
# The adverse impacts from sheet flow on the state-controlled road network are
prevented;
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Request to Amend Application and Response to DSDIP's Information Request.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.