               35.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               36.    The following must be complied with during the construction of the required
                      crossovers/driveways:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete;
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties;
                      c.      The properties’ accesses must be located a minimum of 1m clear of existing power
                              poles, streetlights or other signage. The developer is responsible for any necessary
                              relocation of existing services to provide this clearance and must contact the relevant
                              service authorities and comply with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               37.    All earthworks must be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 2’ as
                      defined in Appendix B.
                      Stormwater Drainage
               38.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               39.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g. by blocking or interfering with natural overland flows).
               40.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Erosion and Sediment Control
               41.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               42.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.



                                                                                                        Page 9 of 13

Document Set ID: 21928199
Version: 7, Version Date: 26/05/2022
Log in to download the original file

Delegated Report - Code - Planning RAL21 0026.pdf · 1.5 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.