Town Planning Report - Other Change Composting Facility · 132005.638.06
“Specialist services and practical solutions”
The applicant has provided an Interim Stormwater Management Plan (ISWMP) prepared by
TOPO for the site as a whole (refer Attachment 8). At this stage, the ISWMP needs to be
considered in context with the currently approved SWMP prepared by Covey (M25-004Rpt,
dated February 2025 (refer condition 15 – Attachment 1A). Further, the completed SWMP will
be provided by TOPO as soon as possible. It is expected that the finalised TOPO SWMP will
replace the current Covey SWMP under the approval.
It is stated by TOPO the objective is to provide an ISWMP for the site, taking into consideration
the current conditions and future works, and identify how runoff will be managed to comply
with the relevant guidelines and licence conditions. The consultant advises that once the layout
for the future works, particularly the development of the northern portion of the site, is
confirmed, hydrologic and hydraulic modelling will be undertaken to size all required drainage
features. The SWMP addresses surface water only and does not include the management of
groundwater or leachate 8.
The stormwater management consultant has made a number of recommendations for the
existing operation across the site and the design of the northern precinct redevelopment:
• assess the catchments within the active filling zones and ensure all disturbed areas are
being directed to an appropriately sized sediment control
• inspect the eastern boundary on the edges of Catchments 12 and 22 and ensure all
runoff has been managed in accordance with the site permit and discharged at an
appropriate location
• implement the recommendations of the TOPO concept design and Covey stormwater
management plan for the upgraded HES basin at SW2
• investigate options for the treatment of runoff from low erosion risk areas in the
northern portion of the NRRC, which is likely to be bioretention systems.
• Ensure all drainage for the NRRC is designed to convey peak flows associated with the
1 in 10 year (10% AEP) event per DETSI 2025, or as required to ensure the necessary
flow rates are conveyed to the HES basin to achieve the annual runoff treatment
percentage necessary.
7 Consultation
While not a requirement under the planning scheme or the Planning Act 2016, the applicant
has previously undertaken consultation with Kabi Kabi Peoples Aboriginal Corporation about
proposed improvements at the NRRC. The proposed use of the site as a utility installation is
consistent with the intended use community infrastructure and is not required to be publicly
notified. Importantly, the proposed development does not extend beyond the existing
operational footprint and does not raise any native title issues.
The proposed composting facility is centrally located within the land and will improve and
complement the existing organic waste management and processing on the site, without
causing significant offsite impacts. In the circumstances, there is no need for additional
community consultation to be undertaken.
8 Stormwater Management Plan, Part 1.1, page 1
23026 – Noosa Resource Recovery Centre (NRRC) – Composting Facility Page 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Town Planning Report - Other Change Composting Facility .pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.