Decision Notice - DBW23 0106 [As Published] · DBW23/0106
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
- - Site Plan prepared by Jo Case Architect 11 August 2023
- - Lower Floor Plan – Proposed New Work prepared 11 August 2023
by Jo Case Architect
- - Upper Floor Plan – Proposed New Work prepared 11 August 2023
by Jo Case Architect
- - Proposed New Roof prepared by Jo Case Architect 11 August 2023
- - Sections prepared by Jo Case Architect 11 August 2023
- - Elevations 1 prepared by Jo Case Architect 11 August 2023
- - Elevations 2 prepared by Jo Case Architect 11 August 2023
Currency Period
3. This development approval lapses if the works have not substantially started by 15
November 2025, unless an application to extend the currency period is approved by Council.
Landscaping
4. Existing native trees on the site must be retained.
5. Prior to the commencement of the use, a mix of native landscaping, such as ground covers,
shrubs and trees, is provided for a width of 5 metres from the rear boundary, to provide
adequate buffering to protect the coastal dune system. Landscaping species to are to be in
accordance with Table 3.1 & 3.2 of Planning Scheme Policy PSP2 of the Noosa Plan 2020.
6. Rear fences adjacent to the beachfront within the Coastal Protection Area are no greater
than a height of 1.2 metres; built of open construction (i.e., at least 50% transparent), light
weight material and dark colours to blend with the natural landscape.
Car Parking
7. A minimum of 2 car parking spaces must be provided on site and made available and
accessible at all times for residents.
Coastal Protection
8. Gates must not be installed along the rear property boundary to gain direct access to the
beachfront.
9. External colours and finishes must be of muted/environmental tones that blend with the
natural environment and low-reflective roofing and cladding materials.
Stormwater Drainage
10. Stormwater runoff from the development must be discharged to the street without causing
scour or damage to the subject site or any adjoining property.
Damage to Services and Assets
11. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
Page 2 of 4
Document Set ID: 22671741
Version: 4, Version Date: 22/11/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - DBW23 0106 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 142 KB (small file)
- File type
No other editions are linked here.