1856-Construction Management Plan (Prelim V2) Oct 2020 - Barlow Shelley · OPW20/0145

of 27

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
4.9    Existing Services

It is the Contractor’s responsibility to locate all existing services (including electrical &
communications) prior to commencement of works and project and maintain these
services for the duration of the works.


Should any services require relocation as part of the works, this shall be carried out by an
approved contractor for each relevant asset owner.


4.10 Protection of Adjacent Properties

All adjacent properties are to be protected for the duration of the works. No works are to
encroach on adjacent properties unless the necessary approvals and the land owners’
consent have been obtained. All existing boundary fencing must be maintained. Any
damage caused by the Contractor is to be rectified at the Contractor’s expense. It is
recommended that photographic evidence of the site and surrounds be collected prior to
the commencement of works.



4.11 Workplace Health and Safety

It is the contractors’ responsibility to ensure that the site is maintained to a suitable standard
to ensure the safety of all workers and site visitors. Adequate safety signage is to be
installed in accordance with the relevant legislation. All site visitors are to hold a minimum
General Safety Induction White Card or equivalent.

4.12 Public Relations & Complaint Management

Signage shall be erected at the site with contact details of the Principal Contractor and Site
Foreman. The site supervisor shall make a record of all complaints. Any disputes are firstly
to be resolved where possible by the Principal Contractor, else, report them to the Project
Manager for clarification of course of action. The Principal Contractor shall also notify Local
Authorities and emergency services of the commencement of works, if required.




Preliminary Construction Management Plan                                                        12
October 2020

Used in these records

About this file

File size
3.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

1856-Construction Management Plan (Prelim V2) Oct 2020 - Barlow Shelley.pdf · 3.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.