Council archive · source document
Table 1 - Part 6 Cooroy Specific Outcomes [As Published] · 132007.2398
Column 1 Column 2 Column 3
Specific Outcomes Probable solutions (if code assessable) Design Response/Comments
Flooding and drainage65 S14.1 Floor levels for habitable rooms are— The site is not subject to external flood impacts.
O14 Buildings and other works are designed and
sited to— a) for areas where minimum floor levels Floor levels within the site have been
are available—not less than the established to take into account overland flows
a) provide flood free access to premises and specified level; and possible internal impacts from roof water
flood free habitable areas; b) for areas where flood modelling is and roadways etc. The site is not affected by
b) allow only minor, short term and infrequent available—a minimum of 500mm external catchments that would contribute to
flooding of non-habitable areas; above the modelled flood level; and adverse site impacts.
c) ensure drainage does not adversely c) for areas where flood modelling is not
impact upon other premises; and available, a minimum of 500mm above Stormwater management on the site provides for
d) ensure filling or excavation does not the highest known flood level; the use of the existing farm dams which will be
adversely impact upon other premises redesigned to assist in the detention and reuse
by— AND of stormwater runoff.
i. causing ponding of water on the site or
nearby land;
S14.2 Where Council infrastructure is Stormwater discharge will be designed to ensure
ii. increasing flooding, which adversely
available— that there is a no-worsening effect downstream
affects the safety or use of any land
of the site.
upstream and downstream; and
iii. adversely affecting the flow of water in a) any drainage (including buildings and
any overland flow path. yards) flows to that infrastructure; and Full details are included in the engineering report
b) b) the infrastructure has the capacity to prepared by Brown Consulting.
accept any additional loading.
Sloping sites S15.1 Buildings are of split level design that Split level housing is not conducive to seniors
O15 On sloping sites, buildings and structures are step down the slope or have suspended floor living.
designed to maximise the use of natural slope and construction; (See Figure 6.1below)
minimise the need for cut and fill. Building designs have been prepared to take
AND account of the slope of the site with earthworks
Figure 6.1—Design for sloping site (suspended being generally limited to a cut/fill depth of 1.5
floor) S15.2 Cut or fill is less than 1.5m in depth; metres.
The site sections included on Drawing
AND 0588_TP_09 provides an indication of the typical
earthworks proposed on the site.
S15.3 The distance between the ground and It is noted that the cut to fill depths across the
the lowest part of the floor of the building does residential care facility may exceed 1.5 metres in
not exceed 3m. some areas due to the size of the building foot
print required for the facility and the need to
provide equitable access to the building from
public access areas.
Table 1 – Code Compliance Checklist – Part 6 - Cooroy Locality Specific Outcomes 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Table 1 - Part 6 Cooroy Specific Outcomes [As Published]Related documentApplication case desk ↗
About this file
- File size
- 143 KB (small file)
- File type
No other editions are linked here.