      In addition, the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
      undertaking in writing that the Title Deed and the easement documents will be lodged at
      the Land Titles Office and any additional Titles Office forms or requisitions requiring the
      consent of Council will be attended to promptly.
      A duly executed copy of the easement shall be submitted to Council for perusal prior to
      the use commencing.
      Any changes required by Council’s Solicitor must be corrected immediately.
      Should the subject site (Lot 8 on SP195871) be amalgamated with the adjoining site (Lot
      7 on SP195871) the requirement for the access and services easement shall not apply.

Additional Condition (21/12/2011) (71-79)
71.   Construction activities must not impede the access of Unitywater or Fire Brigade
      personnel to vital infrastructure (eg. valves, fire hydrants and sewer access chambers).
72.   The fire-fighting demand on Unitywaters water supply system from the development
      must not exceed 15 litres per second.
73.   A single Unitywater installed primary water meter must be provided immediately inside
      the property boundary. Additional water meters must be installed for each title of a
      community title or sub-lease scheme. Meters must be approved by Unitywater, installed
      in accordance with Unitywater requirements and remain accessible at all times for
      reading and maintenance purposes.
74.   The existing Unitywater sewerage infrastructure within Lot 8 must be removed and a
      manhole and new sewer connection constructed inside the southern boundary of Lot 8.
75.   A 3.0 metre wide easement must be provided over Unitywater sewerage infrastructure
      located within private property. Easements must be located centrally over the main.
76.   Buildings and other structures must maintain a minimum clearance of 1.0 metre from
      sewer manhole chambers and the sewerage inspection opening.
77.   Storm water retention systems and gross pollutant traps must maintain a minimum
      clearance of 1.5 metres from Unitywater water supply and sewerage infrastructure.
78.   Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
      Unitywater water mains and 1.5 metres from Unitywater sewerage mains. Landscaping
      plants within these clearances must be low growing when mature and be suitable
      Unitywater approved varieties.
79.   Construction works undertaken in the vicinity of Unitywater water supply or sewerage
      infrastructure must not adversely affect the integrity of the infrastructure. All costs
      associated with repair, replacement or alteration of infrastructure must be met by the
      applicant.

5     REFERRAL AGENCY CONDITIONS
Not Applicable
6     APPROVED PLANS
Refer to table listed in Condition 1 above
7     PLANS/DOCUMENTS REQUIRING AMENDMENT
Not Applicable




                                                                                 Page 12 of 16

Used in these records

About this file

File size
70 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Compiled Decision Notice 132002.220611.4 14 Serenity Cl Noosa Heads.pdf · 70 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.