SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 SEPTEMBER 2019
REPORTS FOR NOTING BY THE COMMITTEE
3 NOOSA SPIT SHORELINE EROSION UPDATE - SEPTEMBER 2019
DOCUMENT INFORM AT ION
Author Project Coordinator – Flooding, Coastal and Foreshore, Daniel Wishaw
Infrastructure Services Department
Index ECM/ Project / Noosa Dog Beach SEMP Coastal Monitoring – CAP. 100723
ECM / Subject / Erosion
Attachments Nil
EXECUTIVE SUMMARY
Not applicable
RECOMMENDATION
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 10 September 2019 providing an update on
the development of a Shoreline Erosion Management Plan (SEMP) for Noosa Spit.
REPORT
1. Background
Council, at its Ordinary Meeting dated 15 November 2018, supported the development of a
Shoreline Erosion Management Plan (SEMP) for Noosa Spit and the provision of a quarterly
update.
2. Project Update
The Noosa Spit SEMP project is currently on track, with the first four of eight phases of the
project now complete (see Table 1 for all phases). Since the June 2019 quarterly update, our
consultants, BMT, have completed the model set-up, conceptual river mouth modelling and have
initiated the coastal strategy development.
As part of the Noosa Spit SEMP project, BMT were tasked with comparing the existing river
mouth configuration with other historically relevant river mouth configurations, as well as,
investigating the impacts of a ‘breakthrough’ event of the Noosa Spit. These were completed
using a process called ‘conceptual modelling’ where the actual configuration of the river mouth is
replicated, within a computer simulated model, to simulate alternative configurations. The
impacts, measured as water levels and water velocities over a typical tidal cycle, were recorded
at 115 points along the Noosa River, for five separate river mouth configurations.
Page 19 of 39
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.