CASCADING CLIMATE RISKS FROM CRITICAL INFRASTRUCTURE FAILURE PROJECT REPORT · Report
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
8.1 CASCADING CLIMATE RISKS FROM CRITICAL INFRASTRUCTURE
FAILURE PROJECT REPORT
Author Program Lead - Climate Change Adaptation, Joanna Pardoe
Strategy & Sustainability | Strategy and Environment
Index
Attachments None
EXECUTIVE SUMMARY
The Cascading Climate Risks from Critical Infrastructure Failure (CIF) Project has been completed
through a partnership with Sunshine Coast Council under the Regional Climate Action Roadmap.
This project systematically examined the compounding and cascading risks of climate hazards and
critical infrastructure failure on key Council services.
The two-year project was enabled through a $1.1m grant from Queensland Reconstruction Authority
as part of the Queensland Resilience and Risk Reduction Fund 2022-2023. An Executive Steering
Group (ESG) which included CEOs and Executive Directors from both Councils, a Stakeholder
Reference Group (SRG) with regional critical infrastructure providers, and a Project Steering Group
(PSG) of key internal staff from both Councils were established as part of the governance framework
for the project. The SRG comprised representatives from critical infrastructure and critical service
providers across the region (see Stakeholder Engagement section for full list).
The findings of this project have highlighted risks to the delivery of Council services due to disruptions
of electricity, water, wastewater, telecommunications and transport networks that arise from
compound climate hazard events, such as bushfires occurring following a heatwave and a prolonged
drought.
The interdependencies between critical infrastructure services, combined with the increasing
frequency and severity of extreme events, make it more likely Council services will be disrupted by
prolonged critical infrastructure outages in the future. The impacts of these outages cascade across
and through Council service areas, which leads to knock on effects to the community that relies on
these services.
The project found prolonged simultaneous outages across critical infrastructure types will impact
staff productivity, health, safety and wellbeing, ability to process payments and collect revenue, and
ability to adhere to governance processes and sound decision-making protocols. These impacts
undermine Council’s service provision to communities across the Shire, regardless of where the
initial outage occurs. Outages could extend for weeks at a time, particularly in hinterland areas, yet
Council’s current business continuity plans anticipate outages of considerably shorter durations and
complexities.
Actions to prepare and enhance the resilience of Council’s service delivery include both
technological (e.g. batteries, generators, radios and mobile filtration units) and non-technological
options (e.g. strategic workforce planning, alternative working hubs, governance procedures). It is
recommended these actions be implemented strategically and holistically to improve delivery
efficiency, avoid duplication, minimise costs, avoid maladaptation and ensure appropriate due
diligence. Addressing risks to staff safety and productivity are priorities.
The priority actions recommended for implementation are:
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 15 pages
Page 2
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
• Implement adaptation and resilience measures at the Local Disaster Coordination Centre/
Noosaville Depot;
• Improve policies, systems and procedures that account for critical infrastructure failure;
• Establish internal data collection systems to inform resilience options and improve future risk
and opportunity assessments;
• Continue to engage with critical infrastructure providers through the Stakeholder Reference
Group.
Amongst other things, the benefits of the project have included:
• Increased awareness for staff and regional Critical Infrastructure (CI) providers on the
implications of compounding critical infrastructure failure for Councils.
• Improved understanding of existing critical infrastructure failure planning by Councils and CI
providers, for current and future planning horizons.
• Improved understanding of local historic CI failure patterns, the role of climate hazards and
impacts on Council services and community.
• Identified key risk drivers for CI providers (climate and non-climate) and potential implications for
Councils.
• Developed future compounding climate hazard scenarios and CI failure scenarios to be used to
inform risk assessments and resilience planning.
• Identified adaptation options (both technical and non-technical) that have the potential to reduce
the risks from CI failure to Council services.
• An economic and financial business case, and rationale for adaptation measures at select
Council-operated case study sites.
• Strengthened relationships between CI providers and Councils to partner and develop
collaborative projects that improve our region’s resilience to climate hazards moving forward.
• Strengthened relationships and improved in-house capabilities through continued partnership
with Sunshine Coast Council on strategic risk reduction.
• Progressed best-practice climate risk management through use of the Intergovernmental Panel
on Climate Change (IPCC)’s climate risk framework.
This project highlights the need to strengthen strategic and operational risk reduction to build
resilience to future impacts of cascading and compounding hazards, which are occurring more often
due to climate change and the increasing interconnections of systems in society. The increasing
complexity of risks poses a significant challenge for local government with new risk management
approaches needed to understand system interdependencies and resilience measures to reduce
risks.
The project’s findings and recommendations will require additional funding and resourcing to
coordinate and implement priority actions, to be considered through future budget processes.
RECOMMENDATION
That Council
A. Note the report by the Program Lead - Climate Adaptation to the Planning & Environment
Committee Meeting dated 10 February 2026; and
B. Note the priority actions to implement the key findings from the project, as listed below:
i. Implementation of adaptation and resilience measures for the Local Disaster
Coordination Centre (LDCC) and Noosaville Depot.
Page 3
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
ii. Establishment of management solutions that improve corporate policies, systems and
procedures to build resilience to critical infrastructure failure and cascading climate risks.
iii. Establishment of required organisational governance to drive a holistic climate
adaptation response to compounding critical infrastructure failure.
iv. Establishment of internal data collection to inform future investigations and improve
Council’s ability to address the consequences of critical infrastructure failure.
v. Continued engagement with critical infrastructure and critical service providers through
the continuation of the Stakeholder Reference Group.
vi. Continued partnership with the Sunshine Coast Council to build on findings and identify
joint solutions to manage the cascading impacts of critical infrastructure failure.
C. Note the recommendations of the study will be used to inform budget submission for Council
consideration for the 26/27 FY.
REPORT
Background
The IPCC’s Sixth Assessment Report on Impacts, Adaptation and Vulnerability (IPCC AR6 WGII),
released in 2022, emphasises how critical infrastructure that comprise electricity, food, water,
wastewater, health, transport and communication systems provide much of the material basis for
society – enabling the flows of people, goods, data, waste, energy and capital.
The failure of these systems during extreme events – which are occurring more frequently, more
intensely, and for longer due to climate change – causes enormous disruption to the function of
society. The Australian Institute for Disaster Resilience (2020) finds that “in many scenarios, a
prolonged infrastructure disruption may be the cause of the most significant consequence.” However,
as the IPCC AR6 report makes clear, properly understanding how these systems will be disrupted
is challenging due to the many, complex interactions and interdependencies between all these
infrastructure systems, the people who depend on them, the physical environment and ecological
systems. Australia’s National Disaster Risk Reduction Framework emphasises: “the networks that
ensure the sustained delivery of food, water and energy involve complex interactions between
infrastructure, people, the environment, money and technology. A failure in any of these elements
could have wide-ranging consequences across communities, businesses, governments and
economies”.
The IPCC AR6 report stresses the importance of undertaking systems analyses to understand these
complex interactions – including how and when critical infrastructure is likely to fail under future
climate scenarios, and how this can cause cascading impacts to key services, the population,
physical assets and the environment.
Noosa & Sunshine Coast Council’s Regional Climate Action Roadmap (RCAR, 2022) included a
priority action to unpack cascading and compounding impacts to Council services from the failure of
electricity, water, wastewater, telecommunications and transport.
Grant funding of $1.1m from the Queensland Reconstruction Authority was awarded to both councils
as part of the Queensland Resilience and Risk Reduction Fund 2022-2023 to undertake the
Cascading Climate Risks from Critical Infrastructure Failure Project (CIF).
The two-year CIF Project systematically explored complex climate risks from critical infrastructure
failure to key Council services to identify management, governance and operational interventions to
increase preparedness and resilience as the regional climate continues to change.
The aims of the Project were to:
Page 4
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
• Identify the key drivers of risk, and interactions between both drivers and risks, to council assets
and services from critical infrastructure failure, and subsequently identify strategies to reduce
these risks.
• Build regional understanding of the interdependencies between critical infrastructure and how
these will be affected by climate risks.
• Introduce ‘climate justice’ considerations into Councils’ responses and shared responsibility
agenda by exploring how disruption and failure of council services, arising from cascading
impacts and exposure and vulnerability to climate-related hazards, may have disproportionate
impacts across the region.
The objectives were to:
• Establish working relationships, and shared understanding, between providers of critical
infrastructure systems and Councils, on the interdependencies between critical infrastructure
and Council services and how these may be affected by complex climate risks that can cascade,
compound, and aggregate.
• Identify key drivers and determinants of risk such as vulnerabilities and exposures of Council
services to critical infrastructure failure – and potential strategies to address these vulnerabilities
and exposures.
• Identify the complex interactions of risk drivers within and between each determinant of risk and
amongst risks, including understanding the role that mitigation and adaptation responses can
play in reducing or increasing risk.
• Build targeted and shared understanding with the broader community of how critical
infrastructure can be affected by climate risks, and to assist them in identifying and addressing
their own vulnerability and exposure to the impacts of critical infrastructure failure.
An Executive Steering Group (ESG) which included CEOs and executives from both councils, a
Stakeholder Reference Group (SRG) with all regional CI providers (see Stakeholder Engagement
section below for details), and a Project Steering Group (PSG) of key internal staff from both councils
were established as part of the governance framework for the project. These groups were important
to enable a strategic and collaborative approach throughout the project, reducing operational silos
and facilitating interdisciplinary technical support with strong executive direction.
The project was also supported by consultants.
Approach
The CIF project focussed on unpacking the complex cascading and compounding risks to Council
services when critical infrastructure fails. Figure 1 demonstrates how impacts cascade from one
system to the next, starting with climate hazards and ending with community who depend on Council
services. Each cascading element can also be subject to compounding effects due to tightly coupled
systems with interactions and interdependencies between elements in each system.
Page 5
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026 Figure 1 The cascading and compounding dimensions of climate hazards and critical infrastructure failure. Figure developed by Councils & Alluvium/Climate in Mind. Over the two-year project, the cascading and compounding critical infrastructure risks were examined through 7 stages as noted below. 1. Project inception, planning and establishment Development of project plan, communication and engagement plan and Monitoring, Evaluation, Reporting & Improvement (MERI) framework, and establishment of the governance structure. 2. Baseline Stocktake Baseline stocktake reviewed existing knowledge on critical infrastructure failure and the extent of planning for climate hazards in our region. 3. Critical Infrastructure Failure Scenarios Following a review of climate hazard projections for the Noosa and Sunshine Coast region, the hazard scenario timeline (Figure 2) was developed, in conjunction with climate scientists to understand how hazards are likely to change in the future. The timeline illustrates historical extreme events that have occurred in the region and projects forward to provide plausible future hazard scenarios based on climate projections. Looking ahead, projections show reductions in the time between events, reducing the time to recover, as well as increasing likelihood of more intense events occurring in close succession.
Page 6
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
Figure 2 Timeline of recent and plausible future climate hazards for southeast Queensland, demonstrating a trend of
compounding hazard events with short recovery periods between events. Figure developed by Councils, Climate in Mind
and climate scientist Kevin Hennesy (Climate Comms).
Workshops with critical infrastructure and critical service providers highlighted that compounding
hazards (e.g. a simultaneous storm tide, riverine flood and severe wind hazard event driven by a
cyclone) in the near-term are likely to increase the likelihood of multiple critical infrastructure failures.
Outages may be prolonged, extending to a week, or longer, with hinterland areas particularly at risk.
Workshops highlighted impacts of outages for one sector are likely to cascade to other sectors. For
example, power outages can cascade to water and wastewater outages if water supplies rely on
pumping and filtration. Disrupted power also accounts for the vast majority of telecommunications
outages, which then reduces access to web-based services, phone lines and transport systems.
4. Assessing Cascading Climate Risks
Workshops with Council staff across a range of service areas were conducted using the critical
infrastructure failure scenarios from Stage 3. The key exposures, vulnerabilities and potential
impacts (i.e. risks) to key Council service delivery areas were identified and risks were prioritised.
The project identified a range of major to moderate impacts to Council services arising from
prolonged and cascading critical infrastructure failure. Some of the most significant include:
• Reduced productivity (e.g. from inability to access buildings, sites, intranet, online services, as
well as backlogs in work, increased workloads, etc)
• Communication failures (e.g. with staff, contractors, key stakeholders, community, etc)
• Inadequate supplies to deliver services (e.g. fuel and equipment supply)
• Disruption to disaster response activities
• Physical impacts to staff from unsafe and unclean workplaces
• Mental health impacts to staff from workload, uncertainty, and extra demands
• Operating and capital costs increase
• Impacts to revenue streams
Page 7
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
• Reduced quality of organisational decision making, accountability, and transparency
• Reputational damage due to decline in quality and quantity of services
Physical risks to staff from outages in heating and cooling systems, drinking water and sanitation
systems, building security and CCTV were also highlighted. Notably, staff in the field are more
vulnerable when communications systems fail. Outages can also cause damage to assets,
inefficiencies as staff deploy workarounds, and loss of revenue from cancelled activities and events.
The project also highlighted a range of governance risks. CI failure can affect staff abilities to access
and update data in organisational systems, proceed through standard delegation processes, use
advisory and governance services, meet mandatory requirements, make timely decisions and
provide information to executives. As impacts cascade through and across Council operations and
ultimately undermine service delivery, this results in negative impacts on community who rely on
these services, leading to damage to Council’s reputation and reduced levels of trust from the
community.
Together these risks can lead to major disruptions to Council service delivery, reduced levels of staff
safety and declining staff wellbeing and resilience, increased costs to deliver services and/or reduced
revenue, and damage to Council’s reputation and trust from the community.
5. Preparedness and Adaptation Measures
Stage 5 investigated potential preparedness and adaptation measures that could address the risks
identified in Stage 4. A hierarchy of interventions starting with redesigning services and reducing
reliance on critical infrastructure, through to emergency backups were identified:
1. Redesigning services, assets, and sites to reduce reliance on CI (e.g. through improved
efficiency or eliminating the need for the CI)
2. Providing the CI service in-house to better enable a rapid recovery and build in redundancy
3. Contracting for priority services
4. Management measures to proactively plan for interventions that reduce the severity of impacts
5. Emergency backups
This stage demonstrated that, while Council faces substantial risks from critical infrastructure failure
technical and non-technical measures can be taken now to prepare and adapt:
Technical solutions include:
• resilience measures such as solar photovoltaic panels and batteries for power;
• satellite services for alternative internet access;
• rainwater tanks for water supply; and
• composting toilets for wastewater.
Non-technological measures include:
• ensuring systems, policies and procedures are in place to effectively respond during a disruption,
as well as to raise staff awareness, and build capacity. A priority is to establish the appropriate
policies and procedures for strategic workforce planning and alternative working arrangements;
and
• improving data collection to improve our response to critical infrastructure disruptions and future
risk and opportunity assessments. Key data to collect includes existing CI usage rates to enable
effective design of alternative and backup systems, as well as capturing the scale and nature of
disruption during events, including monitoring impacts on staff and service provision.
Page 8
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026 In many cases, technological and non-technological interventions not only enhance resilience to critical infrastructure failure but also provide a range of co-benefits to everyday operations through long-term cost savings, improved governance, workforce certainty, reduced emissions, etc. Resilience measures must be considered holistically to reflect interdependencies and ensure overall system resilience. The project demonstrated the need to integrate measures within individual critical infrastructure sectors and to coordinate measures across sectors, given their high level of interconnection. Stage 3 clearly showed how disruptions in one sector can cascade into others. For example, providing satellite services for alterative internet access may be impacted if back up energy supplies are not in place. Similarly, rainwater tanks that require pumps and filtration are also dependent on back up energy supplies. Figure 3 is an example of measures that could be combined for the energy sector. As shown, solar panels can be combined with batteries and diesel generators to provide alternative power. Each option has limitations, for example diesel generators can run out of fuel and solar panels may generate less energy under cloudy conditions. For this reason, combining solutions, rather than relying on one alternate source of power, is recommended. Figure 3 Example adaptation options for energy supply. Figure developed by Councils and Alluvium/Climate in Mind. Similarly, as Figure 4 demonstrates, the interdependencies between critical infrastructure services require adaptations across all sectors. For example, alternate back up power is beneficial but if telecommunication networks (mobile networks and internet services) are impacted by a broad outage, then back up power on site would not be enough to ensure resilient telecommunications. Alternatives like satellite services and even radios can be considered alongside back up energy sources to provide resilience across both sectors. Equally, resilience needs to be enhanced in water and wastewater treatment as well as for the transport network as these are also interdependent sectors.
Page 9
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026 Figure 4 Adaptation solutions for the energy sector and interconnections with other sectors where adaptation options will also be required. Figure developed by Councils and Alluvium/Climate in Mind. Implementing the CIF findings across Council will require a strategic approach to collaborate across the organisation to embed the findings, identify asset-level and administration-level risks and opportunities and to support the identification and implementation of adaptation solutions within and across critical infrastructure types to provide diversity redundancy, and connectivity. 6. Business Case Stage 6 delivered a business case for adaptation measures to enhance resilience at the Noosaville Depot/Local Disaster Coordination Centre (LDCC), and a second case study for resilience measures for the new Noosa Leisure Centre , which would function as a place of refuge during disasters. For each case study, a base case of costs and benefits was established for a break-even analysis. As illustrated in Table 1, for the Noosaville Depot/LDCC, the economic analysis demonstrated that productivity losses alone during a 7-day period of disruption, would cost approximately $237,000. To combat this, temporary (e.g. generators, bottled water and Portaloos) and permanent (e.g. solar and batteries, rainwater tanks and off-grid toilets) resilience measures were assessed to determine the number of 7-day outages that would achieve a break-even point. The analysis considered measures that would enable the Noosaville Depot/LDCC to operate at 25% and 75% capacity and found that for temporary measures, the break-even point was achieved within a single 7-day outage over a 20- year period. For permanent measures, the break-even point was less than five 7-day outages over a 20-year period. While temporary measures are especially cost-effective, there may be challenges to implementing these in unforeseen events or widespread hazard events where demand for temporary back-up facilities may be in high demand across the region. Permanent measures, while representing a more substantial initial investment, would be in place and ready to respond to sudden outages as well as providing further benefits in reducing costs under business-as-usual operations. Based on this initial assessment, the business case for permanent measures has a high benefit cost ration for Council even just considering avoided productivity losses. The measures would also support resilience for outages of shorter durations and ultimately reduce the risks of the Noosaville Depot/LDCC being unable to operate safely and effectively at these critical times.
Page 10
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
Temporary Measures Permanent Measures
Operational 25% 75% 25% 75%
capacity level
Cost $31,697 $75,426 $291,917 $826,067
Break-even point 0.5 0.4 4.7 4.6
Table 1. Economic analysis for Noosaville Depot bundled resilience options. Analysis compares temporary and permanent
measures for operating the Depot at 25% and 75% capacity. The break-even point represents the number of 7-day outages
that would offset costs
7. Lessons Learned
Some of the key reflections in the Lessons Learned report included challenges around data
availability and constraints relating to the Security of Critical Infrastructure Act which limits the level
of detail that critical infrastructure providers can share with Councils and the project consultants.
Next steps
The following 3 areas are suggested as priority next steps for acting on the findings of this Project.
1. Upgrades to the Noosaville Depot / LDCC
A capital works budget request for FY26/27 has been submitted for detailed investigation and
planning at the Noosaville Depot/LDCC, including understanding potential locations and sizing of
technological measures and considering combinations of both temporary and permanent measures.
2. Data collection
Key data gaps that need to be addressed include the following:
• Data on staff affected and amount of downtime for different events
• Impacts on infrastructure projects
• Direct costs
• Impacts and costs attributable to disruption of community use of leased assets
• Disruption of waste collection services
3. Other actions
While the measures recommended for the Noosaville Depot/LDCC are an initial priority, there are
further actions that need to be taken across the organisation. This includes:
• Investigate and improve backup power, water, wastewater and telecommunications options for
evacuation centres and other key Council sites.
• Update Business Continuity Plans to account for longer durations and cascading impacts of
critical infrastructure failure in line with the CIF Project findings.
• Advocate for critical infrastructure providers to register assets that require prioritisation during
outages on critical service lists.
• Develop MOU with fuel providers for priority refuelling of critical generators.
• Collaborate with bulk or large fuel suppliers to participate in or observe exercises to test Council
response to fuel shortages post-disaster.
• Advocate for increased telecommunication network resilience, particularly for critical
communications such as 000, through improvements to the network’s capacity before, during
and after events.
• Investigate viability of electrification of transport infrastructure and households to improve
resilience prior to, during and post disaster events, as well as to reduce emissions which reduces
the frequency/ severity of the hazards.
• Develop program to embed disaster and disruptive event management into Council plans and
operations.
Page 11
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
• Investigate options to support Council staff wellbeing and build workforce climate resilience
including understanding the impacts of climate change on staff.
• Develop program to embed disaster and disruptive event management into Council plans and
operations.
• In partnership with local hospitals, investigate and report local arrangements for surge staffing
to LDCC.
Link to Corporate Plan
Theme No. 4 - Future
This theme is focused on our future, strengthening our relationship with First Nations peoples and to
ensure our community is prepared and resilient to change. A focus on youth, climate resilience and
adaptation, sense of place and destination management.
Previous Council Consideration
Ordinary Meeting Minutes, 19 August 2021 Item 3, Page 28
That Council note the report by the Project Coordinator – Climate Change Adaptation to the General
Committee Meeting dated 16 January 2023 and:
A. Note the Regional Climate Action Roadmap developed in partnership with Sunshine Coast
Council;
B. Note the continued advancement of climate risk management through the three priority themes
identified by Sunshine Coast Council and Noosa Council in the Roadmap, namely: building
climate-ready councils, empowering climate-ready communities and advocating for a climate-
ready region.
Finance
The two-year Project was achieved through grant funding of $1.1m by the QRA. This was paired
with in-kind contributions in staff time from both Councils and all stakeholders involved as outlined
below in Table 2.
Table 2 Project budget including in-kind contributions and actual expenditure
The project’s findings and recommendations will require additional funding and resourcing to
coordinate and implement priority actions, to be considered through future budget processes,
including additional staff resources.
A capital works budget request has been made to advance detailed investigations for bundled
resilience measures at the Noosaville Depot (as demonstrated in the Business Case section above)
for consideration through the FY26/27 budget review process.
Risk & Opportunities
Inaction on adapting to cascading climate impacts is likely to lead to prolonged disruption and failure
of Council services across critical functions such as disaster management, customer service,
Page 12
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
finance, waste management, and civil operations. The Enterprise Risk and Opportunity Management
Policy and associated Framework states that Council will only tolerate unforeseen interruptions to
critical services for up to 1 day and will not tolerate failure to develop plans to respond to a disruption
and ensure continuity of critical business functions. While Council has developed business continuity
plans, the CIF project has demonstrated that these anticipate outages of far shorter durations than
can be expected in the near future.
As demonstrated above, cascading and compounding critical infrastructure failure poses an
immediate risk to Council staff, operations and service delivery. The top risks to Council, as elicited
in Stage 4 of the Project, are:
• Major disruption to Council service delivery
• Reduced levels of staff safety and declining staff wellbeing and resilience
• Increased costs to deliver services and/or reduced revenue
• Damage to Council’s reputation and trust from the community
These reflect the nature of the risks to climate change disruptions and poor management of natural
catastrophes/disaster events that are highlighted in the Strategic Risk Register as extreme risks.
Other important plans that raise related concerns and requirements to address risks related to this
Project are as follows:
1. The Corporate Plan (2023 – 2028) notes several strategic risks that are especially relevant to the
CIF project. These are also identified in the Strategic Risk Register and actions to mitigate these are
included in Council’s risk management program. The risks highlighted are:
• Managing our workforce
• Business continuity planning
• Disaster management and recovery
• Protection of our environment and climate change impacts
2. The Climate Change Response Plan includes key themes related to the CIF project around
• Strong leadership and governance, including an action to strengthen partnerships with
governments and stakeholders to take urgent action to achieve a low carbon economy and
resilient community
• Resilient and adaptive communities and built environments, including building Council and
community awareness and preparedness for climate change and extreme weather events.
3. The CIF Project was part of the Regional Climate Action Roadmap in collaboration with RCAR
partners, Sunshine Coast Council. As such, the Roadmap contributes directly to the goal of building
climate ready councils by strengthening regional collaborations for climate disaster projects and
unpacking cascading and compounding impacts to Council services from failure of critical
infrastructure.
The project has identified a range of technical and non-technical adaptation measures that can be
adopted now to strengthen Council’s resilience to future critical infrastructure failure. Implementing
these adaptation measures presents opportunities to not only address the risks identified and
enhance resilience to CI failure, but to also reduce everyday costs through reduced energy bills,
reduced dependency on critical infrastructure services and enhanced reliability during outages that
may be unrelated to disaster events.
The CIF Project represents a considerable innovation in addressing future hazards and risks
associated with climate change. Council has an opportunity to progress the findings of the Project
and in doing so not only enhance the resilience of the organisation to climate risks but also to
demonstrate strong leadership in an area that has not been considered by most other Councils.
Working in partnership with Sunshine Coast Council and regional critical infrastructure providers,
Page 13
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
presents an opportunity to advocate for priority services, priority recovery and working across
providers to enhance resilience between interdependent sectors.
Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.
Consultation
External Consultation - Community & Stakeholder
Stakeholder engagement has been a vital part of the CIF Project throughout. Overall, the Project
Team engaged in forty-six (46) formal engagement activities and engaged with a range of internal
and external stakeholders across the Council, critical infrastructure service providers and community
groups.
A summary of the formal engagement activities is provided in Table 1 (below) regarding the purpose
of the engagement activities, the stakeholders involved and the number of each type of event. The
formal engagement activities being classified in accordance with the following themes:
• Governance: Engagement with the Executive Steering Group (including both Council CEOs and
key Executives), Project Steering Group and Stakeholder Reference Group (comprising
representatives from critical infrastructure and critical service providers) to inform and guide
project delivery
• Task delivery: Engagement with:
o Council staff and the Stakeholder Reference Group in workshops to deliver specific tasks
(e.g. critical infrastructure failure scenarios, risk assessments and prioritisation of risks and
adaptation options.)
o Targeted workshops with community and business groups to inform understanding of CI
related cascading risks and community resilience.
• Awareness raising: Provision of briefings for:
o Cross sectoral groups with a high level of interest in the project, particularly the District
Disaster Management Group (DDMG) and Local Disaster Management Group (LDMG) for
each local government area
o Governance groups and service areas within each local government
Page 14
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
Table 3 An overview of the formal engagement activities delivered
In addition to the formal engagement activities, informal engagement activities also contributed
significantly to the delivery of the Project. These activities included:
• Ad hoc telephone calls and meetings with council staff and the Stakeholder Reference Group
(SRG) to inform “Requests for Information” (RFI’s) received from the consultants / technical
specialists
• Ad hoc telephone calls and meetings with council staff to:
o Identify and seek access to data that quantified CI failure related costs and damages
o Inform understanding of ‘Controls’ implemented by the councils and, regarding CI failure
patterns expected in the future, their limitations
o Identify, prioritise and characterise the case study sites that were a focus for the economic
analysis
o Obtain legal advice and guidance
• Meetings to inform understanding of opportunities and preferences for post project embedding
of learnings from the CIF project.
• Ad hoc awareness raising
External consultation centred on engagement with critical infrastructure providers and community
groups Critical infrastructure providers were primarily engaged as part of the SRG. The SRG
comprised representatives from the following critical infrastructure providers:
• Energy Queensland / Energex
• Powerlink
• Seqwater
• Unitywater
• Telstra
• Optus
• NBN Co
• Department of Transport and Main Roads
• Queensland Rail
• Queensland Fire Department
Page 15
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
• Queensland Department of Health
• Queensland Police Service
• Queensland Department of Education
• Queensland Reconstruction Authority
The SRF participated in a number of workshops throughout the project. Of these, key workshops
took place in 2022. This included 3 x two-hour on-line climate risk workshops delivered in February
2022. Around 90 key sectoral leaders from across the region were involved in exploring climate
change related risks and opportunities for the region. These workshops delivered improved
understanding of local sectoral leader knowledge and perspectives regarding:
• climate risks specific to our region, and the local causes of those risks
• priority local climate risk issues, and the diverse parties who have control and responsibility for
addressing these issues
• interest in advancing their own climate risk management and pursuing collaborative
approaches to share responsibility.
In July 2022, 55 key sectoral leaders were engaged in a second series of Roundtable workshops (1
x 1.5-hour on-line workshop and 2 x 2-hour in person workshops). At these next Roundtables,
community stakeholders were engaged to:
• Review our learning from Round 1;
• Present and discuss the Roadmap;
• Identify trusted local networks that the Councils can draw on to ‘Empower Climate Ready
Communities’ (Focus Area 2 of the Roadmap) to involve the broader community in the climate
conversation and climate risk management action.
For community engagement, an External Survey was distributed to the residents of Noosa and
Sunshine Coast Council regions, with an abridged version being circulated to younger residents
(aged 18 years and younger). The Community survey elicited 1347 responses (234 responses from
Noosa, 1113 responses from Sunshine Coast) and 270 responses were elicited from the Youth
within the region.
Beyond contributing directly to the project’s insights, engaging regional critical infrastructure
providers expanded the Sunshine Coast and Noosa’s current business continuity and disaster
planning. The workshops and engagement in the Project overall helped raise awareness, particularly
among critical infrastructure providers, of the interdependencies in their service provision and the
compounding impacts of failures which ultimately undermine Council service delivery. The ongoing
value of connecting across service providers has been recognised through the project and is
reflected in their support for an ongoing partnership through the Stakeholder Reference Group
(SRG).
Internal Consultation
Departments consulted:
Office of the CEO, Mayor & Community Services Corporate Services
Councillors
Mayor & Councillors x Director x Director
Chief Executive Officer x Community Development x Financial Services
x Executive Officers x Sport & Active Lifestyles x Fleet
x Community Engagement Arts & Culture Revenue Services
x People & Culture x Community Connection x ICT
x Governance x Customer Experience Procurement
Commercial Property
Page 16
PLANNING & ENVIRONMENT COMMITTEE MEETING 10 FEBRUARY 2026
Strategy & Environment Development & Regulation Infrastructure Services
x Director x Director x Director
x Strategy & Sustainability Development Assessment x Infrastructure Planning, Design
and Delivery
x Economic Development & Local Laws x Civil and Asset operations
Destination Management
x Environmental Services Environmental Health x Waste
Innovation & Digital Hub x Building & Plumbing x Building & Facilities
Property / Permits x Disaster Management
Used in these records
CASCADING CLIMATE RISKS FROM CRITICAL INFRASTRUCTURE FAILURE PROJECT REPORT · ReportReportsMeeting 935 · read item & discussion ↗
About this file
- File size
- 426 KB (small file)
- File type
No other editions are linked here.