24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                                                                                      EWSM- 4 VEGETATION AND WEED MANAGEMENT
                                                                                                                                                                      Version 1



EWSM- 4 VEGETATION AND WEED MANAGEMENT
Hierarchy of Control (HOC): 1. Eliminate 2. Substitute 3. Isolate 4. Engineer 5. Admin 6. PPE


                                                                                                                                                                Responsible Person/s for
    Environmental Aspects                          Impacts                    HOC                          Controls / Work Methods
                                                                                                                                                                   Monitor & Review

Prior to site establishment, check   Risk of adverse environmental harm        5     Before clearing, removing vegetation, or lopping trees, ensure the        Project Manager/
for permit for clearance or remove                                                    project has obtained all permit to clear.                                 Environmental Consultant
vegetation
                                     Misidentify clearing zone                 5     Clearly and accurately define the legal external boundary of you          Project Manager
                                                                                      property and the public land.                                             Site Manager
                                     Erosion and sediment runoff               5     On sites with a soil disturbance exceeding 2500m 2, Erosion and           Project Manager/
                                                                                      Sediment Control Plans need to be signed-off by a suitably qualified      Environmental Consultant
                                                                                      and experienced professional***
                                     Spreading weeds                           5     Identify the present of declared weeds before any ground disturbance      Project Manager/
                                                                                      activities.                                                               Environmental Consultant
Planning works                       Mass soil loss during significant rain    5     Clearing work should be staged to minimise the duration for which soils   Site Manager
                                     events                                           are exposed to wind, rain and concentrated runoff
                                                                                     Clearing zone is protected by erosion and sediment control measures
Lopping/ pruning tree                Risk of adverse environmental harm        5    Check local regulations and laws for protected trees before taking any      Project Manager
                                     on local vegetation and biodiversity           actions                                                                     Environmental Consultant
                                                                                    ACT:
                                                                                      - Trees are 12 or more metres high; have a trunk with a circumference
                                                                                         of 1.5 metres or more, one metre from the ground; have two or more
                                                                                         trunks and the sum of their individual circumferences at 1 m above
                                                                                         ground is 1.5 m or more; or have a canopy 12 m or more wide.
                                                                                    SA:
                                                                                      - Regulated – trunk circumference of 2+ metres at one metre above
                                                                                         ground level (for multiple trunks, the average circumference of each
                                                                                         is 625+mm)
                                                                                      - Significant – trunk circumference of 3+ metres at one metre above
                                                                                         ground (for multiple trunks, the average circumference of each is
                                                                                         625+mm)
                                                                                    VIC:
                                                                                      - Canopy size (from as narrow as 3500mm)


                                                                                                                                                                                           1
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.