INFRASTRUCTURE AND SERVICES MEETING AGENDA 25 MARCH 2014
Option 3. High Level Management Intervention (Environmental Services, Regulatory
Services, and Asset Planning and Delivery Services).
• All of the above actions outlined in Option 2; and
• Engagement with the local community in the design and install of a bank stabilisation and
access structure for recreational purposes at the site. This would include erosion mitigation
measures along the most impacted sections of the creek bank.
Option 3 would achieve the same outcomes as Option 2, but in the long term the site will be
capable of sustaining higher levels of recreational use. Additionally, the community will have the
opportunity to be involved in designing the formalised access to the creek.
Option 4. Minimal Management Intervention and Tree Removal (Environmental Services,
Regulatory Services)
• All of the above actions outlined in Option 2; and
• Removal of high risk trees.
Option 4 would achieve the same outcomes as Option 2. In addition, the risk of failure of existing
eroded trees, bank collapse and public safety risk would be further reduced. However the
environmental and amenity values of the removed trees would be lost.
Previous Council Consideration
Nil.
Finance & Risk
Option 1 - Do nothing Current operating costs only.
Option 2 - Minimal management intervention (Environmental Services and Regulatory
Services), the associated costs for signage, fencing and monitoring is estimated to be in the
order $18,000, with the majority of expenditure occurring in the current financial year.
Option 3 High level management intervention (Environmental Services and Asset Planning
and Delivery Services), the associated costs for design and installation of an appropriate
structure (which will include in-stream erosion mitigation) is estimated to be around $220,000. It
is estimated that $20,000 of expenditure will occur in the current financial year.
Option 4 Minimal management intervention and tree removal (Environmental Services and
Regulatory Services) the associated costs for signage, fencing and monitoring is estimated to be
in the order $18,000 plus approximately $6,000 for tree removal works with the majority of
expenditure occurring in the current financial year.
CONSULTATION
External Consultation - Community & Stakeholder
Council staff have received background information on the matters dealt with in the report from a
number of local residents.
Internal Consultation
A report on Weyba Creek Esplanade – Issues for Natural Area Management was tabled for
discussion at the Community Infrastructure Departmental meeting on 6 March 2014.
Page 34 of 60
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.