Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

2019-12-11 SM Agenda - Item 1 - Attachment 5 - Final New Noosa Plan - Part 1-6 - Clean version

of 400

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Part 4              Local Government Infrastructure Plan

4.1                 Preliminary
(1)   This local government infrastructure plan has been prepared in accordance with the requirements of the Planning Act 2016.
(2)   The purpose of the local government infrastructure plan is to:
      (a)   integrate infrastructure planning with the land use planning identified in the planning scheme
      (b)   provide transparency regarding a local government’s intentions for the provision of trunk infrastructure
      (c)   enable a local government to estimate the cost of infrastructure provision to assist its long term financial planning
      (d)   ensure that trunk infrastructure is planned and provided in an efficient and orderly manner.
      (e)   provide a basis for the imposition of conditions about infrastructure on development approvals.

(3)   The local government infrastructure plan:
      (a)   states in Section 4.2 (planning assumptions) the assumptions about future growth and urban development including the
            assumptions of demand for each trunk infrastructure network
      (b)   identifies in Section 4.3 (priority infrastructure area) the prioritised area to accommodate urban growth up to 2031
      (c)   states in Section 4.4 (desired standards of service) for each trunk infrastructure network the desired standard of
            performance
      (d)   identifies in Section 4.5 (plans for trunk infrastructure) the existing and future trunk infrastructure for the following networks:
            (i)     stormwater
            (ii)    transport
            (iii)   parks and land for community facilities

      (e)   provides a list of supporting documents that assist in the interpretation of the local government infrastructure plan in the
            Editor’s note – Extrinsic material at the end of Section 4.
      (f)   this local government infrastructure plan excludes water supply and sewerage networks as these networks are the
            responsibility of Unitywater as distributor­retailer and are subject to their Netserv Plan.

4.2                 Planning assumptions
(1)   The planning assumptions state the assumptions about:
      (a)   population and employment growth
      (b)   the type, scale, location and timing of development including the demand for each trunk infrastructure network

(2)   The planning assumptions together with the desired standards of service form a basis for the planning of the trunk infrastructure
      networks and the determination of the priority infrastructure area.
(3)   The planning assumptions have been prepared for:
      (a)   the base date (2016) and the following projection years to accord with future Australian Bureau of Statistics census years:
            (i)     mid (2021)
            (ii)    mid (2026)
            (iii)   mid (2031)

      (b)   the LGIP development types in column 2 that include the uses in column 3 of Table 4.2.
      (c)   the projection areas identified on Local Government Infrastructure Plan Maps LGIP­PIA­SC­1 to LGIP­PIA­SC­11 Priority
            Infrastructure Area and Service Catchments in Schedule 3 —Local government infrastructure plan mapping and tables.

(4)   Details of the methodology used to prepare the planning assumptions are stated in the extrinsic material.

Table 4.2—Relationship between LGIP development categories, LGIP development types and uses
Column 1                    Column 2                                   Column 3
LGIP development            LGIP development type                      Uses
category



  **FINAL DRAFT ­ Post Consultation 2019**
                                                                                                                                   Page 1 of 11
Log in to download the original file

2019-12-11 SM Agenda - Item 1 - Attachment 5 - Final New Noosa Plan - Part 1-6 - Clean version(PDF, 15MB).pdf · 15.6 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.