Performance outcomes Acceptable outcomes
PO18
Buildings and structures adjacent to land in a residential zone: No acceptable outcome provided
(a) have a domestic scale, with building size and landscaped
setbacks consistent with that for development in the
residential zone; and
(b) are sited and orientated to minimise the likelihood of
overlooking the private open space of adjacent residential
activities; and
(c) incorporate fencing, landscaping and screening to mitigate
impacts on adjoining residential uses.
PO19
Development facilitates the security of people and property having No acceptable outcome provided
regard to:
(a) opportunities for casual surveillance and sight lines;
(b) exterior building design that promotes safety;
(c) adequate lighting;
(d) appropriate signage and wayfinding;
(e) minimisation of entrapment locations; and
(f) building entrances, loading and storage areas that are well
lit and lockable after hours.
PO20
Walkways, car parks and publicly accessible facilities, including No acceptable outcome provided
toilets, and bicycle racks are located and designed to allow casual
surveillance by other persons.
PO21
Pathways allow clear sightlines in all directions. No acceptable outcome provided.
PO22
Adequate lighting is provided to building entrances, carparks and No acceptable outcome provided.
pedestrian routes.
Editor’s Note—Applicants may find useful guidance in the
Queensland Government’s Crime Prevention through
Environmental Design Guidelines for Queensland
Drainage Table 6.8.2.3 Criteria for assessment (part)
Performance outcomes Acceptable outcomes
Earthworks and Drainage
PO23 AO23
Development and associated site works including filling, Development and associated site works, including filling and
excavation and retaining structures do not directly, indirectly or excavation, are designed and constructed to ensure overland flow
cumulatively cause adverse impacts external to the development and/or flooding is not worsened, impeded, or otherwise diverted to
site by: adversely affect other properties.
(a) causing ponding of water on the site or nearby land;
(b) increasing flooding, which adversely affects the safety or
use of any land upstream and downstream; or
(c) adversely affecting the flow of water in any overland flow
path.
**FINAL DRAFT Post Consultation 2019**
Page 6 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.