Maintenance of ESC measures must occur in accordance with Table 5 below.
Table 5 - ESC maintenance requirements.
ESC Measure Maintenance Trigger Timeframe for
Completion of
Maintenance
Sediment basins When settled sediment exceeds Within 7 days of the
the volume of the sediment inspection.
storage zone
Other ESC measures The capacity of ESC measures By the end of the day.
falls below 75%.
Sediment accumulation on ESC devices is to be removed and disposed of to the satisfaction of NSC.
6. Conclusion
This SWMP outlines how stormwater runoff from the site will be managed in order to not adversely impact
the receiving environment.
Stormwater runoff from developed areas of the site shall be directed to a detention & infiltration tank with
approximately 7m3 detention capacity at the rear of the site. Runoff from the tank shall discharge via either
infiltration or shall surcharge and discharge east to Sunshine Beach as per existing conditions. The detention
tank configuration shall ensure the peak flow rate and total runoff volume discharging to Sunshine Beach is
reduced to pre-development levels. Final layout & configuration of the tank shall be confirmed at the detailed
design phase.
Stormwater treatment could be managed on site by first flush diverters directing runoff for irrigation of
landscaped areas and/or the installation of field inlet pit inserts. Based on the scale of the proposed
development, and typical pollutants produced, these measures are considered adequate.
By implementing the proposed stormwater management system, and providing adequate maintenance, the
downstream environment and neighbouring properties will not experience any adverse deterioration of water
quality as a result of the proposed development.
24 Arakoon Street, Sunshine Beach QLD 4567
Job No – S18-003 STORMWATER MANAGEMENT REPORT 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment D - Stormwater Report.PDFRelated documentApplication case desk ↗
About this file
- File size
- 10.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.