Minor Change Existing Approval MCU25 0057 01, OPW25 0078 01 & RAL25 0010 01 [As Published]
34. Council may request further controls to be installed should the implemented measures be
found inefficient.
35. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
36. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
37. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
38. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
Vegetation Clearing
39. Removal of trees and vegetation must be undertaken by a qualified person* and must
include:
a. No damage to vegetation for retention.
b. Legal disposal of all removed vegetation and debris.
Fauna Management
40. Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
has left vegetation or has been relocated by a qualified fauna spotter catcher.
*(Refer to Advisory Note)
Landscape Works
41. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice.
*(Refer to Advisory Note)
42. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
43. Street trees must:
a. Meet AS2303 Tree stock for landscape use.
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
44. The finished level of all mulch in garden beds and landscaped medians is to be a minimum
of 50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
Page 12 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.