PRESENTATION - Jade Oakley x CR - Noosa Concept Final 24-4-25_Optimized · EXE25/0029

of 39

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

INSTALLATION
METHODOLOGY
The installation process has been carefully developed to align with both the fabrication             Equipment and Tools Required
methodology and the design intent of Crossing The Bar, ensuring a seamless, safe, and                •   Franna crane with licensed dogman for lifting and placement
structurally sound outcome. The steps below outline the general installation approach.               •   1.5-tonne excavator for footing excavation and post-installation re-landscaping

General Installation Process                                                                         On-Site Assembly
                                                                                                     The installation has been designed to be efficient and low-risk, with simplicity and structural
The two installation locations will be accurately marked out on site.                                clarity guiding both the sculpture’s construction and its site assembly. This methodology
                                                                                                     supports a safe and precise installation that respects both the technical demands and
•    Landscaping preparation will include the use of clean fill and excavation of footings as        aesthetic vision of the artwork.
     required.
•    If necessary, screw piles will be installed prior to reinforcement placement.
•    Concrete footings will be poured in accordance with the engineering specifications.
•    Once cured, the angled concrete plinths or pads will be fixed to the footings.
•    The boats will then be positioned and secured on top of the plinths.

All mounting points will be pre-coordinated with the project engineer and builder to ensure
compatibility with site conditions and structural requirements. These mounting points,
embedded in the underside of each concrete boat, are designed to withstand environmental
factors such as wind loading. Lifting lugs will be integrated into the concrete to facilitate safe
and precise installation.

Each sculpture will be placed near its final location, inverted, slung with the crane, rolled
upright, and lowered onto the prepared plinths. Final positioning and fixing will be completed
on site.

Following installation, all surrounding landscape areas will be reinstated and turfed to council
standards where applicable.




Noosa Council CityDeal Public Art Initiative | April 2025                                                                                                              Jade Oakley x Creative Road     21

Used in these records

About this file

File size
5.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

PRESENTATION - Jade Oakley x CR - Noosa Concept Final 24-4-25_Optimized.pdf · 5.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.