SCHEDULE - LANDSCAPE & EXTERNAL WORKS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NOTE: QUANTITIES PROVIDED ARE TO ASSIST IN TENDERING AND ESTIMATION. Totals
ALL QUANTITIES ARE TO BE CHECK MEASURED BY TENDERERS WHEN SUBMITTING PRICING.
Item Legend Code Description Specification Unit Qty.
A PRELIMINARIES AND SITE WORKS, MINOR EARTHWORKS, DRAINAGE
1 0 Site Establishment
1 Preliminaries Refer to specification to determine minimum Sum 1
required works.
1 2 Program PROGRAM DATES, MILESTONES AND HOLDPOINTS 0
TO BE ADDED HERE
START DATE:
PC DATE:
ENTRY WALL START DATE:
REHAB AREAS START DATE:
1 3 Initial Site Rubbish Removal Removal of waste items located on site. Items to Item 1
be removed before works commences.
1 |4 Set-out by surveyor required Survey by setout required. Design CAD files can Day 0
be supplied as requested.
2 Site Works/ Minor Earthworks
2 1 Shaping - adjust civil profiles to desired shape & Civil to provide site at handover minus 100mm m2 1083
trim +/-50mm of finished surface levels shown on
landscape plans
2 2 Cultivation as per specification Planting areas - 200mm cultivation m 773
Gypsum: Incorporate at the rate of 0.25 kg/m2. Turf areas - 100mm
REFER TO DETAIL
2 3 HOLD POINT - CULTIVATION- LANDSCAPE
SUPERINTENDENT TO INSPECTION PRIOR TO
TOPSOIL - PROVIDE Min. 72 HRS NOTICE
2 4 Additional Topsoil due to poor site conditions If subgrade is deemed to be a poor, i.e weathered m? 773
IF ORDERED rock, schist or heavy clay INSTALL an additional
200mm of site topsoil prior to garden bed
preparation
2 5 TPF Tree protection as per VMP - Temporary Fencing m 0
3 Drainage
3 1 Subsoil drains - allowance only Type: 150 mm to raingardens and 100mm Lm 0
diameter to other areas. 100mm slotted HDPP Ag
Drain wrapped in geo-textile, drainage gravel to
be 20mm recycled concrete. Queensland
Recycling Pty Ltd Ph 135 135.
3 CON Subsoil drainage conduits Type: 100mm UPVC Item 275
3 Podium planter water retention layer- |F ORDERED |Type: 100mm HydroCell foam layer with m? 0
protective geotextile over. Refer to detail
3 4 Pits - typically 300 x300 ACO Pits - within planting areas | Type: 300 x300 mm ACO Pits Item 33
Hot dip galv. Grates to AS1428.1
B HARDSCAPE
Pavements
1 General for all pavements Sealer: Provide a penetrative sealer to all
pavements except asphalt.
Sample Panels: Provide a 1m square sample
panel of all pavements ona pallet such that it
can be moved around site as required to
compare to finished work.
Slip resisitance: All pavements to be non-slip as
defined in the BCA
2 P1 Concrete 1 Refer Architect Plans m 0
P2 Concrete 2 Refer Architect Plans m 0
4 P3 Unit paving on concrete subbase Size: 400 x 400mm each 220
Colour: TBC
Supplier: TBC
Sealed: TBC
4 5 GR1 Gravel mulch Type: 20mm washed river gravel over weedmat m 124
Depth: 100mm
5 Fences and Barriers
5 1 Fl Fence type 1 - 1800 high to boundary Refer to Refer Architect specifications m 0
5 2 F2 Fence type 2 - Pool Fence Refer to Refer Architect specifications m 0
5 3 HR Handrail and Balustrades Refer to Refer Architect specifications m 0
5 4 BL1 Feature Bollard Refer to Refer Architect specifications Item 23
C SOFTSCAPE
6 Edging
6 Concrete edge to planting areas Refer to Detail. 150x150mm. m 131
6 Timber edge to planting areas - If ordered Refer to Detail m 0

 

 

 

 

 

 

 

 

 

 

OOSA DOMAIN APARTMENTS - SCHEDULE

 

 

7 TU Turf- (includes watering costs until PC)
7 Imported Soil Blend 100mm deep Soil Blend to AS4419 m? 310
2 Site Topsoil with amendments - |F ORDERED Amendments to be added to the 100mm deep m? 0
site topsoil SPREAD BY CIVIL.
- Soil amendments for Site topsoil should include
the following: Gypsum at (2.5t/ha) following top
soil spread and Dynamic Lifter (2kg/10m2).
Please allow for both Turf topsoil and planting
soil
7 3 TU Turf Agrade 'Legend' turf supplied by Jimboomba Turf m 310
3 PA Planting Areas - (includes watering costs until PC)
8 1 Soil Blend - Site Topsoil Minimum depth 300mm deep Site soil amended m? 773
with gypsum. Mound to 450mm to centre of beds
8 |2 Soil Blend - Imported - If ordered 300mm deep Soil Blend to AS4419. Mound to m 0
450mm to centre of beds. Submit sample for
apporval prior to install.
8 3 Fertiliser Apply dynamic lifter or approved equivalent as
per specification
8 14 Mulch to planting areas Forest Litter mulch 100mm deep m 773
M3 - Site mulch (install only) Site Mulch m- 0
8 DG1 -Decorative Gravel - 100 mm thickness Gravel Type: 20mm washed river gravel m 0
9 Planting Stock
9 1 100 Lt stock Refer to Plant Schedule Item 0
9 {2 45 Lt stock Refer to Plant Schedule Item 65
9 13 25 Lt stock Refer to Plant Schedule Item 3
9 4 300mm pots Refer to Plant Schedule Item 471
9 5 200mm pots Refer to Plant Schedule Item 142
9 6 140mm pots Refer to Plant Schedule Item 2028
9 Relocation of existing palm trees. Refer Planting Plan Item 2
9 |7 Tube stock- Native tube min. 75mm Refer to Plant Schedule Item 0
9 8 Slow release nutrient bags Each 2711
9 Water retention additive for each plant Green Harvest Rainsaver Water crystals or Each 2711
approved similar
* JFP Arborist to inspect plants at nursery to ensure compliance with NATSPEC - Specifying trees
10 PC Post Practical Completion - Plant Establishment Period and Maintenance
Note Practical Completion will be given at the time the Local Authority provides
On Maintenance or Superintendant certifies completion.
10 |1 Plant Establishment Period - 12 week period Fortnightly Mowing and turf edging to all turf Week 12
areas. Fertilising, pruning of street trees as
required and chemical and physical weed
removal to all garden areas. Rubbish removal as
required
10 |2 TU, PA Watering Costs during Plant Establishment Period |Over the 12 week period wateringis required to Week 12
(Provisional Sum) maintain healthy plant growth. Allow for min. 15
waters (3-1st week, 2-2nd week, 1 per week for
Note: the cost of watering prior to Practical following 10 weeks).
Completion being given is to be allowed forin Note: Rates per water will be used if additional
preliminaries or within softscape rates watering is required oras a credit if there is
adequate rainfall. (30mm per week adequate
rainfall). Requirement: Advise superintendent if
All water dockets are to be provided to demonstrate oa: )-Req a . p
timi dvol f teri additional watering is required due to hot
Iming and volume or watering weather /dry conditions over and above the
provisional 15 waters.
Should the weather be excessively dry and/or
hot and additional watering is required notify
superintendent at once. Plant deaths due to
watering will be replaced at the constractors
expense.
10 |3 RV Watering Costs during Plant Establishment Period |Over the 12 week period wateringis required to Week 12
(Provisional Sum) maintain healthy plant growth. Allow for min. 15
waters (3-1st week, 2-2nd week, 1 per week for
Note: the cost of watering prior to Practical following 10 weeks).
Completion being given is to be allowed forin Note: Rates per water will be used if additional
preliminaries or within softscape rates watering is required or as a credit if there is
adequate rainfall. (30mm per week adequate
rainfall). Requirement: Advise superintendent if
All water dockets are to be provided to demonstrate “ae )-Req - . p
. dvol f . additional watering is required due to hot
timing and volume of watering weather /dry conditions over and above the
provisional 15 waters.
Should the weather be excessively dry and/or
hot and additional watering is required notify
superintendent at once. Plant deaths due to
watering will be replaced at the constractors
expense.
11 PC Post Practical Completion - Ongoing Maintenance
Note Practical Completion will be given at the time the Local Authority provides
On Maintenance or Superintendant certifies completion.
11 ]1 TU & PA Ongoing Maintenance after Plant Establishment Fortnightly Mowing and turf edging to all turf Month 9
to areas. Fertilising, pruning of street trees as
Turf & Planting Areas including podium if applicable |required and chemical and physical weed
removal to all garden areas. Rubbish removal as
required
11 |2 RV Ongoing Maintenance after Plant Establishment Fortnightly maintenance as per Specification Months 9
to such as edging to all adjacent turf areas,
Revegetation Areas fertilising, pruning of vegetation as required,
maintenance of stakes & tree guards, and
chemical and physical weed removal to all
rehabilitation areas. Rubbish removal as
required to achieve On & Off Maintenance.
11 1/3 DLP Defects Liability Period - 52 weeks Weeks

 

 

 

 

 

 

 

 

 

 

 

APPROVAL ISSUE

NOOSA COUNCIL
GENERALLY IN ACCORDANCE
OPW12/0110.01 18 APR 2018

 

 

c OP WORKS 2018-02-23 ME ME WA
B DRAFT OP WORKS 2018-02-06 ME ME WA
A PRELIMINARY 2018-01-15 ME ME WA
ISSUE: DETAILS: DATE: DES: DC: QA:
Sass

:

 

}

 

JFOP
PAUAN/ANNPAIND

URBANCONSULTANTS

 

 

PLANNERS BRISBANE - SUNSHINE COAST - CENTRAL QLD
URBAN DESIGNERS BRISBANE - JFP House
SURVEYORS ~~~—- 76 Ernest Street,

South Brisbane Qld 4101
_—_—SOP'1007 3012 0100 W www. jfp.com.au
LANDSCAPE ARCHITECTS —JFP URBAN CONSULTANTS PTY. LTD. A.C.N. 050.414 045

ENGINEERS

 

LIENT: CLIENT NAME HERE PTY L

 

COUNTRY CLUB VILLAGES

NOOSA DOMAIN
APARTMENTS

WALTER HAY DRIVE,
NOOSAVILLE.

SCALE:

COPYRIGHT © 2017 JFP URBAN CONSULTANTS PTY LTD. THIS DOCUMENT MAY NOT BE COPIED OR TRANSMITTED IN ANY
FORM OR BY ANY MEANS IN PART OR IN WHOLE WITHOUT THE WRITTEN CONSENT OF JFP URBAN CONSULTANTS PTY LTD.

ee

COVER SHEET
SCHEDULE

 

 

PLAN NUMBER: B3730LA1-DA1 LA VM

M1717L_A1 CS02C

 

Log in to download the original (M1717 OPW Landscaping GIA OPW12-0110 01 pdf.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.