• A water truck or spray apparatus is to be provided on site when required
• Exposed areas such as cleared areas and stockpiles are to be watered and kept
damp in order to minimise erosion or the potential for dust creation.
• Vehicle speed is to be limited on site to minimise dust generation.
• Trucks entering or exiting the site shall have their loads covered
• All construction vehicles exiting site shall pass through a wheel wash down and/or
drive over a shake down grid which will be located at the site entry /exit.
• Haulage routes shall avoid residential areas and use sealed roads where possible.
• Machinery shall be fitted dust filters all equipment and vehicles are to meet relevant
emission standards.
• Maintenance of wind breaks and barriers where possible.
• Stockpiles heights are to be kept to manageable heights for dust and erosion control
purposes
• Protection of long term soil stock piles with revegetation, watering/moisture or hydro
mulching where practicable revegetate as soon as possible following construction.
5.4 Stormwater and Sediment Control
A stormwater and sediment control plan will be implemented prior to works commencing. A
Sediment and Erosion Control Layout Plan has been prepared by TOD’s Engineering (Sheet 11)
as is enclosed within Attachment A.
This will ensure that stormwater from the development does not enter adjoining properties,
and that all water that enters the council stormwater system does not contain silt or other
contaminants.
Excavation – At the commencement of these works, screens and bunding at the perimeter of
the site where stormwater may run off will be installed. Bunding will also be implemented
around stormwater drains. Diligent housekeeping will be implemented to minimise risk of
dust/debris being washed into pits.
Construction – Drainage pits will be bunded or have filter cloth applied to ensure debris and
silt does not enter the council’s drains.
5.5 Waste Management Plan
A Waste Management Plan will be submitted to Council for approval with the Final
Construction Management Plan at the Pre-Start Meeting.
RG Strategic Construction Management Plan 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Avocet Pde OPW - App C CMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.2 MB (small file)
- File type
No other editions are linked here.