2.   Introduction

2.1 Purpose

       This Construction Management Plan has been documented to describe how the Project
       Management team shall implement and conduct its allocated site management
       responsibilities during the Construction phase of “Multiple Dwelling Units (4 Units)” (the Project).
       A fundamental aim of this Plan is to ensure all construction is properly facilitated, integrated
       and coordinated to deliver certainty to the objectives of the Project.

2.2 Scope of this Plan

       This Plan provides a holistic approach that:

          • advises how the project management team will comply with the requirements of the
               contract relating to construction;

          • defines the project objectives and targets of particular relevance to the construction
               phase;

          • describes constraints specific to the construction phase and the project in general;

          • describes the process for the identification and control of risks specific to the
               construction phase; and

          • details the proposed strategy for the construction phase, with particular regard to
               establishment resourcing, site organisation and construction controls.

2.3 Proposed Works

       The proposed works require the construction of:

          • Ground & Level 1 – Removal of one (1) Unit and existing pool, renovation work to create
               Units 1 to 3 including new Carparking for Units and Visitor Parking and new pool located
               to Unit 1 – refer to Plan A200 as prepared by Zest Building Design Noosa,

          • Level 2 – new Unit 4 and upper level to Unit 1 - refer to Plan 200, and

          • Landscaping, and

          • Road frontage works – see Tod Engineering Plans 20538 C04 Pages 1-11.

       This type of construction will have distinct phases that will require different material handling
       strategies to optimise the construction works and minimise impact to surrounding streets, and
       neighbours. Our material handling strategies and construction planning will be consulted with
       stakeholders and authorities before implementation.

2.4 Site Location

       The proposed development site (refer Figure 1) has direct access from Avocet Parade.



RG Strategic                               Construction Management Plan                                  3

Used in these records

About this file

File size
1.2 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Avocet Pde OPW - App C CMP.pdf · 1.2 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.